Skip to main content

Vexing delays: Atlantic Avenue near Barclays Center will be constricted through late 2017, nearly twice as long as promised

Blue fence constricts three lanes. Photo: AY webcam
The traffic-clogging, pedestrian-endangering constriction of Atlantic Avenue outside the Barclays Center will continue nearly twice as long as previously predicted, near the end of 2017 instead of February 2016, as Greenland Forest City Partners completes work on a West Portal rail connection between the Vanderbilt Yard and the Atlantic Terminal LIRR station.

That delayed schedule was disclosed almost casually by Forest City Ratner executive Ashley Cotton last night at the periodic Atlantic Yards Community Update meeting held at the Shirley Chisholm State Office Building at 55 Hanson Place.

And it was backed up by Empire State Development (ESD), the state agency that oversees/shepherds the project.

The original timeline

Timeline announced in June 2014 for green roof and West Portal work
Green roof progress, delays

Construction of the arena's green roof, Cotton said, "is really close to being done," with nearly all the sedum installed, and officials "expect the crane to be gone in the month of October."

That actually represents two separate delays. As shown in the timeline above, the green roof was originally supposed to be finished in July 2015, with the last crane gone by June. Instead, the project was delayed, as I reported in February, in part because of weather.

This past June, at a Community Update meeting, Cotton said the Atlantic Avenue crane would be "gone this summer, that's our expectation." That didn't happen either.

Clogging Atlantic Avenue

Last night, Cotton said the crane removal "unfortunately" doesn't remove the MPT (maintenance and protection of traffic measures) on Atlantic Avenue.

"As a reminder," she said, "that really is the MPT for the West Portal work, and we tucked the crane for the arena green roof" into it. A small piece of Atlantic Avenue may become free near the arena entrance, she said, the the street will still be constricted.

She said the West Portal would be complete in 2017, thus allowing a more direct connection between the railyard, where cars are stored and serviced, and the transit hub. As shown in the timeline above, it was supposed to take 21 months--with a 19-month traffic detour--and be finished by February 2016. If it lasts until the end of 2017, the traffic detour will have lasted 41 months.

Had the West Portal been built as originally planned along with arena construction, it would have constricted traffic only ten months.

Transparency issues

"This goes to the question of openness and disclosure," commented Peter Krashes of the Dean Street Block Association. He referenced an ESD board meeting last November, when then-CEO Kenneth Adams lamented the narrowing of Atlantic Avenue and asked when the traffic issue would be resolved--and was told 2015.

"It's a construction project, and timelines change," stated Sam Filler, Director, Atlantic Yards Project, for ESD, offering an all-purpose defense.

"It's a two-year change on a major thoroughfare," countered Krashes.

Gib Veconi of the Prospect Heights Neighborhood Development Council asked for specifics about project completion.

"Towards the end" of 2017, responded Forest City executive Jane Marshall. "Almost when the yard is complete."

"About two years from now," Veconi said.

"That's very complex work," Marshall continued.

"I take your word for it," Veconi followed up. "My recollection, and it's a pretty clear recollection, is that originally the work was going to be done in spring of 2016... you may remember a pitch to get Democratic National Convention in there by the summer of 2016."

(So maybe it was good that the DNC didn't come, and some guy who warned that "the convention would be in a major construction zone" had a point.")
Cotton said she'd check on what changed, and suggested that in one past presentation on the railyard, "one of the dates was wrong that one of you guys caught." (It wasn't me.)

"There's nothing about the West Portal that's changed, I owe you guys a better explanation," Cotton said, pledging to discuss it at a future meeting.

"I've been listening to Forest City Ratner for 30 years," commented Regina Cahill, who heads the North Flatbush Business Improvement District. "I think you guys would get better at communicating."

Resident Pauline Blake, former president of the 78th Precinct Community Council, pointed out that the constricted avenue poses a hazard to "such fragile seniors" and "such young children. It's not a game, it's a reality." She expressed fear that the fatal traffic incidents near the Atlantic/Flatbush intersection would recur.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

This graphic, posted in November 2017, is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. Note the unbuilt B1 and the proposed shift in bulk to the unbuilt Site 5.

The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change. The project is already well behind that tentative timetable.

The previous graphic, from August 2017 (without the ghost B1)

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …