Atlantic Yards/Pacific Park FAQ, timeline, and infographics (pinned post)

Greenland USA point man Solish leaves for The Brodsky Organization, which built B15 tower & partnered on B4. What's next? Greenland renegotiation with NY State?

Greenland USA's longtime Pacific Park point man, Scott Solish, who began overseeing development and operations of the project in August 2014 and has faced increasingly tough questions about the project's future, has left for The Brodsky Organization , a family-owned real estate firm that bought one Atlantic Yards development site from Greenland to build a tower and partnered with Greenland to build another. "I'm incredibly proud of the progress and accomplishments realized at Pacific Park," Solish said in a statement in response to my inquiry, "and, although I am no longer involved, I look forward to seeing the next phases of the project be realized by my former colleagues and friends."  In Solish's 8.5 years, Atlantic Yards/Pacific Park's uneven progress included seven new towers, a new railyard for the Long Island Railyard, and plans announced--yet unrealized--for a crucial platform over that railyard to support six towers and deliver most of t...

At brief meeting, developer/ESD punt on big questions: affordable housing deadline, project completion, fines, payments.

This is the fourth of four articles about the July 12, 2022  Quality of Life meeting . I submitted several questions. Some got answers, as noted below, but the big ones got deflected or ignored by developer Greenland Forest City Partners (GFCP) or Empire State Development (ESD), the state authority that oversee/shepherds the project. Affordable housing obligation Does GFCP have a plan to  meet the May 2025 deadline  for affordable housing? Scott Solish of Greenland USA, which owns nearly all of GFCP, said it was the "same answer that we always have. We're moving ahead with our plans with the platform.... We are working on hitting all of our targets, as we always have." Except they haven't hit their targets--for example, they announced in 2019 that the platform would start in 2020.  If that deadline is not met, will ESD enforce the $2,000/month fines for each missing affordable unit? ESD's Tobi Jaiyesimi ignored that question. Project completion If GFCP aims to com...

What's coming at the Vanderbilt Yard? More columns needed to support roof, on first block, that will serve as platform for tower construction.

This is the seventh of ten articles on the 6/7/22 meeting of the Atlantic Yards Community Development Corporation. The  first  concerned the affordable housing timetable. The  second  assessed an estimated 2031 completion date. The  third  addressed the impact of a potential Greenland default. The  fourth  concerned expectations of 421-a benefits. The  fifth  concerned the deadline for the Urban Room. The  sixth  addressed timing for the school.  T he  eighth  discussed community impacts of construction.  The  ninth  concerned plans for B12/B12 affordable housing.  The  tenth  concerned the Open Meetings Law. Construction at the first of two blocks of the Metropolitan Transportation Authority's Vanderbilt Yard is expected to start on Monday, June 20, as has been announced . From presentation (at bottom) At the meeting, Scott Solish of Greenland USA, which owns nearly all of master de...

So, when will the project's middle-school arrive? Though developer claims ignorance and Empire State Development is silent, SCA (still) projects March 2025.

This is the sixth of ten articles on the 6/7/22 meeting of the Atlantic Yards Community Development Corporation. The  first  concerned the affordable housing timetable. The  second  assessed an estimated 2031 completion date. The  third  addressed the impact of a potential Greenland default. The  fourth  concerned expectations of 421-a benefits. The  fifth  concerned the deadline for the Urban Room.  The  seventh  concerned plans for the platform. The  eighth  discussed community impacts of construction.  The  ninth  concerned plans for B12/B12 affordable housing.  The  tenth  concerned the Open Meetings Law. So, 662 Pacific Street, aka B15, is open and its market-rate units fully-leased (though no word on leasing of income-targeted "affordable" units). The only additional construction, said Scott Solish of Greenland USA, is the buildout of the planned school, "being done by the SCA...

Will B5 tower qualify for 421-a benefits? Developer says yes, as deadline approaches. (Next two towers won't.) AY CDC would like confirmation from HPD.

This is the fourth of ten articles on the 6/7/22 meeting of the Atlantic Yards Community Development Corporation. The  first  concerned the affordable housing timetable. The  second  assessed an estimated 2031 completion date. The  third  addressed the impact of a potential Greenland default. The  fifth  concerned the deadline for the Urban Room. The  sixth  addressed timing for the school.  The  seventh  concerned plans for the platform. The  eighth  discussed community impacts of construction.  The  ninth  concerned plans for B12/B12 affordable housing.  The  tenth  concerned the Open Meetings Law. During his slide presentation , Scott Solish of Greenland USA pointed to the location for the first phase (of two) of platform development: Block 1120 of the Vanderbilt Yard--from Sixth to Carlton avenues and Pacific Street to Atlantic Avenue. That will support three towers, the first of...

If Greenland USA's parent defaults, Development Agreement (as Veconi notes) suggests project stall. Company/ESD say: no worries.

This is the third of ten articles on the 6/7/22 meeting of the Atlantic Yards Community Development Corporation. The  first  concerned the affordable housing timetable. The  second  assessed an estimated 2031 completion date. The  fourth  concerned expectations of 421-a benefits. The  fifth  concerned the deadline for the Urban Room. The  sixth  addressed timing for the school.  The  seventh  concerned plans for the platform. The  eighth  discussed community impacts of construction.  The  ninth  concerned plans for B12/B12 affordable housing.  The  tenth  concerned the Open Meetings Law. While the Shanghai-based parent company of Greenland USA--which owns nearly all of master developer Greenland Forest City Partners (GFCP)--is struggling financially and seen its credit rating plummet, representatives of both the U.S. subsidiary and of Empire State Development (ESD), the state author...

Developer essentially admits the obvious: 2025 affordable housing deadline won't be met. Will they get a pass on fines?

This is the first of ten articles on the 6/7/22 meeting of the Atlantic Yards Community Development Corporation. The  second  assessed an estimated 2031 completion date. The  third  addressed the impact of a potential Greenland default. The  fourth  concerned expectations of 421-a benefits. The  fifth  concerned the deadline for the Urban Room. The  sixth  addressed timing for the school.  The  seventh  concerned plans for the platform. The  eighth  discussed community impacts of construction.   The  ninth  concerned plans for B12/B12 affordable housing.  The  tenth  concerned the Open Meetings Law. For the first time, a representative of master developer Greenland Forest City Partners (GFCP) essentially admitted the obvious: they have no plan to meet the  May 31, 2025 deadline  to deliver the required 2,250 units of affordable housing. That requires 876 (or 877, depen...

As construction starts for platform at first railyard block, pedestrian & traffic flow limited; parking truncated; questions about work hours, trucks, sanitation

The most important news, in my view , from last night's appearance of a Greenland USA executive at a meeting of the North Prospect Heights Association regarded the timetable for construction of the first phase of the platform, the first tower (B5), and the question marks over the remaining project. But Scott Solish was there to talk to the project's immediate neighbors about the significant changes to traffic and pedestrian flow from the establishment of construction fences around the perimeter of the first block of the MTA's Vanderbilt Yard, between Atlantic Avenue and Pacific Street, and Sixth and Carlton avenues. This could last three years. Both topics likely will be amplified at tonight's public, online  Quality of Life meeting , hosted at 6 pm by Empire State Development (ESD), the state authority that oversees/shepherds the project. Another close-up view of Block 1120 was also shown; see below Solish, the head of development for Greenland USA, noted he was approa...