Skip to main content

From the latest Construction Alert: new floodlights at railyard; discussions about how to reduce noise during upcoming Atlantic Avenue work

The big news from the latest two-week Atlantic Yards Construction Alert, dated 11/7/11 and distributed yesterday by Empire State Development (after preparation by developer Forest City Ratner) includes:
  • Work at the railyard will continue on Saturdays and some Sundays, "due to the need to expedite all of this work for overall schedule maintenance" (in other words, to not fall behind)
  • Now that Daylight Savings Time is over, Yard Flood Lights will be turned on at 6am and from dusk to 7:30 pm.
  • Work will begin late 1st quarter or early 2nd quarter 2012 on the remaining traffic mitigation work, most of which is made up of raised medians along Atlantic Avenue from Flatbush Avenue to Vanderbilt Avenue. Given previous complaints about noise, the parties involved are discussing how to "reduce noise intensity."
  • Bollard installation is continuing, starting at Flatbush Avenue and Dean Street and is anticipated to be complete around the site perimeter by the middle of December.
I wandered by the site last night and saw a few bollards installed. Based on comments at last Thursday's Atlantic Yards District Service Cabinet meeting, it was my understanding, however, that the city Department of Transportation had not yet approved the bollard plan. (I'll update this when I get it clarified.)

The text below is excerpted from the latest document, with the bolded text indicating what's new compared to the previous alert.

Arena site
Preparation for the erection/installation of a material hoist at the intersection of 6th Avenue and Pacific Street has been cancelled. This hoist is no longer required to service the Project due to the fact that elevator installation will be completed in time to substitute for the hoist transport services.
Excavation
• Excavation for the footings will continue within the footprint of the arena in Area “C” during this reporting period. These footing excavations include the truck elevator and the truck turntable footings.
Exterior work
• Intumescent (fireproof) painting of the structural steel where required as an alternative to spray on fireproofing has started and will continue on a second shift operation during this reporting period. • Roof decking installation has commenced and will continue during this reporting period
• The installation of façade panels at the street level and at the Upper Concourse levels on Atlantic Avenue has been substantially completed. Contractor will return to install the façade panels at the uppermost elevation and in the area of the material hoist at a later date.
Interior work
The waterproofing of the interior walls of the east storm water retention tank will continue during this reporting period. This work may be performed on a second shift.
Mechanical, Electrical, & Plumbing
 • The boiler is being piped and electrical service to boiler being installed during this reporting period.
The construction fence at the ConEd vault will be revised to allow ConEd to begin installation of primary power conduit and cable to the arena at this point of entry. This will require work in the street by ConEd personnel – installers. Metal plates will cover the cable work in Dean Street while it is underway.
• The elevator/escalator subcontractor completed the installation of the Atlantic Avenue elevation escalator equipment during the last reporting period, and will continue with the VIP entry escalator this reporting period. Elevator installation has started and will continue this reporting period. The vertical transportation contractor is expected to work a second shift during this reporting period.
Subway entrance demolition
• Interior demolition of the new southbound local IRT stair has been completed and construction of the new stair will continue for the next several weeks below grade.
Work outside the subway entrance area fence
• Permits have been secured for the portions of the street immediately adjacent to the “Tip” of the project area. Concrete plank/decking in the roadway (at the corner of Flatbush and Atlantic) has been in place for some time. The southern eastbound lane of Atlantic Avenue has now been taken behind an expanded MPT in order to facilitate the removal of the planking/decking to be removed and the installation of temporary roadway restoration. This work is anticipated to occur over the next two to four week period. A pathway for the new water main has been coordinated with the utility team and will be constructed and following the plank removal. This will then permit the next phase of the water main installation to take place which is scheduled for the beginning of the year. This expanded MPT has been approved by DOT.
Waterproofing
• Waterproofing behind the foundation walls is now substantially complete. Waterproofing of the new roof at the tip of the site is now substantially complete and the balance of the roof waterproofing is anticipated to be complete by the end of the year.
Railyard work
Drilling – Support of Excavation, & Tiebacks,
• Drilling of tiebacks will continue in various areas of the yard (BL1120 and Block 1121). These tiebacks are drilled by small rigs, and are required at several elevations as excavation and lagging continue to the final depth of the yard sub-grade. Tieback drilling and placement of the attendant wood lagging will continue for the next two months, as they go together with excavation. Structural bracing of the car shop roof has been substantially completed, except for some additional work required at the east end, and that work should be completed within this reporting period. The contractor has begun removal of the old foundation/retaining wall on the south side of the car shop. This involves use of a Hoe-Ram hammer and will continue for several weeks.
Drainage System
Posillico/Tully is working from west to east to install deep drainage piping in the yard. They will also continue excavation for the associated storm water manholes. This work will be ongoing for the next 3 months. Formwork and rebar is currently being placed for the second and final pour for the Drainage Ejector Pump Vault at the west end of the site near the 6th Avenue Bridge. Concrete will be placed during this reporting period.
Electrical Ducts and Manholes
Conduit has been placed and the first of many concrete pours for underground electrical duct banks (for both train traction power and signal) has been made. Precast manholes have been placed at multiple locations. This work will continue for many months.
Carlton Avenue Bridge
Drill pipe has been delivered and is currently being inspected per NYC-DOT requirements. Posillico/Tully will start the installation of the 30 mini-piles required to be installed to support the new North Abutment during the next two weeks
East End (former Gasoline Station)
• Posillico/Tully will continue working on the lagging and tieback work at this location and continue to lower the grade there. Additional pile-drilling has resumed in this area below grade and will continue during the next two weeks. A crane-mounted shroud is being hoisted in place between the pile drill rig and the western Vanderbilt Avenue sidewalk and will continue to be in place while piles are being installed closest to the sidewalk and street. The excavation and associated support work will be on-going for the next couple of months.
Schedule Maintenance
• Due to the need to expedite all of this work for overall schedule maintenance, it will be progressed on Saturdays and (selected Sunday & Holidays).
Yards Lights
• During the week, to facilitate early start and late finish of work, Yard Flood Lights will be turned at 6am and from dusk to 7:30 pm.
Utility work
• The sanitary sewer and water taps on Dean Street are complete, inspected, backfilled and paved.
• Storm water discharge into the sewers is still in progress. The discharge at Flatbush Avenue is complete but has not yet been inspected. The discharge at 6th and Pacific Streets will be made during November and may begin in the next two week period if permits are received. The work will include a trench and associated sheeting or lagging approximately 17 to 20 feet deep to reach the bottom of the existing sewer main which the storm system will connect to. Because the main is almost in the center of the road and traffic will be limited until it is plated, and subject to DOT and OCMC approval, the trenching can be cut off at grade and plated over. This will work be coordinate with DOT, NYPD, FDNY as well as the arena contractor.
(The previous report stated that this should be done at night. Block 1129)
• The installation of gravel driving base started November 2 in the Block 1129 material lay down lots and may continue during this reporting period.
• Subject to alternate space being made available by Hunt, a portion of Staging area used by the utility and traffic mitigation contractor may be relocated from the Dean Street side to an area closer to Vanderbilt Avenue during this reporting period.
Demolition
Sign off on the removal of the one-story addition to 754 Pacific (aka 752 Pacific) is expected during this reporting period.
Traffic mitigation site work
• The Pacific and Flatbush curb extension is complete.
• The curb extension on Dean Street, west of Flatbush is complete.
• The Pacific Street & 4th Avenue curb extension is complete.
Atlantic Avenue Medians
Work will begin late 1st quarter or early 2nd quarter 2012 on the remaining traffic mitigation work, most of which is made up of raised medians along Atlantic Avenue from Flatbush Avenue to Vanderbilt Avenue. Work will commence when weather permits. The work will be performed during the 10 pm to 6 am shift because traffic lanes must be taken out of service on either side of the median. The arena block, Carlton Avenue Bridge reconstruction and DDC utility work between Carlton and Vanderbilt Avenues also take lanes out of service. Therefore, the median work must be scheduled block by block to coordinate with the other work schedules and MPT configurations. Because the work is a few feet directly above the LIRR tunnel into Atlantic Terminal, the means and methods must be reviewed and approved by the LIRR.
Noise issues
The traffic mitigation work to date required the use of jack hammers due to the requirement to install new conduits for new traffic signals being installed at the 4th, Flatbush and Atlantic intersections and the existence of thicker than normal road bed in many locations around Times Plaza. This second condition was due to the proximity and thickness of IRT and LIRR tunnel roofs, causing the inability to use larger more efficient equipment (i.e.: excavators and hoe rams) which would have reduced the duration of the noise substantially. After the pavement was saw-cut down to approximately 18”, jack hammers were required to be used to do remaining work removing pavement. The upcoming Atlantic Avenue Median work means and methods are being discussed with the LIRR with the goal of performing the pavement removal in a more efficient, rapid way to reduce noise intensity and duration while conforming to LIRR requirements for work in proximity to their facilities.
Arena Site Work
The revised Flatbush Avenue MPT is allowing work to continue on the installation of the Flatbush Avenue façade and the installation of bollards along this same stretch. The MPT revisions are now complete. Part of the overall site work for the arena block, bollard installation, commenced at the intersection of Dean and Flatbush in the area of the southern vents and will continue north along Flatbush, eventually continuing around the entire block. The bollard work is anticipated to be complete by the middle of December. Other work that will be done as part of the site work includes sidewalks, installation of pavers, street furniture, street trees, light and signal poles, way finding signage, hydrants and the canopy to the new subway entrance. Additional detail on the work will be provided as the contractor progresses.
Anticipated Nighttime & Weekend Work
During this reporting period the following work will be performed either at night or during the weekend as noted. All work will be done pursuant to approved permits:
• Long Island Rail Road/Vanderbilt Yard/ Carlton Avenue Bridge:
o Construction hours are 6am – 4:30pm.
o Construction work will take place on Saturdays during the hours of 7am – 5:30pm
o Construction work may take place on Sundays during the hours of 8:00 AM – 4:30PM
The weekend work being performed could be in any area of the yard, and within MPT areas for which permits are on hand.
• Arena Site:
o Arena weekend work will be scheduled no later than close of business on the preceding Thursday, where make-up work due to weather or other delays makes it necessary. Saturday work is expected to continue for this reporting period.
o Subject to receipt of permits, a second shift shall be continued throughout this reporting period, from 3 – 11 PM, Monday-Friday only. Also subject to receipt of permits, a third shift shall be instituted during this reporting period, from 11 PM – 7 AM, Monday –Friday only.
o Hunt has been granted a permit to allow for deliveries from 6 AM to 7 AM to the Arena site from the dispatch center. This work allows for an additional hour of deliveries to take place outside the neighborhood peak traffic patterns and reduce congestion and interference with the local traffic.
o The Developer has been requested to advise ESDC and STV of what contractors will be working over the weekend and what they will be working on. The second shift arena contractors are noted within the arena summary above.
• NYC Transit Improvements:
o Temporary concrete road decking is substantially complete, however, in the event there is a need to do any related work, such work will be performed at night per DOT regulations. Traffic will be restored every morning according to DOT stipulations.
As noted above, work will be performed to repair steel within the BMT Tunnel and will be conducted under a BMT GO during the weekend of November 26th as approved by the NYCT. Additionally, work related to of the BMT structure and below grade concrete, steel and MEP work may be conducted on Saturdays November 12th and November 19th, during this reporting period.
• Block 1129 – staging area:
o Contractors conducting night work may have cause to enter and exit this area as it serves as a staging and material/equipment storage area.
FINAL AY Construction Alert 11-7-2011

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

This graphic, posted in November 2017, is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. Note the unbuilt B1 and the proposed shift in bulk to the unbuilt Site 5.

The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change. The project is already well behind that tentative timetable.

The previous graphic, from August 2017 (without the ghost B1)

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …