Skip to main content

Latest consultant's report is murky: transit connection delayed, but no explanation offered; not-yet-public document indicates "delays" and "extension of the construction term"; 415 workers on site

Hints and statistical evidence that the Atlantic Yards arena and associate infrastructure have slowed somewhat are borne out--though not explicated and perhaps deliberately obscured--in the latest Arena Site Observation Report, dated 11/2/11 and based on a 9/28/11 site visit.

The report, based on cash flow, is prepared by Merritt & Harris, the real estate consultant to the arena PILOT Bond Trustee.

It states that the Barclays Center remains barely on schedule, while the transit connection, for a good while two months ahead of schedule, is now behind schedule.

And some misleading information is provided regarding the latter delay.

Strong hints of delays, but how important?

The report also drops a significant hint that the project is delayed somewhat. For the first time, it mentions a "GMP2"--presumably a revision of the project's Guaranteed Maximum Price--that "includes all delays" and "extension of the construction term." That GMP2 was to be issued October 1, but has not been made public yet.

It's unclear how meaningful the extension would be. The arena has long been planned to open in the fall of 2012 even as final completion would occur in mid-2013. So an extension that affects final completion would have a lesser impact than an extension that affects the opening date.

Similarly, the transit connection is supposed to be finished by April 2012, which presumably leaves significant wiggle room.

Arena progress

The graphic below indicates arena construction progress--slightly ahead of schedule according to graphic and the statistics. However, as indicated by the highlighted number, actual spending in September was  below projected spending. (Click on graphics to enlarge.)

Still, they're only about one-third done, with some significant work left to go--which may be why there's now so much after-hours work.

Transit connection slows

The graphic below indicates transit connection construction progress--now behind schedule. No explanation was given in the document, though Forest City Ratner officials have indicated that Hurricane Irene caused delays, mainly at the railyard, given the below-grade location.

Much of the transit connection work is similarly below grade.


Why the delay?

The latest document offers no explanation for the delays in the transit connection.

Rather, offers a misleading explanation, attributing a one week slippage on "early delays with approval of the test piles."


But that's contradicted by the information provided in the previous month:

In other words, the "early delays with approval of the test piles" did not cause ongoing slippage in the Construction Schedule, since the project was able to return to schedule thanks to "excavation and demolition work." Indeed, as the graphic above indicates, the project was way ahead for a while.

Workers on site: 415

Page 42 of the document indicates 415 workers: 362 persons at the Arena and 53 persons at the Transit Connection.

The previous document indicated 422 workers.

At the Atlantic Yards District Service Cabinet meeting 9/22/11, the developer provided no numbers, but a representative of the state said, “We've estimated that there are currently 520 workers on a given shift."

Forest City Ratner likely counts additional workers on the railyard, which is not subject to bond funding and thus not subject to the consultant's report.

Still, as I've stated, such discrepancies might be explained by a report from the Independent Compliance Monitor (ICM) required by the Community Benefits Agreement, but no ICM has been hired.

Maybe we'll learn more at today's District Service Cabinet meeting.

A photo of the escalator

Whatever the rate of progress, they're building an escalator to the transit connection. Below is a photo from the report, dated 9/28/11.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

So, Forest City has some property subject to the future Gowanus rezoning

Writing yesterday, MAP: Who Owns All the Property Along the Gowanus Canal, DNAinfo's Leslie Albrecht lays out the positioning of various real estate players along the Gowanus Canal, a Superfund site:
As the city considers whether to rezone Gowanus and, perhaps, morph the gritty low-rise industrial area into a hot new neighborhood of residential towers (albeit at a fraction of the height of Manhattan's supertall buildings), DNAinfo reviewed property records along the canal to find out who stands to benefit most from the changes.
Investors have poured at least $440 million into buying land on the polluted waterway and more than a third of the properties have changed hands in the past decade, according to an examination of records for the nearly 130 properties along the 1.8-mile canal. While the single largest landowner is developer Property Markets Group, other landowners include Kushner Companies, Alloy Development, Two Trees, and Forest City New York.

Forest City's plans unc…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…