Skip to main content

From the latest Construction Alert: new medians, subway station progress, arena site work, and some (purportedly) no-impact traffic diversion

The latest two-week Atlantic Yards Construction Alert, dated 8/13/12 (and embedded below) and released today by Empire State Development after preparation by Forest City Ratner, describes progress at the new subway station, and a good amount of visible work on streets and sidewalks.

Third-shift work, of course, continues, in the effort to get the arena ready for a Sept. 28 opening.

For example, new medians are being constructed along Atlantic Avenue, the excavation and grading of the plaza at the northeast corner of the arena block (to be used temporarily for bike parking) has been completed, and broadcast and power conduits for the tv truck parking lot at Dean Street and Sixth avenue should be installed.

Also note that, according to the alert, a flagger posted at the corner of Dean Street and Carlton Avenue is redirecting traffic from coming north as work is done at the Carlton Avenue Bridge, but "[t]his is not having an impact on the traffic flow in the area." According to Atlantic Yards Watch, that's not so at all.

Below I've bolded changes from the previous alert.

Arena site excavation
• All excavation within the arena walls is complete. Excavation at the exterior wall at Dean Street and 6th Avenue may be required for vent piping inspection this reporting period. Also, large catch basin-like structures are to be installed underground at the permanent truck elevator access driveway off of Dean which will house retractable bollards that are being installed as part of the Arena Site work.
Steel Erection Façade Installation
• The façade contractor will continue the installation of the main entry, high halo steel lattice work in this reporting period. This installation will take place during a second and third shift while the canopy supplemental steel is being erected and while the façade is erected over an area where other trades work, due to the fact there are not two levels of deck between the façade pieces and the worker below, as required by OSHA Sub-Part R steel erection requirements. Façade panels will continue to be installed on a second shift (3:30 PM to 11:00 PM) throughout this period. Some work during a partial third shift work (11:00 PM to 3 AM) may also be needed and work on Saturdays will continue. The permit for this third shift has been granted by NYC DOB.
Waterproofing & Fireproofing
• The waterproofing of the interior walls of the east and west stormwater retention tanks has been completed. The testing of the equalizer line, east and west tanks for leaking is completed and all have passed. The testing of the pump system is scheduled for this reporting period.
Mechanical, Electrical, & Plumbing
• The chiller plant and the primary bowl air handling units (AHU’s) are projected to be fully operational this reporting period and arena cooling under full volume is completed.
Note that the chiller plant and the primary bowl AHUs were projected to be fully operational in the past reporting period, as well.
• Elevator and escalator final installation work will continue this reporting period. Some second shift work is expected to be required for elevator/escalator installation throughout this reporting period. The truck elevators number 1 & 2 have been inspected and approved by DOB.
• The installation of the arena bowl ribbon (video boards) will continue this reporting period. The main scoreboard hoist has been placed, and the main scoreboard assembly will continue this reporting period.
Interior Build-out
• The gypsum wallboard (GWB) aka drywall framing & construction subcontractor will continue layout of walls during this reporting period and will continue placement of the top wall track and partition walls at all levels. Steel stud placement for partition walls will continue during this reporting period. The wallboard installation will continue on the Event Level, on Main & Upper Concourse, and on Level 7 mechanical room in Area C this reporting period.
• Seating installation will continue in the lower and upper bowl this reporting period.The retractable seating installation will continue this reporting period.• Exterior signage/interior signage installation will continue this reporting period.
Subway station
• Green roof and fascia waterproofing is now complete. Fascia panels have commenced and will be coordinated with the site paver installation.• Tile work is now complete and punch list work is underway. The steel stair nosings and stair tile work at the main entrance stair is also complete. The TA has now performed inspections and punch list work is underway. Ceiling panel installation will continue after stair punch list work is complete.• Elevator and escalator work is now complete. The 24 hour elevator testing was performed and passed. Escalator 48 hour run test was performed successfully. Minor punch list work is underway and inspections/certification by the vertical transportation consultant is underway.
Mechanical, Electrical & Plumbing
• Mechanical, electrical and plumbing work within the subway station below ground is substantially complete. Minor punch list work remains.
• Fire Alarm system programming is taking place for the station and on-site coordination walkthrough will occur with FDNY and NYCT.
Carlton Avenue Bridge
• MPT continues to be in place at Carlton Ave. and Pacific Street and along Atlantic Avenue during this reporting period. The concrete pour for the stem wall and pedestals of the final pier, Pier 3 have been completed.• Erection of bridge steel for all spans has been completed. Bolt–up and other activities associated with the steel work are ongoing. Installation of forms and rebar for bridge deck pours will be ongoing through the next reporting periods.• Pouring of bridge deck concrete and approach slabs will begin in this reporting period.• CAB underground utility work has begun and will be ongoing through the next reporting period at both the north and south ends of the CAB. The MPT will remain in place until after all underground utilities and final asphalt approach work is completed.
Post Cutover
• The LIRR has begun operations in the north yard. Contractor forces are continuing work to finish various portions of the yard work that were not fully completed prior to the cutover. These include “Punch list” items generated by the LIRR and the design engineers who have both performed detailed inspections of the work. This work is ongoing and will continue through this reporting period.
Block 1129
• Installation of the storm water detention system was completed.• Interior curb work is approximately 90% complete and will continue during this reporting period.
• Site electrical work, including underground conduits, pull boxes and light pole installation, will continue during this reporting period.
• Installation of the permanent fencing will continue during this period.
• Work on the adjacent sidewalks at Carlton Avenue and Dean Street will commence during this reporting period.
Traffic Mitigation Site Work/Atlantic Avenue medians
The first two sections of medians between South Portland and Cumberland Streets and between Clermont to Vanderbilt Avenue are completed except for placement of the strip of asphalt at the perimeter. The next medians to be constructed or modified will be small sections east of Cumberland and west of Clermont. The median at the arena block is expected to begin the week of August 20th. The medians on either side of the Carlton Avenue Bridge will begin in September.
Arena Site Work
• The revised Flatbush Avenue MPT has not [sic] been shifted in board onto the sidewalk area so the Flatbush Avenue roadway restoration, new bus pad and lay by lane can be construction during this reporting period. This work will be performed at night under DOT permits to minimize the impact to vehicular traffic. The bollard work is now complete along Flatbush Avenue and much of the Dean Street, 6th Avenue and Atlantic Avenue frontages.
• The curb installation work, sidewalk and street light installation work is now substantially complete on Flatbush Avenue from Dean Street up to Atlantic Avenue. Sidewalk along Flatbush is now substantially complete up to the tip and will continue during this reporting period. The contractor has installed barrels and fencing to screen work area from traffic and pedestrians.
• Installation of the underground drainage within the plaza area located at the tip of the site and beneath the future plaza area located at the corner of Dean Street and 6th Avenue is substantially complete. A temporary asphalt working surface has been placed throughout much of the plaza as well as in pedestrian areas. MPT along Dean Street and 6th Avenue has been repositioned in accordance with the approved DOT MPT Plan. The 6th Avenue MPT will be repositioned during this reporting period to the property line so the 6th Avenue sidewalk from Pacific Street to Dean Street can be re-opened.Excavation and grading of the B3 plaza has now been completed. Footings for the light pole bases are now complete. Finished concrete work will commence during this period.• The construction of the site benches at the tip of the site is complete. Electrical distribution work for the benches is also substantially complete. Planting mix has now been placed in the planters and the sedum has now been planted. The sedum has also been planted on the Transit Canopy roof.
• Bollard installation work, a tree pit sheeting installation and sidewalk roadway removal along Atlantic Avenue have now commenced from 6th Avenue towards Flatbush Avenue and will continue and is expected to be completed during this reporting period. Once complete the MPT will then be relocated to 8 ft off the curb line per DOT MPT plan. This will then facilitate the Atlantic Avenue mitigation work.
• MPT will also be installed on the west side of the 6th Avenue DOT bridge in order to facilitate the painting of the existing guard rails and the fencing work.
• MPT will also be installed on the west side of the 6th Avenue DOT bridge in order to facilitate the painting of the existing guard rails and the fencing work.
Broadcast Lot – Block 1128
• The trenches for the power and broadcast cable were installed and encased in concrete. During the two week period the layers of stone for the permeable asphalt system will be complete and paving will be installed. The light pole and wiring cabinet bases follow. The work is scheduled to be complete in August.
• During this two week period we expect the Revocable Consent, which allows for broadcast and power conduits for the lot to be installed in roadway and sidewalks, to be approved. Trenching and installation for the conduits will begin immediately upon such approval.
Dean Street Playground Comfort Station
• The contractor mobilized on June 11th. Excavation, foundations and underground piping are essentially complete. During this reporting period, the contractor will begin slab and masonry work. The work is scheduled to be complete this fall.
Tower 2
• Pile installation work for the Tower 2 early work is complete. Foundation installation at the Stair Four egress pad will commence on August 20th and continue for approximately two weeks.
Maintenance & Protection of Traffic (MPT)
MPT continues to be in place for the Carlton Avenue Bridge South Abutment construction staging from Pacific Street. The exact location is in the intersection of Carlton Avenue & Pacific Street. Occasionally a flagger posted at the corner of Dean and Carlton is redirecting traffic from traveling north on Carlton while the construction fence around the south bridge abutment is removed and underground utility and other work is ongoing at the Carlton and Pacific intersection. This is not having an impact on the traffic flow in the area. 
Repeated paragraphs that should've been updated
Arena site
• Revisions to the perimeter construction fence are projected to continue this reporting period, in order to allow the site construction activity to continue. Revisions to the Atlantic Avenue fence may start this reporting period. A temporary sidewalk bridge has been placed over the Flatbush Avenue east side sidewalk during the installation of façade panels on the main entry canopy. The permit has been secured for this work and the work is projected to start late during this reporting period.
• The gate at Dean and 6th Avenue has been relocated to the position of the permanent truck dock for the arena. Approximately three (3) parking spaces along Dean Street directly across from this have been taken for construction purposes. The taking of these spaces continues to be necessary in order to maintain the turning radius for truck deliveries into and out of this gate. At completion a new fence will be installed in board of the new curb. It is anticipated that this condition will be in place for two months during which time all work will be completed, weather permitting and barring any unforeseen conditions
Atlantic Yards Construction Alert 8-13-2012

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Atlantic Yards/Pacific Park graphic: what's built/what might be coming + FAQ (post-dated pinned post)

This graphic, posted in February 2018, is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. Note the unbuilt B1 and the proposed--but not yet approved--shift in bulk to the unbuilt Site 5.

The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change. The project is already well behind that tentative timetable.

How many people are expected?

Atlantic Yards/Pacific Park has a projected 6,430 apartments housing 2.1 persons per unit (as per Chapter 4 of the 2006 Final Environmental Impact Statement), which would mean 13,503 new residents, with 1,890 among them in low-income affordable rentals, and 2,835 in moderate- and middle-income affordable rentals.

That leaves 8,778 people in market-rate rentals and condos, though let's call it 8,358 after subtracting 420 who may live in 200 promised below-market condos. So that's 5,145 in below-market units, though many of them won…

The passing of David Sheets, Dean Street renter, former Freddy's bartender, eminent domain plaintiff, and singular personality

David Sheets, longtime Dean Street renter, Freddy's bartender, eminent domain plaintiff, and singular personality, died 1/17/18 in HCA Greenview Hospital in Bowling Green, KY. He was 56.

There are obituary notices in the Bowling Green Daily News and the Wichita Eagle, which state:
He was born in Wichita, KS where he attended public Schools and Wichita State University. He lived for many years in Brooklyn, NY, and was employed as a legal assistant. David's hobby was cartography and had an avid interest in Mass Transit Systems of the world. David was predeceased by his father, Kenneth E. Sheets. He is survived by his mother, Wilma Smith, step-brother, Billy Ray Smith and his wife, Jane all of Bowling Green; step-sister, Ellen Smith Alexander and her husband, Jerry of Bella Vista, AR; several cousins and step-nieces and step-nephews also survive. Memorial Services will be on Monday, January 22, 2018 at 1:00 pm with visitation from 10:00 am to 1:00 pm Monday at Johnson-Vaughn-Phe…

Some skepticism on Belmont hockey deal: lease value seems far below Aqueduct racino; unclear (but large?) cost for LIRR service

As I wrote for The Bridge 12/20/1, The Islanders Say Bye to Brooklyn, But Where Next?, the press conference announcing a new arena at Belmont Park for the New York Islanders was "long on pomp... but short on specifics."

Notably, a lease valued at $40 million "upfront to lease up to 43 acres over 49 years... seems like a good deal on rent for the state-controlled property." Also, the Long Island Rail Road will expand service to Belmont.

That indicates public support for an arena widely described as "privately financed," but how much? We don't know yet, but some more details--or at least questions--have emerged.

An Aqueduct comparable?

Well, we don't know what the other bid was, and there aren't exactly parcels that large offering direct comparables.

But consider: Genting New York LLC in September 2010 was granted a franchise to operate a video lottery terminal under a 30 year lease on 67 acres at Aqueduct Park (as noted by Gov. Andrew Cuomo).

As…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…