Skip to main content

FCR still working on first tower, says arena and transit connection on schedule (no acknowledgment of delays), "working very aggressively" on Carlton Avenue Bridge

At yesterday's Atlantic Yards District Service Cabinet meeting, a bi-monthly meeting of involved agencies and developer Forest City Ratner, representatives of the latter expressed confidence about current construction (without mentioning evidence to the contrary), less certainty about future towers (for which the timetable has shifted), and assurances (despite some doubts from elected officials) that the Carlton Avenue Bridge would get done in time for the arena opening next year.

First tower: when and what

Will the first tower, known as B2 and located at the northeast corner of Flatbush Avenue and Dean Streete, be modular construction or conventional?

At the most recent cabinet meeting in September, FCR executive Jane Marshall recalled, “we had a robust discussion about traditional vs. modular... We're still working on both designs... So when we get to that fork in the road, we want to make sure that we’re really ready to make that decision.”

The building permit, however, hints at conventional construction.

“We still believe that, before the end of the year, we will be able to announce which way we’re going and show the the design to the public,” Marshall said. “That's our goal, consistent with our goal to break ground on B2 early next year.”

Actually, the timetable has been shifting. This past July, MaryAnne Gilmartin, the developer’s Atlantic Yards point person, said, “We expect to decide on our construction approach in the coming months, and we anticipate a groundbreaking by year end."

That wasn't the first shift. A year ago, at the 11/4/10 Atlantic Yards District Service Cabinet meeting, Gilmartin said the developer intended to release designs and start construction of B2 in the first quarter of 2011.

The Empire State Development Corporation had, in June 2009, said that the first tower, at least, would not be delayed at all.

Next towers?

What about the other three towers on the arena block, two of which are supposed to be exclusively residential?

“We said that we would love to get these buildings into the ground as quickly as possible,” Marshall said, “We have put ourselves a goal of six to nine months after construction of B2, so if we started B2 in the first quarter, we would love to start B3 in the third or fourth quarter of next year, and then six to nine months after that, B4. And so, that’s still our goal.”

She didn’t offer much reason to believe the goal was realistic.

Construction proceeds, delay unmentioned

What about ongoing construction? At the arena, said FCR executive Bob Sanna, the structural steel is 86% erected and the roof should be enclosed by the end of January.

“About 95% of the mechanical equipment that’s required to operate in the building is now in the building and being installed, so the arena is fully on schedule,” he said. “It will be complete in the early part of September.”

As for work on the associated transit connection, Sanna said it’s “moving extraordinarily well. We’re now completing metal decking over the new canopy that covers the stairs.” All the work now is inside, below grade.

Neither Sanna nor any attendee mentioned the latest report from the construction monitor to the bond trustee, which said the transit connection has been slowed, and was behind schedule as of a month ago.

Carlton Avenue Bridge

“As far as the LIRR work is concerned, the major piece of the excavation there is complete, and we continue to do drilling to support the Carlton Avenue Bridge,” Sanna said. “The bridge abutments are currently being constructed at the moment. We have a big pour contemplated tomorrow.”

He added that overtime continues: “We are working in a premium time program... five days a week, ten hours a day,” with an eight-hour day on Saturdays. “We're watching that schedule carefully to be complete in anticipation of the arena opening."

Later, Council Member Letitia James asked Chris Hrones of the Department of Transportation (DOT) if DOT was keeping track of the progress with the long-delayed bridge.

“Our bridges people are monitoring that project,” Hrones said, and looking at both the schedule and the work. However, he didn’t provide any details on those conclusions.

What if there are delays?

At another junction, Council Member Steve Levin asked, “Do we have a projected date of completion, and what happens if it's not open, what if you can't finish it by that time?”

“It is required to be open, and we are monitoring it very carefully,” replied Sanna, who also referenced the DOT’s role. “So we're working very aggressively to ensure that it does open.” He didn't provide a specific completion date.

Levin continued: "What if it doesn’t?"

“We're not contemplating that it will not open,” said Sanna, who noted that “the bridge structure itself is actually in fabrication... We do not anticipate that it will not open.”

“In the world of capital construction, stuff gets delayed all the time, so I’m just wondering,” Levin said.

“That has not been our track record to date,” responded Sanna.

Well, the bridge, which closed in January 2008, was initially supposed to take two years. It was delayed, in part, by Forest City’s redesign of the railyard to save money..

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …

For Atlantic Yards Quality of Life meeting Sept. 19, another bare-bones agenda (green wall?)

A message from Empire State Development (ESD) reminds us that the next Atlantic Yards/Pacific Park Quality of Life Meeting--which aims to update community members on construction and other issues--will be held:
Tuesday, September 19, 2017 @ 6 pm
Shirley Chisholm State Office Building
55 Hanson Place
1st Floor Conference Room
Brooklyn, NY 11217 The typically bare-bones, agenda, below, tells us nothing about the content of the presentation. One thing to look for is any hint of plans to start a new building on the southeast block of the project by the end of the year.

If not, ESD is supposed to re-evaluate a longstanding request from project neighbors to move back a giant wall encroaching on part of Dean Street between Carlton and Vanderbilt avenues. It's said to enclose construction activity, but, in recent months, has significantly served to protect worker parking.

Also, by the way, if you search for Atlantic Yards on Google or the ESD website, it leads to this page for the Atlantic Ya…