Skip to main content

Documents show FCR has missed three deadlines to construct temporary railyard (and that litigation was not a factor)

Both the Empire State Development Corporation and developer Forest City Ratner blame pending litigation for the work stoppage at the Metropolitan Transportation Authority's Vanderbilt Yard.

I've already cited sworn affidavits by FCR executives who promised that work would continue during litigation, claiming that the developer's "construction schedule has been carefully drawn... by commencing work now on vacant properties that are owned by FCRC, the MTA and the City...."

There's another reason not to believe the ESDC/FCR explanation. Construction schedules prepared by/for the developer regarding completion of a temporary railyard--Stage 1 of three at the Vanderbilt Yard--offer no indication that litigation would be a factor.

And, contrary to the claim by FCR spokesman Joe DePlasco that "we've gone about as far as we can go at this point with preliminary work," the temporary railyard is way behind schedule, having missed three deadlines.

In fact, a license for temporary yard work signed 2/14/07 states (right; click to enlarge) that, if construction of a permanent railyard does not begin within 24 months, the MTA has the option to ask Forest City Ratner "to fully restore the Present VD Yard Functions" and--apparently, though the language is murky--end the deal. There's no indication that the MTA would exercise such leverage, but the option would become available in some ten weeks, as the authority waits for the $100 million FCR has pledged to lease the railyard.

Deadlines missed

Initially, according to a Construction Schedule attached to the Atlantic Yards Final Environmental Impact Statement (excerpt at right; click to enlarge), the temporary yard was supposed to open 8/17/07. That was unrealistic, given that the work never could have commenced 11/1/06, since that was nearly two months before the project was officially approved.

But the delay is now nearly 16 months, not two months, and will just continue to grow.

For example, according to the Preliminary Draft Construction Schedule that is part of the 2/14/07 license agreement entered into by MTA and LIRR with FCR, the temporary yard was supposed to open 11/8/07, nearly three months late.

According to another document, Construction Schedule Stage One (right), dated 5/20/08, the Temporary Yard was supposed to open 10/24/08, more than 14 months late.

Both documents were obtained from the MTA via Freedom of Information Law requests.

Why the delay?

I asked for more specifics about the timetable, but I didn't get any answers. I asked before the stall at the railyard had become evident; litigation wasn't cited as an explanation for delays.

"There isn't a more updated document," MTA spokesman Jeremy Soffin told me November 21. "It's a complicated construction project, and some delays are not unusual. I don't have updated projections at this time."

In other words, though the construction schedule describes various elements of work under columns such as "Remaining Duration" and "% Completion," he was unable to offer more detail about how much was done nor when completion of Stage 1 was expected. Nor could he offer any projection about the ensuing two stages of LIRR work.

The 2/14/07 contract does suggest that clarifications should be made available. It states that Forest City Ratner "shall deliver to Licensors from time to time (which may be during the course of project meetings held weekly or at such other intervals as the Parties may from time to time deem appropriate) updates or modifications to the Construction Schedule."

One example

The Atlantic Yards Construction Update for the weeks beginning November 17, 2008 and November 24, 2008, the last construction update to describe work at the railyard, indicated, among other work:
Continue installing gabion wall, Block 1121.

However, according to the updated MTA schedule issued in May, the gabion wall (a retaining wall) was supposed to be finished by 7/30/08, more than four months ago.

And, as I noted, the construction update did not indicate that the work was completed, even though in other cases the construction updates make that distinction.

In other words, it's a safe bet that the installation is not finished--and that the delay has nothing to do with litigation.

Deal was supposed to close a year ago

A 9/4/07 New York Observer (NYO) article headlined Atlantic Yards: The Suspense Builds described delays:
The company has not closed on a $100 million deal to lease the 8-acre Long Island Rail Yard from the Metropolitan Transportation Authority, but has been working instead under a license agreement. (M.T.A. spokesman Jeremy Soffin said the deal should close at the end of this year or in the beginning of 2008.) While contractors have taken the first step to construct a temporary rail yard on the eastern end of the site—a precondition for work on the arena, where trains are currently stored—that work was supposed to be completed by the middle of August, according to the schedule from last year.

But the deal did not close in early 2008.

In an MTA webinar last April, executive director Elliot (Lee) Sander expressed concern about the whereabouts of the $100 million. He said the money was assigned to the 2005-09 capital program, and brought up Atlantic Yards without being asked.

His statement:
There was approximately a billion dollars associated with the sale of MTA real estate assets to support that program. There are some monies there that look like there may be challenges to proceed upon right now. There is money there--100 million dollars associated with the sale of Atlantic Yards, and I think many of you have read in the newspapers some of the difficulty Forest City is having with that development, so hopefully that will proceed, but we want to make sure that that happens—but we’re concerned about that.

There's no indication in available MTA documents that the authority is counting on getting the money by next year.

A flashback on credibility

The NYO article offered some choice quotes that, in hindsight, hint at the credibility of various parties.

FCR spokesman Joe DePlasco: "We anticipate opening the arena in time for the 09-10 season."

Empire State Development Corporation spokesman Errol Cockfield (who now reps Gov. David Paterson): "We’re working with Forest City Ratner to achieve the goal of opening the arena by the 2009 season."

NYO on AYR: "Journalist Norman Oder first reported on the affidavit in his blog, Atlantic Yards Report, last April, and has repeatedly questioned Forest City’s ability to complete all phases of the work by 2016."

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

This graphic, posted in November 2017, is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. Note the unbuilt B1 and the proposed shift in bulk to the unbuilt Site 5.

The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change. The project is already well behind that tentative timetable.

How many people are expected?

Atlantic Yards/Pacific Park has a projected 6,430 apartments housing 2.1 persons per unit (as per Chapter 4 of the 2006 Final Environmental Impact Statement), which would mean 13,503 new residents, with 1,890 among them in low-income affordable rentals, and 2,835 in moderate- and middle-income affordable rentals.

That leaves 8,778 people in market-rate rentals and condos, though let's call it 8,358 after subtracting 420 who may live in 200 promised below-market condos. So that's 5,145 in below-market units, though many of them won't be so cheap.

As…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Atlantic Yards/Pacific Park in 2017: no new towers, unfilled affordable units, Islanders prepare to leave, project timetable fuzzy

My 2018 preview.

It was another wait-and-see year for Atlantic Yards/Pacific Park, with one big twist--the beginning of a slow goodbye for the New York Islanders--but continued delays for towers, a lost (mostly) 421-a subsidy for condos, and new skepticism about unfilled not-so-affordable housing units.

So ongoing questions linger regarding the project's pace, affordability, and even future ownership.

In my 2017 preview, I predicted--not exactly going out on a limb--that two and likely three more towers would open, though it would be unclear how fast they'd lease up and sell.

Indeed, we've learned that the middle-income below-market units at 461 Dean (which opened in 2016) and 535 Carlton have leased very slowly, while it's too soon to assess progress for commensurate units at 38 Sixth. (At 535 Carlton and 38 Sixth, middle-income units make up half the "100% affordable" buildings.) Meanwhile, many apartments are up for rent at the 550 Vanderbilt condo buildin…