Skip to main content

Barclays Center green roof behind schedule, due September; Flatbush Avenue crane (and lane closing) coming in April; four cranes (!) around arena

Also see coverage of other issues raised at the Quality of Life meeting, including dangerous intersections, NBA All-Star Weekend preparations, and the huge green wall around most of the southeast block of the project site.

The green roof being installed on the Barclays Center--an exoskeleton aimed to beautify the view and also tamp down escaping noise--is several months behind schedule, not that representatives of arena developer Forest City Ratner will admit it.

Last night, at the periodic Atlantic Yards Quality of Life meeting hosted by Empire State Development, the state agency overseeing/shepherding the project, and developer Forest City Ratner, residents got an update from FCR external affairs executive Ashley Cotton.

Structural work on the arena should be completed in May, Cotton said, after a crane is placed on Flatbush Avenue, "probably towards the end of April." 

That's about five months late, though faster work at the final end of installation may make the overall project only two months late. While the delay has not been discussed in detail, Forest City Ratner CEO MaryAnne Gilmartin last week acknowledged that winter weather has proven "extremely challenging" for the roof work.

The original timeline

Note that, according to the project timeline (above) released last June, the Flatbush Avenue crane was supposed to be placed in January, and all cranes were supposed to be gone by the end of January.

Note that the Flatbush crane will necessitate the closing of a lane of traffic and likely additional traffic congestion. 

B2 crane at left, B3 center, Atlantic Avenue crane at right
Also note that, according to the original schedule, the Atlantic Avenue crane was supposed to be removed before the Flatbush Avenue crane was installed. 

Instead, it seems likely all three roof cranes will be in use, while the crane at the site of the B2 modular building, long placed, remains and may be in use by spring.

Finishing up

Now, "all [roof] cranes will be gone this summer, that's our expectation," Cotton said. That suggests a delay of at least five months from the original schedule.

"Everyone knows the crane on the B3 site needs to be gone to break ground by the end of June," she added, referring to the southeast corner of the arena block. Greenland Forest City Partners, the developer of the tower planned at that site, will be fined $5 million if they miss the deadline.

The installation of sedum--the grassy roof materials, as with the top of the subway entrance on the arena plaza-- will be done in September, Cotton said.

If so, that means they'd be catching up on a good part of the delay, since the sedum was supposed to be installed by July, two months before September.

"Cranes in many ways aren’t needed for the sedum," Cotton said. "They kinda get trucked up and then can be rolled out... so if you see the cranes going away, and we don't have a green roof that helps you understand how the structure gets done."

OK, but note that the original plan also cited a "sedum crane" for three of four months of the installation.

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.