Atlantic Yards/Pacific Park FAQ, timeline, and infographics (pinned post)

Construction union advocates need a better example than Atlantic Yards to highlight less costly development projects

An article in THE CITY today, by contributor (and former Crain's New York Business editor and columnist, if you're wondering about any slant) Greg David,  Can Mamdani Make Union-Built Affordable Housing Add Up? , notes that Democratic mayoral nominee Zohran Mamdani has avoided weighing in on three controversial ballot proposals because he doesn't want to tangle with construction unions, which oppose them. The issues are nuanced and complicated--I'll point to more of the debate in a separate post--but it is true that union labor pays higher wages, and union advocates would like the City Council to retain power, in part to ensure a union presence. Do higher wages make projects more costly? One argument for union labor is that it's higher quality, thus enabling faster, more effective construction. Here's the argument ventilated in the article, though: Anyone claiming that higher priced union workers makes the projects too costly is “a lying silly goose,” said Kevin...

OK, this time they really mean to start combined sewer installation and water main replacement on Dean Street between Sixth and Vanderbilt avenues

One year ago, I reported ( link ) that work on the long-delayed "Pacific Park Project Phase II – Combined Sewer Installation and Water Main Replacement on Dean Street between 6th Avenue and Vanderbilt Avenue" was expected to ramp up in Spring 2024 and take until November 2025. That didn't happen, and it's not starting until next year. (The work was supposed to start on October 24, 2022, according to an  announcement  posted by Brooklyn Community Board 8. According to a May 2022  presentation  by the Department of Design and Construction (DDC), the project was supposed to take 36 months.) The update So credit Kaya Laterman of the BK Reader for her Dec. 18 article,  Delayed by More Than a Year, Will a Brooklyn Infrastructure Upgrade Ever Get Done? The project, she noted, was 15 months behind schedule, given multiple parties at odds: When DeBoe Construction, the general contractor that won the bid for the Dean Street project, sent its crew to start work in April 20...

From the latest Construction Update: nothing's happening, so delayed info delivery not crucial

On Friday, March 8, at 4:35 pm, those on Empire State Development's (ESD) email list for Atlantic Yards/Pacific Park got an email stating: Attached for your information is the March 4, 2024 and March 11, 2024 Atlantic Yards Project construction activity update. As a reminder, please be advised that construction alert emails will be sent once a month until there is a change in construction activity. Bi-weekly construction alerts will continue to update on the Atlantic Yards website: https://esd.ny.gov/atlantic-yards-community-development-corporation-1 . Note that a document that was supposed to be delivered before the first of two work weeks began was instead delivered at the end of that first work week. Then again, since nothing's happening, such slacking is not particularly irresponsible. I was on vacation when I got the document. Had it disclosed anything important, I would have written about it promptly. Instead, I slacked, too. What is pending: the school That said, ESD, th...

The latest Construction Update (nothing happening) and a small footnote re Empire State Development

It's no big deal, but it's worth nothing that two versions of the same Construction Update email were sent yesterday to recipients of Atlantic Yards/Pacific Park updates on the mailing list maintained by Empire State Development (ESD), the state authority that oversees/shepherds the project. The text of the email: Attached for your information is the February 5, 2024, and February 12, 2024 Atlantic Yards Project construction activity update. As a reminder, please be advised that construction alert emails will be sent once a month until there is a change in construction activity. Bi-weekly construction alerts will continue to update on the Atlantic Yards website As stated in the document (bottom), regarding the future platform over the MTA's Vanderbilt Yard, "There are no construction activities scheduled for the reporting period." And that means, without the platform, no tower construction. Who's behind it? The email was attributed to ESD's Atlantic Yards ...

Checking on the latest (non)-Construction Update. It's online only. Plus a clarification: ESD says 876 affordable units to go. Super's unit counts.

According to the Atlantic Yards page ( link ) from Empire State Development (ESD), the state auithority that oversees the project, there's no construction scheduled. Duh. What's new is that, though they continue to produce the updates bi-weekly, they're emailing them only monthly, at least until construction resumes. New info on affordable units Also, I belatedly noticed a change in the page's official description of the project, one that has been in place since at least October , according to the Internet Archive. The second paragraph in the official description has been updated: The Atlantic Yards Project The Atlantic Yards Project is a 22-acre, $4.9 billion project, that consists of the 18,000-seat Barclays Arena; the development of a reconfigured and improved LIRR train yard and subway facility upgrades; the development of 16 buildings for residential and commercial uses, including up to 6,430 apartments, of which 2,250 will be affordable to low, moderate and middle...

Latest (non-) Construction Update: nothing to report, so alerts now monthly. Shouldn't ESD discuss the requested financial analysis & pending foreclosure sale?

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning Monday, Nov. 27 was circulated Monday, Dec. 4 at 9:52 am (way late) by email by Empire State Development (ESD), the state authority that oversees/shepherds the project. As with the Update two weeks earlier , there's nothing new to report. There are no construction activities planned for the platform needed for construction over the railyard. Each of two platform blocks would support three towers. The ESD stated in the cover email: Please be advised that construction alert emails will be moved to monthly alerts until there is a change in construction activity. Biweekly construction alerts will continue to update on the Atlantic Yards website. What about the project's future? Big questions about the project's future loom. As I  reported , while the advisory Atlantic Yards Community Development Corporation on Aug. 2 requested that the parent ESD prepare, by Oct. 3. a financia...

From the latest (non-) Construction Update: the platform's on hold, & there's nothing to report. What about the requested financial analysis?

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning Monday, Nov. 13, was circulated yesterday at 1:51 pm (lead time) by email by Empire State Development (ESD), the state authority that oversees/shepherds the project. As with the Update  two weeks ago , there's nothing new to report. There are no construction activities planned for the platform needed for construction over the railyard. Each of two platform blocks would support three towers. That depends on, as I  wrote  in August, a tax deal to bring back the savings from the 421-a tax break as well as adherence to--or a renegotiation of--the May 2025 deadline for the project's affordable housing. Some 876 (or 877) units remain to be built.  Further transparency? I had predicted (wrongly) two weeks ago that it's possible that ESD will no longer circulate these updates, which are historically prepared by the project's developer(s). That said, construction of the schoo...

From the latest (non-) Construction Update: no new work, but open space outside 595 Dean should be finished, with completion of East Courtyard work

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning  Monday, Oct. 16, was circulated Friday at 9:57 pm (lead time) by email by Empire State Development (ESD), the state authority that oversees/shepherds the project. As with the Update  two weeks ago , there's no major construction activity, but, at the B12/B13 towers (595 Dean), "East Courtyard Work is expected to be completed for the upcoming reporting period." That means the open space would finally be finished, though the buildings have been open for months--albeit not for the  "affordable" units . Baseline competency The document notes that weekday work hours are 7 am-6 pm and adds "Saturday work is not currently scheduled during this reporting period." That clarification is a reminder that, for many months, the Updates had misleadingly suggested after-hours work might continue and also suggested that platform work might start. I'd note that ESD...

From the latest (non-) Construction Update: again, no new work, just continued open space work in fountain area at 595 Dean

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning  Monday, Oct. 2, was circulated yesterday at 12:03 pm (lead time) by email by Empire State Development (ESD), the state authority that oversees/shepherds the project. As with the Update  two weeks ago ., there's no major construction activity, but, at the B12/B13 towers (595 Dean), "East Courtyard Work ongoing for the fountain area." That's incremental progress from the previous alert, which said work "remains to be completed pending final delivery of materials."  Indeed, the open space isn't yet done, though the buildings have been open for months--albeit not for the  "affordable" units . Baseline competency The document notes that weekday work hours are 7 am-6 pm and adds "Saturday work is not currently scheduled during this reporting period." That clarification is a reminder that, for many months, the Updates had misleadingly sugge...

From the latest (non-) Construction Update: again, no new work, just continued open space work at 595 Dean

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning  Monday, Sept. 18, was circulated yesterday at 10:22 am (lead time) by email by Empire State Development (ESD), the state authority that oversees/shepherds the project. As with the Update two weeks ago ., there's no major construction activity, but, again, at the B12/B13 towers (595 Dean), "East Courtyard Work remains to be completed pending final delivery of materials."  Indeed, the open space isn't yet done, though the buildings have been open for months--albeit not for the  "affordable" units . Baseline competency The document notes that weekday work hours are 7 am-6 pm and adds "Saturday work is not currently scheduled during this reporting period." That clarification is a reminder that, for many months, the Updates had misleadingly suggested after-hours work might continue and also suggested that platform work might start. I'd note that ES...

From the latest (non-) Construction Update: no new work, just continued open space work at 595 Dean

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning  Monday, Sept. 4, was circulated yesterday at 9:04 am (lead time) by email by Empire State Development (ESD), the state authority that oversees/shepherds the project. There's no major construction activity, but, at the B12/B13 towers (595 Dean), "East Courtyard Work remains to be completed pending final delivery of materials."  Indeed, the open space isn't yet done, though the buildings have been open for months--albeit not for the  "affordable" units . Baseline competency The document notes that weekday work hours are 7 am-6 pm and adds "Saturday work is not currently scheduled during this reporting period." That clarification is a reminder that, for many months, the Updates had misleadingly suggested after-hours work might continue. As with the Update two weeks ago, as I wrote , it's a return to minimal competency, with no obvious errors, a d...

From the latest (non-) Construction Update: no new work, but at least ESD displays baseline competency by circulating document, eliminating errors.

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning  Monday, Aug. 21 was circulated yesterday at 11:55 am (lead time) by email by Empire State Development (ESD), the state authority that oversees/shepherds the project. There's no major construction activity, but, at the B12/B13 towers (595 Dean) "Courtyard Work remains to be completed pending final delivery of materials." Indeed, the open space isn't yet done, though the buildings have been open for months--albeit not for the "affordable" units . Baseline competency That said, this document suggests a return to baseline competency by ESD and/or the preparer of the document. (The document has traditionally been prepared by the master developer, long Greenland Forest City Partners, now operating as Pacific Park Development LLC.) First, the document was circulated by email, with lead time, as had long been the practice--though for several weeks it wasn't cir...

From the latest (non-) Construction Update: no new work, but work continues in open space at 595 Dean, on southeast block

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning  Monday, Aug. 7, has  not  (yet) been circulated by email, as it should have been by Empire State Development (ESD), the state authority that oversees/shepherds the project. Update : it was circulated by Monday at 9:48 am, a bit late.  But it was available Friday (lead time) at ESD's  Atlantic Yards page , as shown in the screenshot below. Perplexingly, ESD does not see fit to list previous updates.  (The document has traditionally been prepared by the master developer, long Greenland Forest City Partners, but operating as Pacific Park Development LLC.) Reason for confusion Perplexingly, after two two-week periods ( June 12 ,  June 26 ) in which ESD claimed that there were no new construction activities for the coming two weeks and thus didn't circulate a document, it has three times essentially issued a duplicate of the May 29 document, again with no ...

From the latest (non-) Construction Update: document again repeats from late May, with no new information (but still that hint about the platform).

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning yesterday, Monday, July 24, has  not  been circulated by email, as it should have been by Empire State Development (ESD), the state authority that oversees/shepherds the project. But I did notice it yesterday, after it should've been circulated, at ESD's  Atlantic Yards page . (The document has traditionally been prepared by the master developer, long Greenland Forest City Partners, but operating as Pacific Park Development LLC.) Reason for confusion Perplexingly, after two two-week periods ( June 12 ,  June 26 ) in which ESD claimed that there were no new construction activities for the coming two weeks and thus didn't circulate a document, it has twice essentially issued a duplicate of the May 29 document, again with no new activities. As with two weeks ago , while it states that there are no construction activities for the platform, long planned to be built over t...

From the latest Construction Update: after hiatus, document repeats from late May, with no new information (but still that hint about the platform).

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning Monday, July 10, has  not  been circulated by email, as it should have been by Empire State Development (ESD), the state authority that oversees/shepherds the project. But I did notice it yesterday, well after it should've been circulated, at ESD's  Atlantic Yards page . (I checked around 8:15 am and didn't see it, and then saw it when I checked in the evening. The document has traditionally been prepared by the master developer, long Greenland Forest City Partners, but operating as Pacific Park Development LLC.) Reason for confusion Perplexingly, after two two-week periods ( June 12 ,  June 26 ) in which ESD claimed that there were no new construction activities for the coming two weeks and thus didn't circulate a document, it has essentially issued a duplicate of the May 29 document, again with no new activities. Again, while it states that there are no constructio...

From the latest Construction (non-) Update: again, nothing new, not even a document.

As I wrote June 10, for the first time in memory, Empire State Development (ESD), the state authority that oversees/shepherds Atlantic Yards/Pacific Park, neglected to circulate to those on its mailing list a bi-weekly Construction Update that indicates construction activity--at least by the developers involved--at the site. Instead, the ESD's website stated that there were no new construction activities for the two weeks beginning June 12. Similarly, the  website  now states there are no new construction activities for the two weeks beginning tomorrow, June 26. As I previously wrote, some work is ongoing, notably the construction of a middle school at the B15 site, 662 Pacific Street. But because it's not a developer responsibility, it's not part of that two-week documentation.

From the latest Construction (non-) Update: nothing new, not even a document. But surely some work is being completed. And the school's still coming.

OK, every two weeks, Empire State Development (ESD), the state authority that oversees/shepherds Atlantic Yards/Pacific Park, is supposed to circulate to those on its mailing list a Construction Update that indicates construction activity--at least by the developers involved--at the site. Two weeks ago, oddly enough, ESD did not circulate the document but rather posted it online. There were seeming errors in it--phrasing that, despite all evidence to the contrary, suggested that some work that's part of platform construction was imminent--so it seemed careless. Similarly, the document continued to say, despite clear evidence (via the Department of Buildings) to the contrary, that after-hours work was continuing at the 595 Dean (B12/B13) site. As I wrote, no one proofreads the documents. Such documents have traditionally been prepared by the master developer, now Greenland Forest City Partners. But it's possible that the document is updated with the participation of TF Cornerst...

From the latest Construction Update: continued work at the 595 Dean site. No platform work planned, but odd (sloppy?) mention of future suspension of bus service.

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning Monday, May 29 (though a holiday), has not been circulated by email yet by Empire State Development (ESD) after preparation (presumably) by master developer Greenland Forest City Partners. But I did notice it yesterday--maybe it was there earlier--at ESD's Atlantic Yards page . Again there's little change, compared with the  previous update , though there is something odd. The previous document simply said, regarding Block 1120, the crucial first block of the Vanderbilt Yard, where a platform would support three towers, "There are no construction activities scheduled for the reporting period." (The block is bounded by Sixth and Carlton avenues, and Pacific Street and Atlantic Avenue.) The latest update repeats that, but goes on to add phrasing that was previously part of the Updates when the platform work was teased,  starting in May 2022 : The MTA B45 bus stop at A...

From the latest Construction Update: not much new, but on southeast block, completion work at 595 Dean towers continues, as does plaza work outside

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning Monday, May 15, was circulated at 2:16 pm yesterday (lead time) by Empire State Development (ESD) after preparation (presumably) by Greenland Forest City Partners (GFCP), which is dominated by Greenland USA. Again there's little change, compared with the  previous update , though the document again confirms that there are no construction activities planned for the crucial first block of the platform over the Vanderbilt Yard, which would support three towers. Remember: such work had been teased as  starting last May , but a in March they finally confirmed it wasn't happening.  That suggests that Greenland USA, having  lost  its Atlantic Yards/Pacific Park point man (with no replacement) and with no chance of meeting the May 2025 affordable housing deadline, with at least 876 units due, is renegotiating and reconsidering the project. They don't want to pay t...

From the latest Construction Update: not much new, but on southeast block, finishing touches on/around 595 Dean towers

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning Monday, May 1, was circulated at 10:59 am today (late!) by Empire State Development (ESD) after preparation (presumably) by Greenland Forest City Partners (GFCP), which is dominated by Greenland USA. Again there's little change, compared with the previous update , though the document again confirms that there are no construction activities planned for the crucial first block of the platform over the Vanderbilt Yard, which would support three towers. Remember: such work had been teased as  starting last May , but a month ago they finally confirmed it wasn't happening.  That suggests that Greenland USA, having  lost  its Atlantic Yards/Pacific Park point man (with no replacement) and with no chance of meeting the May 2025 affordable housing deadline, with at least 876 units due, is renegotiating and reconsidering the project. They don't want to pay the $2,000/mont...