Skip to main content

Report: schedule indicates Carlton Avenue Bridge delayed, but could meet arena opening date thanks to overtime; ESDC says "mitigation plan" reference incorrect; arena still on schedule for September 5; transit connection slips to mid-August

The Carlton Avenue Bridge is still scheduled to be completed on 10/3/12, five days after the first event at the Barclays Center, but, according to a report from the construction monitor for the arena bond trustee, Forest City Ratner is paying overtime to meet the completion date, and also has asked the city Department of Transportation for the OK to open the bridge with temporary street lighting and railing.

The report, dated 6/4/12 and based on a site visit 4/26/12 and a later document review, was issued by Merritt & Harris, which reports to the bond trustee, developer Forest City Ratner, and the Empire State Development Corporation.

The report also states, "Nevertheless, the Empire State Development (ESD) has requested that FCRC propose a mitigation plan to control and alleviate the traffic flow congestion for the first event at the arena, scheduled for September 28, 2012."

Is that so? Arana Hankin, Director, Atlantic Yards Project, ESD, told me the report was wrong. Merritt & Harris, she suggested, might be referring to the Transportation Demand Management plan (TDM) developed by Forest City.

Then again, the TDM plan refers to arena activities in general, not "the first event at the arena."

I queried Forest City Ratner spokesman Joe DePlasco, who also did not confirm the Merritt & Harris account. "As the report indicates we remain confident that we can meet the opening date and are looking at some temporary measures too to ensure that the bridge is operational when the arena opens," he stated. "We will be developing event specific traffic and transportation plans for every event."

Forest City is contractually obligated to ensure that the bridge is open before the arena opens, but the penalty is rather toothless: freezing of the developer's rights to move forward on any new residential development--which is already delayed.

Arena schedule

The report, after finally analyzing an ultimately not-so-mysterious GMP2 [Guaranteed Maximum Price], indicates that the arena remains on schedule for a substantial completion of 9/5/12, providing some 23 days to test the building before it opens.

The final completion date remains 6/30/13.

Transit Connection

The adjacent Transit Connection, once supposed to be finished by 4/2/12, is now scheduled for 7/14/12--though the monitor suggests that "a mid-August completion date is more realistic."

Given that the Transit Connection will open in conjunction with the Arena--why not open it somewhat earlier--the report says the slippage "will have no impact on the overall project schedule."

The reason for slippage is said to be "early delays," but, as I've written, the early delays were overcome.

Number of workers down

According to the report, there were 490 people working on the arena and 48 working on the Transit Connection, a decrease attributed to the "substantial completion of the steel work."

That's a decrease from the previous report, which counted 520 and 62 workers respectively, and likely the one before that. Note that Merritt & Harris does not count workers at the separate railyard project.

Reserves exceeded

Given additional costs, including for interior finishes, equipment upgrades, the building facade, and facade lighting, costs have increased, drawing down existing contingency reserves, requiring Forest City Ratner to put up another $30 million.

Deficiencies with exterior steel being fixed

Several deficiencies in the exterior were identified in the report two months ago, and are being remedied.

Schedule: arena

The schedule is based on comparing the amount of money spent to the amount projected. It appears that the arena is ahead of schedule, but that required extending the schedule so that projections would be spread over a longer time period.


Schedule: transit connection

The transit connection schedule has also been tweaked. For example, an earlier version of this chart indicated that, by August 2011, actual spending began to hit parity with projected spending, and then dip.

More photos: courtside club, new curbing

The report also includes photos, as indicated below, of work in progress.


Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

Click on graphic to enlarge. This is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change, and the project is already well behind that tentative timetable.


Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…