Skip to main content

Latest consultant's report: arena still ahead of schedule (but lead is narrowing), while transit connection is on schedule (but no longer ahead)

According to the latest Arena Site Observation Report, dated 9/9/11 (and based on a 7/28/11 visit and documents made available 8/29/11), the Barclays Center remains one month ahead of schedule, while the associated transit connection to the Atlantic Avenue subway hub--after being ahead of schedule--is simply on schedule.

The estimate, based on cash flow, comes in a report prepared by Merritt & Harris, the real estate consultant to the arena PILOT Bond Trustee. Last month's report, however, stated that the transit connection was two months ahead of schedule.

(The transit connection is supposed to be completed by 3/26/12, while the arena is due 8/27/12.)

Some opacity

Also, there seems to be a lingering dispute about the schedule for which the resolution just keeps being put off, with no clarity from the consultant.

NetsDaily stated that the arena is ahead of schedule "despite" the hurricane and earthquake in August. The Site Observation Report makes no mention of the impact of either.

The hurricane hit 8/28/11, by which time nearly all of the month's spending, in documents made available 8/29/11, had been completed. In other words, next months' report should be more illuminating, though, given the relative opacity of these reports, I wouldn't bet that the impact of the hurricane will be noted.



Workers on site: 409 vs. Ratner's 430

There seem to be fewer workers on site than Forest City Ratner has reported. Page 40 of the document indicates 409 workers: 365 persons at the Arena and 44 persons at the Transit Connection.

By contrast, at the Atlantic Yards District Service Cabinet meeting 7/14/11, the developer reported 430 workers on site.

Forest City Ratner likely counts additional workers on the railyard, which is not subject to bond funding and thus not subject to the trustee's report.

Still, as I've stated, such discrepancies might be explained by a report from the Independent Compliance Monitor (ICM) required by the Community Benefits Agreement, but no ICM has been hired.

Arena progress

The graphic indicates that the arena is still ahead of schedule, though it suggests that the gap is narrowing.

The graphic is based on spending. As of June 2011, for example, the estimated cumulative spending was $139.1 million, while the actual spending was $149.8 million. As of July 2011, the estimated cumulative spending was $164.15 million, while the actual spending was $170.3 million.

Transit connection progress

The graphic indicates that the transit connection, while slightly ahead of schedule (though apparently closer to "on schedule" than a month ahead), has slowed down somewhat.


The graphic is based on spending. As of June 2011, for example, the estimated cumulative spending was $26.65 million, while the actual spending was $29.2 million. As of July 2011, the estimated cumulative spending was $30.5 million, while the actual spending was $31.8 million. That gap is $1.3 million, while in March 2011 the gap was $8.1 million.

Schedule disputes or discrepancies?

For months, Merritt & Harris has hinted at some unresolved, if not necessarily highly contentious, discrepancies over the schedule, with a resolution "expected" soon but instead continually put off.

From p. 8 of the latest document:
The original High Level Arena Summary Construction Schedule, dated July 16, 2010, had been provided for our review. We subsequently received the Executive Level Summary for Schedule 12M, dated February 10, 2011, prepared by Hunt, which indicates that substantial completion is anticipated to be by August 27, 2012. The Developer is currently reviewing that schedule and is working with Hunt to reach an agreement. A resolution is expected by September 2011.
(Emphasis added)

Nearly the same statement appeared in the documents in August and July, with the erroneous prediction that a resolution was expected in the month of the document.

The resolution date has been steadily pushed back. The 1/28/11 report:
A High Level Arena Summary Construction Schedule, dated July 16, 2010, has been provided for our review. The current schedule, prepared by Hunt, indicates that substantial completion is anticipated to be by August 12, 2012. The Developer is currently reviewing that schedule and is working with Hunt to resolve current schedule disputes. A resolution is expected over the next few months.
(Emphases added)

Note that the substantial completion date has since been nudged back 15 days to 8/27/02, and that the term "schedule disputes" is no longer used.

The 1/3/11 report also used the term "schedule disputes" and hinted at a much earlier resolution:
A High Level Arena Summary Construction Schedule, dated July 16, 2010, has been provided for our review. The current schedule, prepared by Hunt, indicates that substantial completion is anticipated to be by August 12, 2012. The Developer is currently reviewing that schedule and there is a meeting anticipated for mid-December to resolve current schedule disputes.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

So, Forest City has some property subject to the future Gowanus rezoning

Writing yesterday, MAP: Who Owns All the Property Along the Gowanus Canal, DNAinfo's Leslie Albrecht lays out the positioning of various real estate players along the Gowanus Canal, a Superfund site:
As the city considers whether to rezone Gowanus and, perhaps, morph the gritty low-rise industrial area into a hot new neighborhood of residential towers (albeit at a fraction of the height of Manhattan's supertall buildings), DNAinfo reviewed property records along the canal to find out who stands to benefit most from the changes.
Investors have poured at least $440 million into buying land on the polluted waterway and more than a third of the properties have changed hands in the past decade, according to an examination of records for the nearly 130 properties along the 1.8-mile canal. While the single largest landowner is developer Property Markets Group, other landowners include Kushner Companies, Alloy Development, Two Trees, and Forest City New York.

Forest City's plans unc…