From the latest Construction Update: after-hours sewer connection work on Dean Street starts Monday after-hours (but how late?)
According to the latest Atlantic Yards/Pacific Park Construction Alert (bottom), issued Friday (appropriate lead time) for the two weeks beginning Monday, February 29, after-hours sewer connection work will occur along Dean Street near Sixth Avenue starting Monday.
That's for the B3 (38 Sixth Avenue) site at the southeast corner of the arena block. All work will be done after 6:30 pm, but no end time was specified in the alert, which was distributed by Empire State Development, the state authority overseeing/shepherding the project, after preparation by Greenland Forest City Partners.
Nor was there any information about noise or impact on traffic or pedestrians. The process should take about two weeks.
Saturday work may continue at B2 (461 Dean Street), B3, and B14 (535 Carlton). There could be weeknight work at B14 until 9 pm. Also, there will be weekend work in the Long Island Rail Road tunnel and rail yard. Hours were not reported.
Other new work is reported verbatim below.
B3 - 38 Sixth Avenue:
• Superstructure phase of construction will continue with the framing and pouring of the 1st floor.
• Overhead protection will be constructed at the Barclays Center loading dock area pending approvals
and permits.
B-15 (6th Ave and Pacific Street):
• Soil characterization and boring logs will continue during this reporting period.
That's for the B3 (38 Sixth Avenue) site at the southeast corner of the arena block. All work will be done after 6:30 pm, but no end time was specified in the alert, which was distributed by Empire State Development, the state authority overseeing/shepherding the project, after preparation by Greenland Forest City Partners.
Nor was there any information about noise or impact on traffic or pedestrians. The process should take about two weeks.
Saturday work may continue at B2 (461 Dean Street), B3, and B14 (535 Carlton). There could be weeknight work at B14 until 9 pm. Also, there will be weekend work in the Long Island Rail Road tunnel and rail yard. Hours were not reported.
Other new work is reported verbatim below.
B3 - 38 Sixth Avenue:
• Superstructure phase of construction will continue with the framing and pouring of the 1st floor.
• Overhead protection will be constructed at the Barclays Center loading dock area pending approvals
and permits.
B-15 (6th Ave and Pacific Street):
• Soil characterization and boring logs will continue during this reporting period.