Skip to main content

Despite stop-work order, Atlantic Yards parking lot proceeds, as (per FCR) tanks have not been installed, only "placed"

Work done before stop-work order, via AY Watch
There's been a lot of work on the Atlantic Yards surface parking lot in the past week, despite a stop-work order regarding the installation of stormwater detention tanks, aimed to collect water so it doesn't overwhelm the sewer system.

Indeed, the installation on Block 1129--between Carlton and Vanderbilt avenues, and Dean and Pacific streets--looks fairly far along.

If so, it looks like Forest City Ratner's decision to start work on the installation without a permit to do so--it describes the tanks were "placed"-- has paid dividends.

After all, the Department of Buildings (DOB) says the developer's work these past few days was not out of compliance

Installation vs. placement

Work done after stop-work order, via AY Watch
As stated on Atlantic Yards Watch, regarding work done June 15, "Work that appears to be unapproved is taking place on block 1129. What appear to be retaining tanks for the detention system have been installed. Excavation has taken place. The detention system is shown as being 'disapproved' on the DOB website."

"Impactful work has taken place causing vibrations," the report continued. "A hoe ram has been used. Large stones have been dropped in containers. A selection of photos has been submitted to the Department of Buildings."

According to the Department of Buildings web site (screenshot below), a partial stop-work order was issued on June 15 and partly rescinded on June 18, but only to continue grading. However, the DOB also allows work intended to shore up safety, and that offers broad latitude.


FCR: tanks not installed

Forest City Ratner spokesman Joe DePlasco stated yesterday, "The tanks have not been installed (though they may have been placed in the holes)."

That depends, apparently, on what the word "install" actually means. The meaning encompasses both "to place in position" and to "connect for service or use."

From the DEP/DOB Guidelines
DePlasco was apparently using the latter definition, though I don't think that conforms to what the city typically requires, as explained below.

DePlasco added, "As you know, the stop work order was rescinded." (Not completely, as shown above.)

"Work has started on a fence and there’s some preparation work (excavation) on the tanks," he stated. "We anticipate doing the tanks next week."

"Our inspectors were at the site this morning and found that all work at the site was in compliance with the Stop Work Order," DOB spokeswoman Ryan FitzGibbon state yesterday. "Currently, Forest City Ratner is in the process of submitting the necessary paperwork to the Department to resume work on the retention tanks."

Asked to clarify, FitzGibbon stated, "The Stop Work Order was issued for the installation of retention tanks. However, safety work to make sure the tanks already placed at the site were secure was and is allowed. This includes backfilling around the tanks to secure them."

When should construction start?

From the DEP/DOB Guidelines
How and when should such tanks be installed?

The construction phase should come only after the Plan Examination and Approval by the Department of Buildings, according to a chart (above right) in the Guidelines for the Design and Construction of Stormwater Management Systems, developed by the New York City Department of Environmental Protection in consultation with the DOB.

Such approval had not been granted.

According to the 16-phase "Recommended Construction Sequencing" in the DEP/DOB Guidelines (left), excavation is #7, the installation of bedding stone is #10, and the installation of system components is #11.

It does not make a distinction between "install" and "place."

So the act of putting the components in the ground is fairly far along in the process, according to the sequencing. And that's already done, at least in  part, on Block 1129.

Comments

  1. Anonymous1:39 PM

    once again politics prevails and FCR will walk away with not even down time on their illegal parking lot.I hope the tanks do not leak and flood out the railroad grade below and adjoining.

    ReplyDelete

Post a Comment

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

This graphic, posted in November 2017, is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. Note the unbuilt B1 and the proposed shift in bulk to the unbuilt Site 5.

The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change. The project is already well behind that tentative timetable.

How many people are expected?

Atlantic Yards/Pacific Park has a projected 6,430 apartments housing 2.1 persons per unit (as per Chapter 4 of the 2006 Final Environmental Impact Statement), which would mean 13,503 new residents, with 1,890 among them in low-income affordable rentals, and 2,835 in moderate- and middle-income affordable rentals.

That leaves 8,778 people in market-rate rentals and condos, though let's call it 8,358 after subtracting 420 who may live in 200 promised below-market condos. So that's 5,145 in below-market units, though many of them won't be so cheap.

As…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Atlantic Yards/Pacific Park in 2017: no new towers, unfilled affordable units, Islanders prepare to leave, project timetable fuzzy

My 2018 preview.

It was another wait-and-see year for Atlantic Yards/Pacific Park, with one big twist--the beginning of a slow goodbye for the New York Islanders--but continued delays for towers, a lost (mostly) 421-a subsidy for condos, and new skepticism about unfilled not-so-affordable housing units.

So ongoing questions linger regarding the project's pace, affordability, and even future ownership.

In my 2017 preview, I predicted--not exactly going out on a limb--that two and likely three more towers would open, though it would be unclear how fast they'd lease up and sell.

Indeed, we've learned that the middle-income below-market units at 461 Dean (which opened in 2016) and 535 Carlton have leased very slowly, while it's too soon to assess progress for commensurate units at 38 Sixth. (At 535 Carlton and 38 Sixth, middle-income units make up half the "100% affordable" buildings.) Meanwhile, many apartments are up for rent at the 550 Vanderbilt condo buildin…