Skip to main content

New report: for three months, arena has been (slightly) behind schedule; completion date for arena nudged back; site work could continue almost to Jay-Z concert date

Delays are taking their toll on Atlantic Yards construction, with new data from November indicating--for the first time--that the arena is now behind, and had been slightly behind for three months.

Apparently as a consequence, the substantial completion date of the arena has been pushed back a week to 8/30/12, and the substantial completion date of site work (landscaping, trees, sidewalks, bollards, etc.) pushed back a month to 9/25/12, just three days before Jay-Z is supposed to inaugurate the Barclays Center.

The information comes from the latest Site Observation Report, based on a visit of 11/22/11 and documents made available on 12/20/11, from Merritt & Harris, the real estate consultant to the arena PILOT Bond Trustee.

(The substantial completion date last April was nudged back two weeks from 8/12/12 to 8/27/12, but in October was nudged forward to 8/23/12.)

Cause for worry?

The report, dated 1/4/12, indicates that work seems to be proceeding appropriately. Confoundingly, it does not acknowledge in its text that the arena is behind, as a chart indicates.

Construction progress, based on cash flow, is behind 1.23%, a relatively small figure. However, given that the arena has long been ahead of schedule, that surely has provoked concern, as well as second shifts to get the work done.

Though the Barclays Center displays significant structural and exterior work, as of November, the arena was still only about half-finished, in terms of cash flow.

The Merritt & Harris report, dated 12/27/11, was completed before news surfaced of the shutdown of ASI Limited, the firm fabricating the custom panels for the arena exterior; the firm's owner left open the possibility of a reopening.

The report also acknowledges that the associated Transit Connection is a week late, though that project likely has much more leeway, given scheduled completion on 4/1/12.

And there are other indications of a slowdown. The Final Completion Date for the project, involving punch list work and subcontractor close-outs, was in the previous month's report indicated as 3/8/13; now, it could be extended nearly three months,  to 5/30/13.

Also, the latest report indicates the expectation of a GMP2 (Guaranteed Maximum Price 2), which both offers an early completion bonus (July 2012) and seemingly contemplates additional delays.
That report has apparently been issued but not made public.

Contradictory, confusing information

The Merritt & Harris report is contradictory and confusing in places. For example, the text of the document indicates that the arena is on schedule:

But that is contradicted by the chart and other data in the report. The highlighted part of the chart and the highlighted statistics (click to enlarge) indicate that actual cash flow has lagged estimated progress.

It's also the first time that Merritt & Harris has revealed any delays in arena construction (note the negative percentages on the bottom line).

The consultant did not explain in yesterday's report why delays had not been previously reported, but apparently there were errors in the chart accompanying the previous report (below), issued 12/2/11.

Note that both the chart and the statistics offered two separate notations for the month of September 2011 and that neither the September 2011 nor October 2011 statistics in the two charts match.

The Transit Connection

The Transit Connection has been behind for three months. The document at one point states:
The construction term of 20 months (August 2, 2010-April 1, 2012) is reasonable, but, due to early delays with approval of the test piles, had slipped by approximately 1 week.
At another point, it states:
The construction term of 20 months (August 2, 2010-April 1, 2012) is reasonable, but, due to early delays with approval of the test piles, had slipped by approximately 1 month.
Both are misleading, as I wrote two months ago: the "early delays with approval of the test piles" did not cause ongoing slippage in the Construction Schedule, since the project was able to return to schedule thanks to "excavation and demolition work."

After omitting the graphic regarding the Transit Connection last month, this month's report does contain such a graphic. It indicates that the Transit Connection is more than 78% done, in terms of cash flow, so it's in the home stretch. But it should be more than 85% done.


Finally checking on that Deficiency

In my 12/7/11 post, I noted that a section in the report headed Deficiency indicates, as in predecessor reports, that some concrete compression test results have been found to be deficient, but also leaves things murky, given that expected 56-day testing presumably was complete as of June 2011.

The latest report finally follows up, noting that a letter has been requested from the Structural Engineer.

ASI Limited

That chart below on subcontracts indicates that the contract with ASI Limited for the exterior facade, at $32.4 million, was considerably below the $39.2 million originally budgeted by the general contractor.

Did ASI Limited offer a low bid to get the work? If so, is that part of the firm's financial troubles? Both of those questions are speculative, as of now, but worth consideration.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

This graphic, posted in November 2017, is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. Note the unbuilt B1 and the proposed shift in bulk to the unbuilt Site 5.

The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change. The project is already well behind that tentative timetable.

The previous graphic, from August 2017 (without the ghost B1)

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …