Skip to main content

Reopening of Carlton Avenue Bridge, closed since January 2008 (supposedly for two years), nudged from April 2012 to "summer 2012"; will it go longer?

It was inevitable, wasn't it? We knew that the Carlton Avenue Bridge, closed since January 2008, had to reopen before the Atlantic Yards arena reopens.

And now that "substantial completion" of the arena is August 12, 2012, so too has the city Department of Transportation nudged back the reopening of the bridge from the most recent deadline, April 2012, to "summer 2012."

That's not the first revision of the plan, not by a long shot.

And I'd say there's a good chance that the bridge reopening could be nudged further back to "fall 2012," if the arena opens in the fall.

Closure for four-and-a-half years?

All this means that bridge would be closed for at least four-and-a-half years, more than twice as long as originally promised in the Atlantic Yards environmental review, approved in 2006.

Above right, the previous estimation from DOT.

Original plans

The bridge, which connects Pacific Street to Atlantic Avenue and thus Prospect Heights to Fort Greene, closed in 1/23/08. In January 2009, the DOT said the work "is scheduled for completion January 2010."

By August 2009, DOT had quietly advanced the official opening date (above left) to January 2011--three years after closure. I wrote at the time that there was ample reason to believe that the reopening would be delayed even more.

Most recent estimates

According to the June 2009 Technical Memorandum of the Empire State Development Corporation (ESDC), accompanying the 2009 Modified General Project Plan:
Under the revised schedule, completion of the arena construction would occur in the first quarter of 2012, and the reconstruction of the Carlton Avenue Bridge would be completed in time for the opening of the arena and would be compatible with LIRR rail yard operations and the new permanent yard, which is expected to be completed in 2013.
Note that "completion of the arena construction" is not necessarily the same thing as "the opening of the arena."

In a December 2010 Response to the Remand Order of Supreme Court Justice Marcy Friedman, hearing an ongoing case regarding whether the ESDC should have studied the impacts of a 25-year (rather than ten-year) buildout, the ESDC stated:
Also, a delay in the construction of the Project would not affect the duration of the closure of the Carlton Avenue Bridge, because the 2009 MGPP requires the Carlton Avenue Bridge to be re-built and operational by the Arena opening condition.
That's not precisely true, given the nudge back.

In the December 2010 Technical Analysis, the ESDC stated:
As detailed in Table 5 below, the 2009 Technical Memorandum found that the duration of construction of most Project elements, would not change as a result of their modified start date within the overall construction schedule. Rather, with the exception of Project elements whose construction had already commenced, the schedule’s overall timeline reflected a shift by approximately three years from what was presented in the FEIS. Under the schedule presented in the FEIS, in the fourth quarter of 2009 the construction of the arena would be completed and by the fourth quarter of 2010 the remaining arena block buildings—Buildings 1, 2, 3, and 4—would be completed. Under the revised schedule, completion of the arena construction would occur in the first quarter of 2012, and the reconstruction of the Carlton Avenue Bridge would be completed in time for the opening of the arena and would be compatible with LIRR rail yard operations and the new permanent yard, which was expected to be completed in 2013.

... Reopening of Carlton Avenue between Pacific Street and Atlantic Avenue would take place with the opening of the arena.
Longer sequence than promised

Why is it all taking so long? Partly because Forest City Ratner is proceeding in three stages, a far slower sequence than that disclosed in the Final Environmental Impact Statement (FEIS).

As I wrote, Chapter 17, Construction Impacts, of the FEIS prepared by the Empire State Development Corporation (ESDC), made no reference to such phasing. Rather, the bridge was presumed to be fully demolished and reconstructed within two years, during the construction of the temporary yard.

Also, the contract terms were more generous than predicted in the FEIS. While Forest City Ratner had three years to complete the job without penalty, a clause in the contract, signed 12/17/07, provides up to five years to complete the work in case of Unavoidable Delay.

One definition of Unavoidable Delay is a delay in "completing the Master Closing," which includes the ESDC's exercise of eminent domain and the closing of a purchase and sale agreement with the MTA/LIRR for the Vanderbilt Yard.

As I wrote 3/1/10, the bridge was originally supposed to reopen by the time a temporary railyard was completed--and the latter had been accomplished.

A key factor in the delay was likely Forest City Ratner's effort in 2009--well after the demolition process had begun--to renegotiate plans for a smaller and less costly permanent railyard.

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…