Skip to main content

Thanks to (disruptive) overtime, Carlton Avenue Bridge is now on schedule to reopen before arena

Will the Carlton Avenue Bridge, a key connection between Prospect Heights and Fort Greene and one route to the adjacent arena surface parking lot, open before the Barclays Center does on September 28?

Yes, say developer Forest City Ratner and the state official overseeing the project--and this time, unlike in previous months, that pledge is backed up by reports from the state's construction monitor.

To get the bridge open, and avoid traffic chaos, the builders were considering opening the bridge with a temporary pier, not a permanent one. But even that won't be needed, thanks to overtime work, part of an accelerated schedule that caused considerable collateral damage to neighbors

Last report

At an Atlantic Yards District Service Cabinet meeting July 12, Forest City construction chief Bob Sanna said that the arena and the bridge were both on schedule.

Is there a contingency plan for the bridge? “We really do expect to have the bridge in place,” said Sanna.

Photo 8/8/12
Arana Hankin, Director, Atlantic Yards Project, Empire State Development, intervened. “They are ahead of schedule and things are going extremely well,” she said, “so there's no concern on our end about them not opening the bridge in time.”

Closer look

Well, in this case "ahead of schedule" means "ahead of the previous worst-case schedule," not ahead of some previously announced schedules. After all, when the bridge closed in January 2008, it was supposed to reopen two years later. And there's been much obfuscation about the timetable.

For months, the bridge was behind schedule. ESDC consultant STV, which provides weekly reports to the agency, said 3/9/12 that the bridge was "officially one month behind schedule," and would open in "late September," though time could be saved with a temporary pier and opening the bridge before asphalt was paved.




The bridge reconstruction is part of an "Arena Opening Condition" required by the Atlantic Yards Development Agreement. However, failure to meet that condition would result in only the freezing of Forest City Ratner's rights to move forward on any new residential development.


The firm Merritt & Harris, which serves as a construction monitor for arena bondholders, reported in June that the bridge was supposed to be finished by October 3, five days after the arena, but the developer was optimistic it could speed things up, via an overtime program.

That seems to have worked.

New schedules

In reports to ESD, STV has indicated changing completion times for the bridge.

For example, a schedule issued to STV in April--also apparently the one on which Merritt & Harris relied--indicated that the bridge would be complete in "late September/early October," assuming time savings from a temporary pier.


Schedule #12, dated 5/31/12, continued the same assumptions.
Curiously enough, there was no indication of a Schedule #13. (Was that some kind of superstition?)

Catching up

However, Schedule #14, dated 7/10/12, just before the District Service Cabinet meeting, indicated that things had been improved: the project is expected to be complete by September 20.


That temporary pier

Pier 3, Hankin reported, is roughly the same size as the other two piers, Piers 1 and 2. The temporary pier was a steel frame pier, compared to the permanent pier, which is concrete reinforced with steel reinforcing bars.

The permanent pier, Hankin said, "was constructed in July through early August and went a lot faster than the earlier piers. As such, the temporary pier, which was to stay in place through September, has already been disassembled as it is no longer needed. It is currently being stored on site in the now defunct south yard and, upon further disassembly, will be removed from the site."

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

Click on graphic to enlarge. This is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change, and the project is already well behind that tentative timetable.


Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …