Skip to main content

Documents show FCR has missed three deadlines to construct temporary railyard (and that litigation was not a factor)

Both the Empire State Development Corporation and developer Forest City Ratner blame pending litigation for the work stoppage at the Metropolitan Transportation Authority's Vanderbilt Yard.

I've already cited sworn affidavits by FCR executives who promised that work would continue during litigation, claiming that the developer's "construction schedule has been carefully drawn... by commencing work now on vacant properties that are owned by FCRC, the MTA and the City...."

There's another reason not to believe the ESDC/FCR explanation. Construction schedules prepared by/for the developer regarding completion of a temporary railyard--Stage 1 of three at the Vanderbilt Yard--offer no indication that litigation would be a factor.

And, contrary to the claim by FCR spokesman Joe DePlasco that "we've gone about as far as we can go at this point with preliminary work," the temporary railyard is way behind schedule, having missed three deadlines.

In fact, a license for temporary yard work signed 2/14/07 states (right; click to enlarge) that, if construction of a permanent railyard does not begin within 24 months, the MTA has the option to ask Forest City Ratner "to fully restore the Present VD Yard Functions" and--apparently, though the language is murky--end the deal. There's no indication that the MTA would exercise such leverage, but the option would become available in some ten weeks, as the authority waits for the $100 million FCR has pledged to lease the railyard.

Deadlines missed

Initially, according to a Construction Schedule attached to the Atlantic Yards Final Environmental Impact Statement (excerpt at right; click to enlarge), the temporary yard was supposed to open 8/17/07. That was unrealistic, given that the work never could have commenced 11/1/06, since that was nearly two months before the project was officially approved.

But the delay is now nearly 16 months, not two months, and will just continue to grow.

For example, according to the Preliminary Draft Construction Schedule that is part of the 2/14/07 license agreement entered into by MTA and LIRR with FCR, the temporary yard was supposed to open 11/8/07, nearly three months late.

According to another document, Construction Schedule Stage One (right), dated 5/20/08, the Temporary Yard was supposed to open 10/24/08, more than 14 months late.

Both documents were obtained from the MTA via Freedom of Information Law requests.

Why the delay?

I asked for more specifics about the timetable, but I didn't get any answers. I asked before the stall at the railyard had become evident; litigation wasn't cited as an explanation for delays.

"There isn't a more updated document," MTA spokesman Jeremy Soffin told me November 21. "It's a complicated construction project, and some delays are not unusual. I don't have updated projections at this time."

In other words, though the construction schedule describes various elements of work under columns such as "Remaining Duration" and "% Completion," he was unable to offer more detail about how much was done nor when completion of Stage 1 was expected. Nor could he offer any projection about the ensuing two stages of LIRR work.

The 2/14/07 contract does suggest that clarifications should be made available. It states that Forest City Ratner "shall deliver to Licensors from time to time (which may be during the course of project meetings held weekly or at such other intervals as the Parties may from time to time deem appropriate) updates or modifications to the Construction Schedule."

One example

The Atlantic Yards Construction Update for the weeks beginning November 17, 2008 and November 24, 2008, the last construction update to describe work at the railyard, indicated, among other work:
Continue installing gabion wall, Block 1121.

However, according to the updated MTA schedule issued in May, the gabion wall (a retaining wall) was supposed to be finished by 7/30/08, more than four months ago.

And, as I noted, the construction update did not indicate that the work was completed, even though in other cases the construction updates make that distinction.

In other words, it's a safe bet that the installation is not finished--and that the delay has nothing to do with litigation.

Deal was supposed to close a year ago

A 9/4/07 New York Observer (NYO) article headlined Atlantic Yards: The Suspense Builds described delays:
The company has not closed on a $100 million deal to lease the 8-acre Long Island Rail Yard from the Metropolitan Transportation Authority, but has been working instead under a license agreement. (M.T.A. spokesman Jeremy Soffin said the deal should close at the end of this year or in the beginning of 2008.) While contractors have taken the first step to construct a temporary rail yard on the eastern end of the site—a precondition for work on the arena, where trains are currently stored—that work was supposed to be completed by the middle of August, according to the schedule from last year.

But the deal did not close in early 2008.

In an MTA webinar last April, executive director Elliot (Lee) Sander expressed concern about the whereabouts of the $100 million. He said the money was assigned to the 2005-09 capital program, and brought up Atlantic Yards without being asked.

His statement:
There was approximately a billion dollars associated with the sale of MTA real estate assets to support that program. There are some monies there that look like there may be challenges to proceed upon right now. There is money there--100 million dollars associated with the sale of Atlantic Yards, and I think many of you have read in the newspapers some of the difficulty Forest City is having with that development, so hopefully that will proceed, but we want to make sure that that happens—but we’re concerned about that.

There's no indication in available MTA documents that the authority is counting on getting the money by next year.

A flashback on credibility

The NYO article offered some choice quotes that, in hindsight, hint at the credibility of various parties.

FCR spokesman Joe DePlasco: "We anticipate opening the arena in time for the 09-10 season."

Empire State Development Corporation spokesman Errol Cockfield (who now reps Gov. David Paterson): "We’re working with Forest City Ratner to achieve the goal of opening the arena by the 2009 season."

NYO on AYR: "Journalist Norman Oder first reported on the affidavit in his blog, Atlantic Yards Report, last April, and has repeatedly questioned Forest City’s ability to complete all phases of the work by 2016."

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

So, Forest City has some property subject to the future Gowanus rezoning

Writing yesterday, MAP: Who Owns All the Property Along the Gowanus Canal, DNAinfo's Leslie Albrecht lays out the positioning of various real estate players along the Gowanus Canal, a Superfund site:
As the city considers whether to rezone Gowanus and, perhaps, morph the gritty low-rise industrial area into a hot new neighborhood of residential towers (albeit at a fraction of the height of Manhattan's supertall buildings), DNAinfo reviewed property records along the canal to find out who stands to benefit most from the changes.
Investors have poured at least $440 million into buying land on the polluted waterway and more than a third of the properties have changed hands in the past decade, according to an examination of records for the nearly 130 properties along the 1.8-mile canal. While the single largest landowner is developer Property Markets Group, other landowners include Kushner Companies, Alloy Development, Two Trees, and Forest City New York.

Forest City's plans unc…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…