Skip to main content

Company fabricating metal arena facade shuts down; work was supposed to extend through May; no comment from Forest City at this time

The Whitestown, IN-based company that has been fabricating the weathered steel for the Barclays Center facade unexpectedly went out of business last week, raising questions about whether and when the additional steel needed would be delivered, and how the overall project timetable may be affected.

It's unclear how much of the steel has been fabricated and delivered by ASI Limited, but a considerable amount of facade work remains to be done. Some steel has been delivered to and is stored at the southeast block, Block 1129, as shown in the photo above, taken today by Tracy Collins.

A spokesman for developer Forest City Ratner said "we cannot comment at this time." The Empire State Development (ESD), the state agency overseeing Atlantic Yards, said it was a question for Forest City.

ESD at 5:30 pm today issued a two-week Construction Alert (prepared by Forest City) covering work beginning this week; it indicates continued work on the facade, and does not disclose anything about the facade fabricator.

Work extending through May

The Exterior Skin--which likely includes more than the metalwork--is not supposed to be completed until the "Early Finish" date of 5/13/12, according to a report from Merritt & Harris, construction monitor for the arena bond trustee.

(Photo from Patch slideshow/video.)

All subcontractors must be bonded in an amount equal to its subcontract price--$32.4 million in the case of ASI Limited, according to Merritt & Harris--but this is specialized work and presumably not easily transferred.

Indeed, the factory in Whitestown was customized specifically for this weatherization process. As the facade architect, SHoP, explained on its blog:
Earlier this year ASI Limited, the facade contractor for Barclays Center, flipped the switch on for their custom built 2500′ linear conveyor system designed to accelerate the weathering process for the 12,000 individual panels and supporting rails that make up the weathering steel portion of the facade designed by SHoP Architects. 
Surprise shutdown

ASI Limited officials, according to theIndyChannel, surprised 250 employees with the closure after Christmas; another report suggested the total was closer to 150.

"Regretfully, ASI, Ltd. is no longer profitable and is winding down the business," officials told employees.

However, owner Ken Smith also stated, "Management is currently reviewing its financial viability moving forward. It is hopeful that we can re-commence operations sometime in the near future."

Presumably those building the Barclays Center want very much to ensure that operations do re-commence, since there's a tight schedule to get the arena done.

What ASI Limited does

ASI Limited, according to the company's web site (page below, as well), was hired "to provide the 219,000 square feet of total building façade and enclosure." The work includes "a custom designed unitized mega-wall system that will include blast resistant curtain wall, insulated weather wall and exterior weather steel lattice screen."

The two-week Construction Alert issued 12/19/11 described the installation of erection clips and panels on the Flatbush Avenue and along the west elevations, as well as of erection clips along the 6th Avenue  and Dean Street elevations. A second shift was needed.

While the installation of façade panels at the street level and at the Upper Concourse levels on Atlantic Avenue was substantially completed, installation of the façade panels at the uppermost elevation was expected during December. However, in the Construction Alert issued today, it states that such work will be done "at a later date."

According to the Atlantic Yards web cam accessible through Atlantic Yards Watch, the side of the arena facing Sixth Avenue clearly lacks such panels, as shown in the photo above.

Previous problems

It's not the first bump in the road involving ASI Limited, which set up shop in October 2010 in a on Dean Street east of Flatbush, right next to a well-restored 19th-century house and across from the arena site.

(Photo by Tracy Collins)

In April, Forest City Ratner executive Bob Sanna said that the process of "weathering cycles" is behind, with efforts afoot to speed up the process.

Also in April, ESD said that a planned visual mock-up of the facade had been delayed for two months.

A message left today with ASI Limited was not returned.

ASILIMITED Barclays Center

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

"There is no alternative": DM Glen on de Blasio's affordable housing strategy

As I've written, Mayor Bill de Blasio sure knows how to steer and spin coverage of his affordable housing initiatives.

Indeed, his latest announcement, claiming significant progress, came with a pre-press release op-ed in the New York Daily News and then a friendly photo-op press conference with an understandably grateful--and very lucky--winner of an affordable housing lottery.

To me, though, the most significant quote came from Deputy Mayor Alicia Glen, who, as the Wall Street Journal reported:
said public housing had been “starved” of federal support for years now, leaving the city with fewer ways of creating affordable housing. “Are we relying too heavily on the private sector?” she said. “There is no alternative.” Though Glen was using what she surely sees as a common-sense phrase, it recalls the slogan of a politician with whom I doubt de Blasio identifies: former British Prime Minister Margaret Thatcher, a Conservative who believed in free markets.

It suggests the limits to …