Skip to main content

From the latest Atlantic Yards Construction Alert: work on raised Atlantic Avenue medians to begin in April, but unclear whether it will be by day or at night

Below are some excerpts from the latest two-week Atlantic Yards Construction Alert, dated 3/12/12 and released yesterday by Empire State Development after preparation by Forest City Ratner.

One highlight: work is expected to begin in April on the remaining traffic mitigation work, mostly the creation of raised medians along Atlantic Avenue from Flatbush Avenue to Vanderbilt Avenue. But it's unclear whether the work will be performed during what the alert calls "limited daytime, which will prolong the construction period, or at night between 10 pm and 6 am."

The decision will be made by the Department of Transportation's Office of Construction Mitigation and Coordination (OCMC).

Also, "construction of a tall retaining wall along the Vanderbilt Ave. end of the yard," between Atlantic Avenue and Pacific Street, should begin soon. The southbound traffic lane and adjoining sidewalk will be taken out of service--for how long it's not quite clear--when concrete trucks are present to pum concrete into the wall below.

"Orwellian, almost"?

The regular heading "Construction at the Arena Site Progresses as Scheduled" is "Orwellian, almost",
since it contains this sentence:
• Revisions to the perimeter construction fence are projected to begin this reporting period, in order to allow the site construction activity to ramp up.
Why Orwellian? Because the same sentence appeared in the previous Construction Alert, which suggests that construction is not progressing "as scheduled"--or that someone forgot to update the paperwork.

Also omitted in this report, but within the last report. was this:
The steel erector is expected to begin on the main entry canopy steel erection on or about March 26, 2012. Fabrication of this material has started.
So it may be delayed. Below, I've bolded the notable changes from the previous alert.

Steel Erection and Stadia Installation
• Primary (truss) roof steel erection has been completed. Secondary roof framing will continue during this reporting period. Preparation to erect the main entry canopy steel is expected to begin this reporting period.
Façade Installation
The façade subcontractor will continue to work a second shift as needed throughout this reporting period. Work may be performed on the 6th Avenue, Flatbush Avenue and Atlantic Avenue elevations on second shift.
Waterproofing & Fireproofing
Phase 1 of the permanent roofing will continue throughout this reporting period as weather allows. The lower roofs temporary protection is substantially complete and the west elevation high roof installation (Denglass Board, Insulating Board, Vapor Barrier and Rubber Membrane) will continue. The roofer should begin the east half of the arena high roof this reporting period.
Mechanical, Electrical, & Plumbing
The transformers have been placed in the ConEd vault. The first of the transformers has power to the line, or service side, and permanent power should be available to all transformers on or about March 19th.

The piping for the storm/sanitary/water services from the street mains to the arena at 6th and Pacific has been completed and the testing/inspection results submitted to DEP.

The construction fence at the ConEd vault was revised in an earlier period to allow ConEd and the Arena contractors to continue to conduct work related to the installation of transformers that will service the arena. ConEd continues to execute work at this location.
Interior Build-out
The delivery of the primary kitchen and concessions equipment is expected to start during this reporting period.
Subway Transit Canopy
The steel and concrete roof for the canopy is now complete along with the spray fireproofing. The contour slab has been completed. Work continues on the roofing.
Carlton Avenue Bridge
Carlton Avenue and Pacific Street MPT DOT permit is in place and the suspension of parking on the north side of Pacific Street running approximately 100 linear feet from the existing cross walk in a westerly direction is now in effect. This was done to accommodate the construction of the Carlton Ave. bridge abutment and the associated work on the approach slab and utility connections. As was done previously by direction of the NYCDOT, fliers were distributed and posted 48 hours in advance of the no parking rules going into effect.
• Concrete has been placed at the Pier #2 footing, base and center portion of the stem wall. Concrete placement for the balance of the stem wall will continue this reporting period.
East End (former Gasoline Station)
Construction of a tall retaining wall along the Vanderbilt Ave. end of the yard is set to begin once permits have been secured. Work will require that e west southbound traffic lane and adjoining sidewalk be taken out of service when concrete trucks are present from which will be pumped concrete into the wall below.
Track Work
Tracks Unlimited has started to deliver ballast material to the west end of the site (B1120) in preparation of the start of track installation in the yard. This work item will continue through the next 3 month period.
Replacement of Adjacent Water Mains and other Utility Work
Stormwater discharge at Flatbush Avenue is complete and approved. Work on the discharge at 6th and Pacific Streets was completed, approved and paved in the last 2-week period. The retention tank and pumping systems connected to the discharge will be inspected and tested during the upcoming two-week period.
Traffic Mitigation Site Work/Atlantic Avenue Medians
Work is expected to begin in April 2012 on the remaining traffic mitigation work, most of which is made up of raised medians along Atlantic Avenue from Flatbush Avenue to Vanderbilt Avenue. OCMC is reviewing the scope and location of the medians and will determine whether the work shall be performed during limited daytime, which will prolong the construction period, or at night between 10 pm and 6 am. If the work is done at night, mobile light units will be used to illuminate the work area. The arena block, Carlton Avenue Bridge reconstruction and DDC utility work between Carlton and Vanderbilt Avenues also take lanes out of service. Therefore, the median work must be scheduled block by block to coordinate with the other work schedules and MPT configurations. Because the work is a few feet directly above the LIRR tunnel into Atlantic Terminal, the means and methods must be reviewed and approved by the LIRR.
Arena Site Work
Installation of the underground drainage within the plaza area located at the tip of the site and the plaza located at the corner of Dean Street and 6th Avenue is substantially complete. The balance of the drainage will be completed as the work at the tip of Atlantic and Flatbush is completed in the Spring and Summer. A temporary asphalt working surface has been placed throughout the plaza. MPT along Dean Street and 6th Avenue will be repositioned in accordance with the approved DOT MPT Plan.
AY Construction Alert 3-12-2012

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Atlantic Yards/Pacific Park graphic: what's built/what might be coming + FAQ (post-dated pinned post)

This graphic, posted in January 2018, is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. Note the unbuilt B1 and the proposed shift in bulk to the unbuilt Site 5.

The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change. The project is already well behind that tentative timetable.

How many people are expected?

Atlantic Yards/Pacific Park has a projected 6,430 apartments housing 2.1 persons per unit (as per Chapter 4 of the 2006 Final Environmental Impact Statement), which would mean 13,503 new residents, with 1,890 among them in low-income affordable rentals, and 2,835 in moderate- and middle-income affordable rentals.

That leaves 8,778 people in market-rate rentals and condos, though let's call it 8,358 after subtracting 420 who may live in 200 promised below-market condos. So that's 5,145 in below-market units, though many of them won't be so cheap.

As …

The passing of David Sheets, Dean Street renter, former Freddy's bartender, eminent domain plaintiff, and singular personality

David Sheets, longtime Dean Street renter, Freddy's bartender, eminent domain plaintiff, and singular personality, died 1/17/18 in HCA Greenview Hospital in Bowling Green, KY. He was 56.

There are obituary notices in the Bowling Green Daily News and the Wichita Eagle, which state:
He was born in Wichita, KS where he attended public Schools and Wichita State University. He lived for many years in Brooklyn, NY, and was employed as a legal assistant. David's hobby was cartography and had an avid interest in Mass Transit Systems of the world. David was predeceased by his father, Kenneth E. Sheets. He is survived by his mother, Wilma Smith, step-brother, Billy Ray Smith and his wife, Jane all of Bowling Green; step-sister, Ellen Smith Alexander and her husband, Jerry of Bella Vista, AR; several cousins and step-nieces and step-nephews also survive. Memorial Services will be on Monday, January 22, 2018 at 1:00 pm with visitation from 10:00 am to 1:00 pm Monday at Johnson-Vaughn-Phe…

Some skepticism on Belmont hockey deal: lease value seems far below Aqueduct racino; unclear (but large?) cost for LIRR service

As I wrote for The Bridge 12/20/1, The Islanders Say Bye to Brooklyn, But Where Next?, the press conference announcing a new arena at Belmont Park for the New York Islanders was "long on pomp... but short on specifics."

Notably, a lease valued at $40 million "upfront to lease up to 43 acres over 49 years... seems like a good deal on rent for the state-controlled property." Also, the Long Island Rail Road will expand service to Belmont.

That indicates public support for an arena widely described as "privately financed," but how much? We don't know yet, but some more details--or at least questions--have emerged.

An Aqueduct comparable?

Well, we don't know what the other bid was, and there aren't exactly parcels that large offering direct comparables.

But consider: Genting New York LLC in September 2010 was granted a franchise to operate a video lottery terminal under a 30 year lease on 67 acres at Aqueduct Park (as noted by Gov. Andrew Cuomo).

As…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…