Latest construction alert: overnight railyard deliveries for electrical substation, delayed, may start Feb. 22

According to the latest Atlantic Yards/Pacific Park Construction Alert, issued yesterday (some lead time) for the two weeks beginning Monday, February 15, beginning on Feb. 22, there will be overnight deliveries at the railyard for an electrical substation. 

Note that this was supposed to happen in January, then supposed to start this next Monday. There's been no explanation for the delay. So who knows if it will be pushed back again.

Saturday work may continue at B2 (461 Dean Street), B3 (38 Sixth Avenue), B11 (550 Vanderbilt), B14 (535 Carlton), as well as demolition work on two blocks. There could be weeknight work at B11 and B14 until 9 pm.

Below is new work listed, with the description verbatim.

B3 - 38 Sixth Avenue• Superstructure phase of construction will begin
• Inspection and installation of tower crane is pending Department of Buildings scheduling. A community notice will be distributed when details are finalized. [It was supposed to happen this weekend, but has been delayed]

LIRR Yard Activities - Block 1120 & 1121• Delivery and installation of the LIRR 38kV Substation, 5kV Substation, and Substation Control Buildings are expected to be completed during February 2016. Project deliveries of the equipment are expected to take place during overnight hours during the weeks of February 22th and 29nd; vehicles will access the site at Pacific and Vanderbilt and will be stored overnight in the Pacific Street  staging area. Installation of the substation equipment may require overnight, extended weekday work hours, and/or weekend hours to complete.

B11 – 550 Vanderbilt Avenue• Crawler crane will be removed during this reporting period. A community notice will be distributed
when details are finalized. [It's coming Monday]
• Elevator contractor has mobilized, begin work on elevator shaft.*

B14- 535 Carlton Avenue
• Installation of permanent generator will occur during this reporting period

B-15 (6th Ave and Pacific Street)• Soil characterization for B15 site will be done during this reporting period.