Skip to main content

Flashback: ESDC attorney once assured court that Forest City have "to bring the Project to completion by 2019, with sanctions imposed for any failure to do so"

Way back in January 2010, as the last major Atlantic Yards legal case faced its first hearing, I pointed to a key point of dispute. In retrospect appears to be either a glaring untruth or, more charitably, an incredibly misguided prediction about the state of New York's capacity to negotiate with Atlantic Yards developer Forest City Ratner.

It's worth another look. (Tomorrow I'll write about the legal battle over the appeal in the aftermath of the convoluted case.)

Timetable challenge

Two coalitions of civic groups had challenged the Empire State Development Corporation's (ESDC) September 2009 approval of the Modified General Project Plan (MGPP), asserting that the project could last some 22 years--because of the revision of the Vanderbilt Yard deal, allowing much slower payments--rather than the promised ten year.

The ESDC said no, and countered by pointing to a set of documents that, at the time of the November 2009 filing of legal papers, had not yet been signed. They were signed in December 2009, but withheld by the agency until after the January 2010 court hearing.

A state judge ruled in favor of the state and Forest City, thus allowing financing for the arena to proceed. Had the documents actually been released, the financing--or at least the release of proceeds--instead might have been stalled.

Only after the documents released was the case reopened and the result reversed--the state would have to conduct a Supplemental Environmental Impact Statement (SEIS). The result was upheld by an appellate court, but the ESDC and Forest City are trying to appeal to the state Court of Appeals.

The ESDC contention

The ESDC Memorandum of Law made an entirely inaccurate prediction:
Petitioners' errors in describing the purpose and effect of the MTA term sheet are compounded by the fact that they look only to the transaction with MTA to discern FCRC's obligations. What they apparently fail to apprehend in painting their dismal picture of the future course of the Project is that there will be an entirely separate set of agreements between FCRC and ESDC, and that under those agreements FCRC will be contractually committed to implementing the 2009 MGPP. (Fact Statement 39.) Among other things, FCRC will be required to use "commercially reasonable efforts" to complete the Arena and certain Phase 1 buildings in accordance with a specified schedule, and to bring the Project to completion by 2019, with sanctions imposed for any failure to do so. (Fact Statement 39, AR 4692, 7979.)
(Emphases added; click on graphics to enlarge)

Yes, there would be an entirely separate set of agreements, but there were no sanctions imposed for a failure to bring the project to completion by 2019. Rather, the sanctions for Phase 1 would kick in after 12 years and for the project as a whole would kick in after 25 years.

Still under negotiation

What was in the cited Fact Statement 39, used as backup for the legal claim? According to the ESDC's legal Answer:
As required by the 2009 MGPP, the Development Agreement being negotiated between ESDC and FCRC will require FCRC to "use commercially reasonable efforts... to complete the entire Project by 2019." (AR 4692.) (As used herein, the term "Development Agreement" encompasses the development agreement, interim leases, development leases and ancillary agreements being negotiated between ESDC and FCRC to implement the project. (AR 7067-79.)) In the unexpected event that FCRC were to renege on its contractual commitments to ESDC and abandon the Project, the 2009 MGPP would remain in full force and effect, and would not be rendered unlawful as a plan for the Atlantic Yards site. In the event of such a default, ESDC could seek to recruit another developer to finish the work.
What was said in court

In court, as the transcript showed, ESDC attorney Philip Karmel admitted, "Well, the penalties are not set forth in the record." That's because the record did not include the Development Agreement, even though it had been signed during the interim period between the filing of legal papers and the court hearing.

And, indeed, there would be no sanctions for failure "to bring the Project to completion by 2019." Instead, the deadline is 25 years.

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.