Vanderbilt Yard delay well less than that of East Side Access, now due in 2023

Hey, remember East Side Access, Long Island Rail Road service to Grand Central Station in Midtown East (as opposed to Penn Station in Midtown West)? It was once supposed to begin in 2016, which meant that delays in the revamped Vanderbilt Yard, which would enhance shuttle service between Jamaica and Brooklyn, could have been problematic. The new Vanderbilt Yard has been delayed numerous times, but is now almost finished . Forest City Ratner in 2005 agreed to build a nine-track yard that can accommodate 76 train cars but, with the 2009  renegotiation , got the Metropolitan Transportation Authority (MTA) to agree to a seven-track yard holding 56 cars. East Side Access is even more delayed. As the Daily News reported 9/19/19, in  MTA seeks another $798 million to finish East Side Access project long plagued by delays and rising costs , the completion date is now projected as 2022, 13 years behind the original schedule, while the $11.1 billion estimated cost is $6.8 bil...

Flashback: Forest City executive swore the temporary railyard was complete, but LIRR confirmed later completion

The two mantras I stressed to understand Atlantic Yards/Pacific Park were "It's a never-say-never project" and "The devil's in the details." Yesterday I wrote about another important one: "It's a very tight fit." Today let's consider the other two : "The culture of cheating" and "Power defines reality." Those serve as a reminder that Atlantic Yards/Pacific Park has never been honestly and fairly presented. The lack of information we have today--what exactly is the project schedule?--confirms that. A historical question But let's look back at the answer to a seemingly bureaucratic question that I've been trying to pin down: when was the temporary railyard finished? Remember, the functions of the Vanderbilt Yard, used to store and service Long Island Rail Road trains, were moved temporarily to another section of the railyard to enable the construction of the Barclays Center, which overlaps part of the...

Plans for shuttle service between Jamaica and Atlantic Terminal emerge (2021-22)

Hey, remember one of the reasons for the Vanderbilt Yard upgrade? It's supposed to help fuel Long Island Rail Road shuttle service between the hub in Jamaica and Atlantic Terminal in Brooklyn. And the delays in finishing the upgraded yard--finally due this year--have been less damaging because plans for the upgraded LIRR service have been delayed as well. Newsday, in a 3/25/19 article headlined  New amenities coming to Jamaica station, but it might be bad marriage for Brooklyn , reported: A $380 million effort to unclog and modernize the Long Island Rail Road’s hectic Jamaica station will bring new amenities, track infrastructure, and even an additional platform for riders, but also could complicate the travels of tens of thousands of Brooklyn-bound commuters. Although the long-discussed Jamaica Capacity Improvements project, or “JCI” as its known, promises several upgrades needed to handle the booming demand at the 106-year-old station, one key aspect of the effort — the cons...

As Nassau Coliseum reopens for NHL hockey, thanks to Cuomo contribution, a lingering question about who pays for key Belmont upgrade

The Nassau Coliseum has a re-do for major league hockey, as Newsday explains here and here : The Islanders on Saturday will play Columbus in the first of 21 games this season at the Coliseum, and the first of at least 60 in the next three years before their new arena at Belmont Park is ready. New York State contributed $6 million to make sure the Coliseum arena fits NHL specifications, while the Islanders chipped in $4 million. Additions include new locker rooms, and investments in dehumidification and ice plant redundancy — the NHL requires teams to have both the ability to maintain the ice, and a backup in case the primary ice plant goes down. There are also updates to the arena’s broadcast capabilities, with two new cameras pointed at center ice. Yes, that's $6 million of public funds that Gov. Andrew Cuomo decided to put in to help both the Islanders and BSE Global, which operates the Coliseum and the Barclays Center, and has been eager--maybe desperate--to move games out of...

Belmont Park environmental review: ESD studying LIRR service for arena events only, no analysis of cost and source of funding

Newsday's Randi Marshall, in a column 8/29/14, found a key twist in the saga of the planned arena at Belmont Park, built by a consortium including owners of the New York Islanders: Responding to questions about the potential expansion of Long Island Rail Road service at Belmont, the state’s development agency offered this bureaucratese: “. . . While there have been discussions regarding the provision of additional LIRR service for the retail village during off-peak periods during times with no arena events, the transportation analyses in the DEIS [the draft environmental impact statement] will conservatively assess future conditions with additional LIRR service provided to Belmont Park station for arena events only.” Translation: Empire State Development will study providing extra service only during New York Islanders games, concerts, and other events at the new arena. However, Marshall inquired, and was told that officials at ESD said there is ongoing discussion about year-...

Starting July 9, traffic changes near Vanderbilt and Atlantic avenues, lasting five weeks

According to a Community Notice circulated by the developer of Atlantic Yards/Pacific Park, a second phase of construction for the Vanderbilt Yard's East Portal, beginning Monday, July 9, will have several impacts, for some five weeks: the west and south crosswalks at Vanderbilt and Atlantic avenues will be closed the north crosswalk at Vanderbilt Avenue and Pacific Street will be closed the westbound B45 bus stop on Atlantic Avenue has been moved from the northwest corner of Vanderbilt Avenue to the northwest corner of Clermont Avenue no turns will be permitted from Atlantic Avenue to southbound Vanderbilt Avenue, so vehicles will be directed to detour down Washington Avenue and then Pacific Street

Newsday on Belmont arena: yes, 2021 best-case scenario; unspecified state funds will support full-time LIRR service

A recent Newsday article by Jim Baumbach, Analysis: Islanders’ Belmont arena expected to take 3 years to open , concludes that the planned Belmont arena likely won't open before the 2021 hockey season. Indeed, I  wrote that  earlier, relying, as did Baumbach, on statements at a 12/21/17 board meeting of Empire State Development (ESD). What Baumbach added notably were comments from Islanders’ c-owner Jon Ledecky on WFAN regarding full-time rail road service: “There’s money in the budget according to the governor and his people,” Ledecky said. “We have to make sure that money gets spent and that station becomes a vital part of the community, not just when there is horse racing and not just when there is a concert or a game. All the time, 365 [days a year], 24 hours a day.” That number is not specified, and state and Long Island Rail Road officials wouldn't add details Unmentioned by Newsday: as I reported, the state hasn't done a market study regarding the arena'...

Late notice: overnight work starts tonight near Sixth/Atlantic, part of West Portal construction

A message from Pacific Park Brooklyn indicates late night and weekend work beginning during the overnight hours tonight, near the intersection of Sixth Avenue and Atlantic Avenue. "As part [of] Long Island Railroad West Portal construction for Pacific Park Brooklyn contractors will be working during the overnight hours" through 5 pm Sunday, "demolishing portions of a suspended electrical duct bank." The West Portal is a new entrance from the Vanderbilt Yard to the Atlantic Terminal railway hub. The notice states that "Localized directional lighting will be used and all construction equipment meets environmental project requirements regarding noise." That doesn't mean it will be quiet. The notice says that "Coordination with LIRR schedules require that his work take place during this time," which is plausible. Less plausible is that it was not announced in the two-week Construction Update circulated last Friday . For information/concer...

MTA: Jamaica Center upgrade part of East Side Access and better Atlantic Terminal service (by 2022); leaves slack for Vanderbilt Yard delay

Long Island-based attendees of Barclays Center events, who are most notably New York Islanders fans, will ultimately get a boost from an upgrade to Jamaica station and the implementation of East Side Access, a plan to bring Long Island Rail Road trains to Grand Central Terminal. The MTA on 9/21/16 announced, among other things $64.9 Million Contract Award to Improve Jamaica Station : The new platform and tracks at Jamaica station will allow the LIRR to more easily re-route trains, take tracks out of service and support supplemental train service to and from Atlantic Terminal for customers attending games and events at the Barclays Center . The new platform will also feature glass-enclosed, heated waiting areas, as well as Wi-Fi and USB charging stations allowing customers to stay connected and charge their phones while they wait for the train. In addition, New York-based artist James Little will create brightly colored art glass installations on the station’s westerly bridge, an...