Skip to main content

From the latest Construction Alert: more late shifts, plus a plan to begin deliveries at 6 am through the entire arena construction period

According to the latest two-week Atlantic Yards Construction Update (below, dated August 1) and prepared by developer Forest City Ratner and issued by the Empire State Development, there exists significant potential for second- and third-shift work at around the project site.

Also, the main contractor, Hunt Construction, has requested a permit to allow for deliveries to the arena site beginning at 6 am, rather than at 7 am, though arena completion in fall 2012. The rationale?
This work allows for an additional hour of deliveries to take place outside the neighborhood peak traffic patterns and reduce congestion and interference with the local traffic. The permit response is expected to be received this period. If granted, the intention is to continue to permit deliveries during this timeframe through to completion of the Arena.
There's certainly a logic, from the construction standpoint, since it would speed work. However, given that trucks can be noisy, and have idled in the neighborhood before official delivery hours, such a change could lead to significant disruption in the lives of neighbors.

That plan was not disclosed in the Final Environmental Impact Statement. Chapter 17, Construction Impacts, stated:
In accordance with city laws and regulations, construction work would generally begin at 7 AM on weekdays, with some workers arriving to prepare work areas between 6 AM and 7 AM. Normally, work would end at 3:30 PM. It is anticipated that the workday would be extended for specific trades to complete some specific tasks beyond normal work hours.
A delay

A material hoist, which according to the 7/18/11 Construction Update was supposed to be installed last month or this has been delayed:
Preparation for the erection/installation of a material hoist at the intersection of 6th Avenue and Pacific Street has been revised and is now projected to commence sometime in September.
Late work on the streets

Either in the next two weeks, or shortly after, work on the streets could run late:
Excavation for storm/sanitation/water services near the intersections of Dean & Flatbush as well as 6th & Pacific will commence during this reporting period or the next. These excavations (trenches) will be in excess of 25 feet below street level and will require tie-in to existing piping within both Dean Street and /or 6th Avenue. Permits are being submitted to borough agencies to allow the tie-ins and a maintenance and protection of traffic/pedestrians plans(s) is being prepared; installation will not occur until permits have been granted. A second and/or third shift is being considered to execute this work.

The piping for the storm/sanitary/and water services to the arena at 6th & Pacific as well as Dean & Flatbush is expected to start during this or the next reporting period. The tie-ins for this piping will require work in the street. A second and/or third shift is being considered to execute this work.
Work on the sidewalks

The update refers to sidewalk work connected with traffic changes:
The first element of the 2011 work includes the installation of curb extensions at the Pacific/4th Avenue Dean/Flatbush and Pacific/Flatbush intersections and the reversal of traffic from westbound to eastbound on Pacific between 4th and Flatbush Avenues. Permits for this work have been secured and work has commenced. During the next two week period curb extensions, lights, signals, signs and pavement striping will be installed to achieve the closure of the northbound traffic on 4th Avenue, north of Atlantic Avenue. This phase of the work is expected to take approximately 4 to 6 weeks.

In addition, completion of the curb extension at Pacific and Flatbush, which started last period, will continue as far as possible outside the sidewalk bridge in front of a private owner’s commercials building at 604 Pacific Street. The final sidewalk paving under the sidewalk bridge cannot be completed until the private owner makes repairs to his building and remove the protection. This phase of work is expected to be completed by the end of August.
Night and weekend work

The document reveals anticipated night and weekend work:
During this reporting period the following work will be performed either at night or during the weekend as noted. All work will be done pursuant to approved permits:Long Island Rail Road/Vanderbilt Yard/ Carlton Avenue Bridge:
o As of May 2nd, yard construction hours are 6am – 4:30pm.
o In addition, as of Saturday May 7, 2011, construction work will take place on Saturdays during the hours of 7am – 5:30pm for a period of at least three months.
Arena Site:
o Arena weekend work will be scheduled no later than close of business on the preceding Thursday, where make-up work due to weather or other delays makes it necessary. Saturday work is expected to continue for this reporting period.
o Subject to receipt of permits, a second shift may be continued throughout this reporting period, from 3 – 11 PM, Monday-Friday only. Also subject to receipt of permits, a third shift may be instituted during this reporting period, from 11 PM – 7 AM, Monday –Friday only.
NYC Transit Improvements:
o Temporary concrete road decking is substantially complete, however, in the event there is a need to do any related work, such work will be performed at night per DOT regulations. Traffic will be restored every morning according to DOT stipulations.
o Work related to demolition of BMT structure and below grade concrete, steel and MEP work may be conducted on Saturdays, August 6th and August 13th, during this reporting period. All such work will take place within the site.
Block 1129 – staging arena:o Contractors conducting night work may have cause to enter and exit this area as it serves as a staging and material/equipment storage area.
Off Site Mitigation work:
o Work taking place at Pacific/Flatbush and4th/Pacific will be done during the overnight pursuant to DOT permits. Work will be concluded by 6 AM so that related MPT is removed for the morning rush hour.
During the course of work, conditions may be encountered at the site which may warrant the need for night and/or weekend work. Work will be done pursuant to approved permits.
Atlantic Yards Construction Alert 8-1-2011

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…