From the latest Construction Update: after hiatus, document repeats from late May, with no new information (but still that hint about the platform).
The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning Monday, July 10, has not been circulated by email, as it should have been by Empire State Development (ESD), the state authority that oversees/shepherds the project.
But I did notice it yesterday, well after it should've been circulated, at ESD's Atlantic Yards page. (I checked around 8:15 am and didn't see it, and then saw it when I checked in the evening. The document has traditionally been prepared by the master developer, long Greenland Forest City Partners, but operating as Pacific Park Development LLC.)
Reason for confusion
Perplexingly, after two two-week periods (June 12, June 26) in which ESD claimed that there were no new construction activities for the coming two weeks and thus didn't circulate a document, it has essentially issued a duplicate of the May 29 document, again with no new activities.
Again, while it states that there are no construction activities for the platform, long planned to be built over the first railyard block, it again adds phrasing that was previously part of the Updates when the platform work was teased, starting in May 2022, including:
The MTA B45 bus stop at Atlantic and 6 Av. will be temporarily suspended during the platform construction period. The following active bus stop is at Carlton and Atlantic Avenues.That hints that the work might actually be starting, though no announcement has been made. Pacific Park Development LLC, dominated by Greenland USA, recently told ESD that work on the platform was likely to start in the second half of 2023, but no official announcement has emerged.
Protocols and facilities have been established to ensure an orderly, safe workplace by following LIRR requirements and permits Monday through Friday from 7:00 am until approximately 3:30 pm.
On the southeast block, work
The new document does not indicate new work at the B12/B13 site, 595 Dean Street, two towers said by developer TF Cornerstone to already be open.
While in the two previous two-week periods there was nothing to report, the new document does state that Mechanical, Plumbing, Fire Protection and Electrical punch list work is ongoing, as is LEED Commissioning and start-up of (unspecified) equipment. Punch list work for apartments continues.
Regarding after-hours work at the B12/B13 site, the document says there's a variance for work to start at 6 am on weekdays. No such variances for that time have been listed since mid-February, which suggests they're getting closer to completion.
Comments
Post a Comment