Skip to main content

From the latest Construction Alert: arena moves toward Temporary Certificate of Occupancy (thanks to three shifts of work)

The key information from the latest two-week Atlantic Yards Construction Alert, dated 8/27/12 and issued yesterday by Empire State Development (after preparation by Forest City Ratner) is the move toward a needed TCO, or Temporary Certificate of Occupancy, which is supposed to be achieved by 9/5/12.

According to the document (embedded below), it looks like they're on schedule:
The NYC DOB [Department of Buildings) performed the first and preliminary TCO walk-though of the facility on 08/20/12. The second is scheduled for 08/27/12, and the final on 09/04/12. The FDNY started the fire alarm and fire protection inspections on 08/21/12 and will continue through the week of 08/21/12, returning three days for the final inspections the week of 08/27/12.
A TCO indicates that a building is safe to occupy and can get insurance; the document typically expires in 90 days but can be renewed.

The Construction Alert details progress in various areas, as well as the need for overnight shifts, and jackhammers, to get all the work done. Clearly substantial work will be needed to finish the building, both to open it on Sept. 28 and to complete it fully by 6/30/13, but the issue for the DOB is whether

For example, punch list work is now complete on the Transit Canopy and New York City Transit will inspect this week.

Carlton Avenue Bridge

The concrete pours for the North Approach Slab and the bridge deck have been completed, while "[e]rection and bolt-up of bridge steel for all spans has been completed," with pouring of sidewalks and approach slabs continuing.

The surface parking lot, Block 1129
• Work on the adjacent sidewalks at Carlton Avenue and Dean Street has commenced and will continue for the next three weeks. The north side parking lane on Dean Street will be taken during construction of the sidewalk. Permits have been secured.
• Installation of the site sewer connections in Pacific Street between Carlton Avenue and Vanderbilt Avenue will continue and is expected to be completed in approximately two weeks. Traffic on Pacific Street will be closed at the locations of the work being performed.
• Asphalt paving will begin during this period on the west side of the parking lot.
Enlarging Pacific Street sidewalk between arena and parking lot
During this two week period the strip of weeds on the north side of Pacific Street between 6th and Carlton Avenues will be replaced with concrete sidewalk to widen the pedestrian area as required by the FEIS. The parking lane on the north side of the street and the entire sidewalk will be closed for the duration of the work. Work is expected to take approximately 5 days. Work may or may not be done during the holiday weekend, depending on weather and logistics. No parking signs will be posted at the beginning of the week
On Dean Street
• The retractable bollard installation at the truck entry has commenced and will continue during this reporting period during overnight hours.
A few delays

While the traffic median on Atlantic Avenue at the arena block is expected this week, according to the previous alert it was supposed to begin last week. Bollard installation on Sixth Avenue was supposed to be complete last week.
Atlantic Yards Construction Alert 8-27-2012

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.