Skip to main content

From the latest Construction Alert: arena down to the wire, as some work won't be finished within two weeks

The Barclays Center, in both exterior and interior photos, looks close to finished, but there's still a lot of work to do regarding the arena and the site in general before the arena opens Sept. 28. And that's why there are double shifts daily to get the work done.

According to the latest two-week Atlantic Yards Construction Alert, dated today and issued by Empire State Development (after preparation by Forest City Ratner), the path to a Temporary Certificate of Occupancy (TCO) has been delayed somewhat, as indicated at last week's Atlantic Yards District Service Cabinet

While the NYC Department of Buildings  performed the first and preliminary TCO walk-though of the facility on 08/20/12 and did a second on 08/27/12, the final walk-through, scheduled for 9/4/12, was rescheduled to 09/07/12--though the document doesn't explain whether it actually occurred.

The FDNY inspections of the fire alarm were supposed to be finished  the week of 08/27/12 but now are "expected to be completed during this reporting period."The Department of Health inspection of the food service was scheduled for yesterday, 9/10/2012.  

While New York City Transit was initially expected to inspect the new subway entrance during the week of 8/27/12, it's now expected to inspect it this week. A soft opening of the station entrance is tentatively scheduled for September 14. 

More continuing work

At the parking lot, site electrical work will be completed during this reporting period, but installation of the permanent fencing "will continue," which suggests it won't be done until the final week of the month.  Similarly, while asphalt paving has been completed on the west side of the lot, it "will continue during this period on the east side."

Also continuing is work on the medians to the north of the arena block between Ft. Green and 6th Avenue and exterior work for the retractable bollard installation at the truck entry, and delivery of the remaining kitchen and concessions equipment.

The challenge

The overall challenge: getting the arena tested and commissioned before opening, a process that Forest City executive MaryAnne Gilmartin once swore had to start in July after the arena was completed.

My prediction: the arena will open, but it will be a bumpy ride.

Below some contrasts, marked in bold, with the last Construction Update.

Mechanical, Electrical, & Plumbing 
The ice floor will have test ice made during this reporting period. 
Interior Build-out
• The masonry, gypsum board and millwork contractors will continue working at all levels on punch list activities during this reporting period.
• The installation of the perforated metal panel in the main concourse will continue this reporting period.
• Final cleaning of the arena will be completed during this reporting period.
Note that the metal panel was supposed to be completed during the last reporting period.

Subway entrance
• The Transit Authority has decided to install the token booth and has commenced the installation. This work will continue during this period. The MVM’s will also be delivered and installed by NYCT. TA forces are also in the process of completing the installation of the AFC turnstiles.
Carlton Avenue Bridge
• Median work at Carlton and Atlantic Avenues will begin on September 7th and will be completed during this reporting period. MPT along Atlantic Avenue will be shifted to allow for median restoration work.
• The concrete pours for the Main Deck Slab, South Approach Slab and on-bridge sidewalks have been completed. Dry curing will be completed during this reporting period.
• Final welding of bridge bearings will be completed during this period. 

• Pouring of concrete for sidewalks and parapet walls has been completed and the concrete will be during this reporting period.
• CAB utility, lighting and signal work will continue in this reporting period at both the north and south ends of the CAB. MPT will remain in place until after all underground utilities and final asphalt approach work is completed.
• Installation of pedestrian fence on the bridge will be ongoing during this reporting period
• Paving and striping will be completed during this reporting period.  
Arena site work
•Excavation and grading of the B3 plaza has now been completed. Footings for the light pole bases are now complete. Finished concrete work will be completed. The soil has been placed and the lawn will be planted during this period. The loading dock entry and the truck staging area have also been paved. The fencing and light pole installation will follow during this period.
AY Construction Alert 9-10-2012

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.