Skip to main content

From the latest Construction Alert: arena down to the wire, as some work won't be finished within two weeks

The Barclays Center, in both exterior and interior photos, looks close to finished, but there's still a lot of work to do regarding the arena and the site in general before the arena opens Sept. 28. And that's why there are double shifts daily to get the work done.

According to the latest two-week Atlantic Yards Construction Alert, dated today and issued by Empire State Development (after preparation by Forest City Ratner), the path to a Temporary Certificate of Occupancy (TCO) has been delayed somewhat, as indicated at last week's Atlantic Yards District Service Cabinet

While the NYC Department of Buildings  performed the first and preliminary TCO walk-though of the facility on 08/20/12 and did a second on 08/27/12, the final walk-through, scheduled for 9/4/12, was rescheduled to 09/07/12--though the document doesn't explain whether it actually occurred.

The FDNY inspections of the fire alarm were supposed to be finished  the week of 08/27/12 but now are "expected to be completed during this reporting period."The Department of Health inspection of the food service was scheduled for yesterday, 9/10/2012.  

While New York City Transit was initially expected to inspect the new subway entrance during the week of 8/27/12, it's now expected to inspect it this week. A soft opening of the station entrance is tentatively scheduled for September 14. 

More continuing work

At the parking lot, site electrical work will be completed during this reporting period, but installation of the permanent fencing "will continue," which suggests it won't be done until the final week of the month.  Similarly, while asphalt paving has been completed on the west side of the lot, it "will continue during this period on the east side."

Also continuing is work on the medians to the north of the arena block between Ft. Green and 6th Avenue and exterior work for the retractable bollard installation at the truck entry, and delivery of the remaining kitchen and concessions equipment.

The challenge

The overall challenge: getting the arena tested and commissioned before opening, a process that Forest City executive MaryAnne Gilmartin once swore had to start in July after the arena was completed.

My prediction: the arena will open, but it will be a bumpy ride.

Below some contrasts, marked in bold, with the last Construction Update.

Mechanical, Electrical, & Plumbing 
The ice floor will have test ice made during this reporting period. 
Interior Build-out
• The masonry, gypsum board and millwork contractors will continue working at all levels on punch list activities during this reporting period.
• The installation of the perforated metal panel in the main concourse will continue this reporting period.
• Final cleaning of the arena will be completed during this reporting period.
Note that the metal panel was supposed to be completed during the last reporting period.

Subway entrance
• The Transit Authority has decided to install the token booth and has commenced the installation. This work will continue during this period. The MVM’s will also be delivered and installed by NYCT. TA forces are also in the process of completing the installation of the AFC turnstiles.
Carlton Avenue Bridge
• Median work at Carlton and Atlantic Avenues will begin on September 7th and will be completed during this reporting period. MPT along Atlantic Avenue will be shifted to allow for median restoration work.
• The concrete pours for the Main Deck Slab, South Approach Slab and on-bridge sidewalks have been completed. Dry curing will be completed during this reporting period.
• Final welding of bridge bearings will be completed during this period. 

• Pouring of concrete for sidewalks and parapet walls has been completed and the concrete will be during this reporting period.
• CAB utility, lighting and signal work will continue in this reporting period at both the north and south ends of the CAB. MPT will remain in place until after all underground utilities and final asphalt approach work is completed.
• Installation of pedestrian fence on the bridge will be ongoing during this reporting period
• Paving and striping will be completed during this reporting period.  
Arena site work
•Excavation and grading of the B3 plaza has now been completed. Footings for the light pole bases are now complete. Finished concrete work will be completed. The soil has been placed and the lawn will be planted during this period. The loading dock entry and the truck staging area have also been paved. The fencing and light pole installation will follow during this period.
AY Construction Alert 9-10-2012

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

This graphic, posted in November 2017, is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. Note the unbuilt B1 and the proposed shift in bulk to the unbuilt Site 5.

The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change. The project is already well behind that tentative timetable.

The previous graphic, from August 2017 (without the ghost B1)

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …