Skip to main content

From the latest Construction Alert: at railyard, weekday double shifts; railyard flood lights on until 11 pm through Carlton Avenue Bridge replacement (next summer!)

The latest two-week Atlantic Yards Construction Alert, dated 12/19/11, was distributed today by Empire State Development (after preparation by developer Forest City Ratner).

Notable is that railyard work will proceed on double shifts during the weekdays along with Saturdays and selected Sundays, all in the name of "overall schedule maintenance," aka "staying on time." The previous alert indicated extra work only on weekends.

Also, it seems quite possible that floodlights at the railyard will be illuminated until 11 pm for many months, through next summer, as "Yard Flood Lights will be turned on at 6am and from dusk to 11:00 pm, during double shifts through the completion of the Carlton Avenue Bridge replacement, as needed."

The bridge is supposed to be finished before the arena opens in August 2012, though no firm schedule has been announced.

The text below is excerpted from the latest document (bottom), with the bolded text indicating what's new compared to the previous alert.

Deliveries & Site Access
One of the two larger steel erection cranes inside the arena has been demobilized and replaced by a hydraulic crane set up on the 6th Avenue elevation between Pacific and Dean.
Steel Erection and Stadia Installation
• A second shift was implemented on December 6th to demobilize one of the steel erection cranes. The need for a second shift crew will be re-evaluated throughout this period. Some weekday overtime may be needed and work on Saturdays will continue.
• Intumescent (fireproof) painting of the structural steel where required as an alternative to spray on fireproofing will continue on a second shift operation as needed and as weather allows during this reporting period.
Façade Installation
The façade subcontractor will resume a second shift on December 19t and continue the second shift as needed throughout this reporting period. Work may be performed on the Flatbush Avenue and 6th Avenue elevation on this shift.
• The installation of façade panels at the street level and at the Upper Concourse levels on Atlantic Avenue has been substantially completed. Contractor will return to install the façade panels at the uppermost elevation during December and in the area of the material hoist at a later date.
Waterproofing & Fireproofing
The waterproofing of the interior walls of the east storm water retention tank should resume this reporting period. This work may be performed on a second shift.
Mechanical, Electrical, and Plumbing
The piping for the storm/sanitary/water services to the arena at 6th & Pacific has been cancelled for this reporting period, due to site constraints (access at the main gate). The Dean & Flatbush piping is has also been cancelled for this reporting period. The tie-ins for this piping will require work in the street. -- specifics of where will be provided at such time when the work resumes. A second and/or third shift is being considered to execute this work, as well as weekend work.
Interior Build-Out
Precast concrete stadia erection of the upper seating bowl was completed during the last reporting period at Blocks 10-12 (Dean Street elevation). Precast erection will resume within the lower bowl seating area following completion of roof erection.
Work outside the Fence
Permits have been secured for the portions of the street immediately adjacent to the “Tip” of the project area. The southern eastbound lane of Atlantic Avenue has now been taken behind an expanded MPT in order to facilitate the removal of the planking/decking to be removed and the installation of temporary roadway restoration. A pathway for the new water main has been coordinated with the utility team and will now been constructed. A substantial amount of the roadway plank has now been removed. This will now permit the next phase of the water main installation to take place which is scheduled for the beginning of the year. This expanded MPT, noted above, has been approved by DOT.
Subway entrance
Track Outages (General Orders)
• IRT and BMT Tunnel inspections have taken place and the tunnel repair work is now substantially complete in both the IRT and BMT. Minor repair and cleanup work will occur on selective evenings under scheduled NYCT flagging protection.
Railyard work
Drilling – Support of Excavation, & Tiebacks,
• Drilling of tiebacks will continue at the east end of the yard (Block 1121). These tiebacks are drilled by a small rig, and are required at several elevations as excavation and lagging continue to the final depth of the yard sub-grade. Tieback drilling and placement of the attendant wood lagging will continue for the next month, as they go together with excavation. Posillico/Tully has started the forming of the foundations for the new car shop wall and the new east lead track wall. This work will be ongoing for the next few months.
Carlton Ave Bridge
• Posillico/Tully has commenced work to excavate the area of the car shop exterior wall location to set forms to install rebar and pour concrete for the new car shop wall foundation. Work will continue west to east in 200 foot sections until the foundation is completed. Upon completion of the foundation, work related to the forming and pouring of the wall will commence. All work is located within Block 1121 and will be ongoing for the next few months.
Railyard Schedule Maintenance
• Due to the need to expedite all of this work for overall schedule maintenance, it will be progressed on double shifts during the weekdays along with Saturdays and selected Sundays& holidays.
Yards Lights
• During the week, to facilitate early start and late finish of work, Yard Flood Lights will be turned on at 6am and from dusk to 11:00 pm, during double shifts through the completion of the Carlton Avenue Bridge replacement, as needed.
Replacement of Adjacent Water Mains and other Utility Work
Stage One began in early August. The first work included the installation of a distribution water main along the sidewalk of Flatbush, north of Atlantic. The work is being done at night (10 pm to 6 am) and requires partial closure of the sidewalk and the curb lane of traffic during the work hours. The work will take two to three months in this location and then will move on southward and cross Flatbush. The bus stop at the west side of Flatbush, north of Pacific, has been removed by NYC DOT, per the approval of NYCTA. The trench for most of the work in the Flatbush sidewalk is completed and plated. The contractor will continue for the next 3 to 4 weeks. Steel pipe was installed, welded and partially backfilled along the northern part of the zone.

Anticipated Nighttime & Weekend Work
During this reporting period the following work will be performed either at night or during the weekend as noted. All work will be done pursuant to approved permits:
• Long Island Rail Road/Vanderbilt Yard/ Carlton Avenue Bridge:
o All weekdays days all locations in the yard: 6:00AM to 11:00PM
o Saturdays as required: 7:00 AM to 11:00 PM
o Sundays and Holidays as required: 8:00AM to 11:00PM
o The weekend work being performed could be in any area of the yard, and within MPT areas for which permits are on hand.
o The work hours will remain in place for a minimum of the next three months.
• Arena Site:
o Arena weekend work will be scheduled no later than close of business on the preceding Thursday, where make-up work due to weather or other delays makes it necessary. Saturday work is expected to continue for this reporting period.
o Subject to receipt of permits, a second shift shall be continued throughout this reporting period, from 3 – 11 PM, Monday-Friday only. Also subject to receipt of permits, a third shift may be instituted during this reporting period, from 11 PM – 7 AM, Monday –Friday only.
o Hunt has been granted a permit to allow for deliveries from 6 AM to 7 AM to the Arena site from the dispatch center. This work allows for an additional hour of deliveries to take place outside the neighborhood peak traffic patterns and reduce congestion and interference with the local traffic.
o The second shift arena contractors are noted within the arena summary above.
• NYC Transit Improvements:
o Temporary concrete road decking will now be removed as noted above. Such work will be performed at night per DOT regulations. Traffic will be restored every morning according to DOT stipulations.
Work related to the BMT structure and below grade concrete, steel and MEP work may be conducted on Saturdays December 10th and 17th, during this reporting period.
• Arena Site Work:
o Underground utility work may occur within the site at the main plaza. Work will be conducted during the hours of 8 A.M. to 4 P.M., subject to NYCDOB permits

Atlantic Yards Construction Alert 12-19-2011

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.