Two views of Block 1129: in one, two towers progress toward completion. In another, perspective on the missing platform.

When I did a walk Aug. 5 around the arena block, I took two photos of Block 1129, the southeast block of the project, where B12 & B13 (615 Dean St. & 595 Dean St.) have topped out and are nearly fully enclosed, headed for a mid-2023 opening.  The block is bounded by Dean and Pacific streets, and Sixth and Carlton Avenues. But it all depends on perspective. The first photo below, taken from Carlton Avenue south of Atlantic Avenue, shows the four towers--including the already completed B11 (550 Vanderbilt Ave., far left) and B14 (535 Carlton Ave., far right)--without much perspective on what's left to do. Photos: Aug. 5, 2022 The second photo, looking east over the MTA's Vanderbilt Yard, shows the towers only fractionally. The railyard block is bounded by Atlantic Avenue and Pacific Streets, and Sixth and Carlton Avenues. A large and expensive platform must be built to support three towers (B8/B9/B10), and that's the second phase of a two-phase project that hasn't...

As B12 & B13 start looms, no info about affordability (middle-income?); Chelsea Piers still involved ("storage" was placeholder); dubious exchange on expanded parking

This is the third of three posts on the 7/21/20 Quality of Life meeting , sponsored by Empire State Development (ESD). The first concerned construction progress and open issues. The second concerned Barclays Center issues. The B12 and B13 towers at the southeast block of the site have not actually started, TF Cornerstone's Amir Stein said at the meeting, though a construction fence has been installed. "We're working on final coordination with city agencies." Once construction starts, it should take one year to build the foundation, part of a three-year total buildout. The towers will be built simultaneously. There may be off-hour deliveries of construction equipment in coming weeks, he said. He said the first five months, drilling piles, should be the noisiest, follwed by seven months of concrete pouring. Then eight months of superstructure. After that, general construction, including interior work. He said there "likely will have to be night and week...

Looking at southeast block parking: potential bottleneck at single Dean Street garage entrance for 758 cars, and 5 cars/minute (?) at peak hour

This is the third of eight posts regarding the 1/28/20 Atlantic Yards/Pacific Park Quality of Life meeting . The first regarded delays in B12/B13, the platform, and Site 5. The second concerned progress at B4, B15, and the railyard. The fourth concerned impacts from Barclays Center operations. The fifth concerned the Community Liaison Office, and impacts from workers. The sixth concerned the next Atlantic Yards Community Development Corporation meeting. The seventh concerned questions for the Department of Transportation. The eighth concerned DEP digging. Block 1129 garages, Reduced Parking Alternative; Saturday 1-2 pm pre-game; 910 total spaces The issue of parking on Block 1129, the southeast block of the 22-acre site , first raised at the previous Quality of Life meeting last November, remains confounding. The bottom line: though the state studied the impact of far more cars using a three-entrance parking garage on the block, it never studied the impact of a larger n...

Belated notice: for two years, a 16-foot fence plus sidewalk closings at Block 1129 to accommodate construction

Late yesterday afternoon, the developers of Atlantic Yards/Pacific Park Brooklyn sent a Community Notice indicating major changes would begin next Thursday, lasting two years, to accommodate construction on the southeast block of the project site, including a 16-foot high fence aimed to dampen noise and the closing of sidewalks around the perimeter of the site. The notice was headed, not inaccurately but somewhat incompletely, "Temporary Changes to the Roadway Network on Carlton Avenue, Vanderbilt Avenue, and Dean Street." None of the changes were hinted in the two-week Construction Alert sent this past Monday. Note that, while the next tower to start, at 535 Carlton Avenue (the southwest corner of the block), is supposed to open in the fall of 2016, according to a fact sheet distributed by the New York City Housing Development Corporation, the text of the notice states that the "fence around the entire block will remain in place for approximately 24 months." ...