Skip to main content

Company fabricating metal arena facade shuts down; work was supposed to extend through May; no comment from Forest City at this time

The Whitestown, IN-based company that has been fabricating the weathered steel for the Barclays Center facade unexpectedly went out of business last week, raising questions about whether and when the additional steel needed would be delivered, and how the overall project timetable may be affected.

It's unclear how much of the steel has been fabricated and delivered by ASI Limited, but a considerable amount of facade work remains to be done. Some steel has been delivered to and is stored at the southeast block, Block 1129, as shown in the photo above, taken today by Tracy Collins.

A spokesman for developer Forest City Ratner said "we cannot comment at this time." The Empire State Development (ESD), the state agency overseeing Atlantic Yards, said it was a question for Forest City.

ESD at 5:30 pm today issued a two-week Construction Alert (prepared by Forest City) covering work beginning this week; it indicates continued work on the facade, and does not disclose anything about the facade fabricator.

Work extending through May

The Exterior Skin--which likely includes more than the metalwork--is not supposed to be completed until the "Early Finish" date of 5/13/12, according to a report from Merritt & Harris, construction monitor for the arena bond trustee.

(Photo from Patch slideshow/video.)

All subcontractors must be bonded in an amount equal to its subcontract price--$32.4 million in the case of ASI Limited, according to Merritt & Harris--but this is specialized work and presumably not easily transferred.

Indeed, the factory in Whitestown was customized specifically for this weatherization process. As the facade architect, SHoP, explained on its blog:
Earlier this year ASI Limited, the facade contractor for Barclays Center, flipped the switch on for their custom built 2500′ linear conveyor system designed to accelerate the weathering process for the 12,000 individual panels and supporting rails that make up the weathering steel portion of the facade designed by SHoP Architects. 
Surprise shutdown

ASI Limited officials, according to theIndyChannel, surprised 250 employees with the closure after Christmas; another report suggested the total was closer to 150.

"Regretfully, ASI, Ltd. is no longer profitable and is winding down the business," officials told employees.

However, owner Ken Smith also stated, "Management is currently reviewing its financial viability moving forward. It is hopeful that we can re-commence operations sometime in the near future."

Presumably those building the Barclays Center want very much to ensure that operations do re-commence, since there's a tight schedule to get the arena done.

What ASI Limited does

ASI Limited, according to the company's web site (page below, as well), was hired "to provide the 219,000 square feet of total building façade and enclosure." The work includes "a custom designed unitized mega-wall system that will include blast resistant curtain wall, insulated weather wall and exterior weather steel lattice screen."

The two-week Construction Alert issued 12/19/11 described the installation of erection clips and panels on the Flatbush Avenue and along the west elevations, as well as of erection clips along the 6th Avenue  and Dean Street elevations. A second shift was needed.

While the installation of façade panels at the street level and at the Upper Concourse levels on Atlantic Avenue was substantially completed, installation of the façade panels at the uppermost elevation was expected during December. However, in the Construction Alert issued today, it states that such work will be done "at a later date."

According to the Atlantic Yards web cam accessible through Atlantic Yards Watch, the side of the arena facing Sixth Avenue clearly lacks such panels, as shown in the photo above.

Previous problems

It's not the first bump in the road involving ASI Limited, which set up shop in October 2010 in a on Dean Street east of Flatbush, right next to a well-restored 19th-century house and across from the arena site.

(Photo by Tracy Collins)

In April, Forest City Ratner executive Bob Sanna said that the process of "weathering cycles" is behind, with efforts afoot to speed up the process.

Also in April, ESD said that a planned visual mock-up of the facade had been delayed for two months.

A message left today with ASI Limited was not returned.

ASILIMITED Barclays Center

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

This graphic, posted in November 2017, is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. Note the unbuilt B1 and the proposed shift in bulk to the unbuilt Site 5.

The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change. The project is already well behind that tentative timetable.

How many people are expected?

Atlantic Yards/Pacific Park has a projected 6,430 apartments housing 2.1 persons per unit (as per Chapter 4 of the 2006 Final Environmental Impact Statement), which would mean 13,503 new residents, with 1,890 among them in low-income affordable rentals, and 2,835 in moderate- and middle-income affordable rentals.

That leaves 8,778 people in market-rate rentals and condos, though let's call it 8,358 after subtracting 420 who may live in 200 promised below-market condos. So that's 5,145 in below-market units, though many of them won't be so cheap.

As…

The passing of David Sheets, Dean Street renter, former Freddy's bartender, eminent domain plaintiff, and singular personality

David Sheets, longtime Dean Street renter, Freddy's bartender, eminent domain plaintiff, and singular personality, died 1/17/18 in HCA Greenview Hospital in Bowling Green, KY. He was 56.

There are obituary notices in the Bowling Green Daily News and the Wichita Eagle, which state:
He was born in Wichita, KS where he attended public Schools and Wichita State University. He lived for many years in Brooklyn, NY, and was employed as a legal assistant. David's hobby was cartography and had an avid interest in Mass Transit Systems of the world. David was predeceased by his father, Kenneth E. Sheets. He is survived by his mother, Wilma Smith, step-brother, Billy Ray Smith and his wife, Jane all of Bowling Green; step-sister, Ellen Smith Alexander and her husband, Jerry of Bella Vista, AR; several cousins and step-nieces and step-nephews also survive. Memorial Services will be on Monday, January 22, 2018 at 1:00 pm with visitation from 10:00 am to 1:00 pm Monday at Johnson-Vaughn-Phe…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…