Water and sewer work around project site now projected to start in fall, last 3 years. Aimed to support new buildings, which open next year. At least city agency will have onsite liaison.
The NYC Department of Design and Construction (DDC) last night made a presentation to Brooklyn Community Board 8's Environment, Sanitation and Transportation Committee on what's called Pacific Park Project Phase I, involving a combined sewer installation and water main replacement, expected to start this fall and last three years. (I first wrote about it last month.) Some key details were scarce, but it seemed clear that work along Dean Street between Carlton and Vanderbilt avenues, and then up Dean one block and Vanderbilt up two blocks, would intersect with, and impact, construction in the neighborhood. Though one reason for the project is to support newly constructed buildings, it won't be completed until well after the B12 and B13 towers (615 Dean/595 Dean) open in mid-2023, raising questions about why it didn't start sooner. ( Update : those buildings will rely on existing infrastructure installed by the developers; this new work will add support.) A DDC rep said ...