Mockup of weathered steel façade panels for arena delayed two months, should be delivered in mid-May

Remember how Forest City Ratner VP for Construction Bob Sanna said that arena subcontractors were behind on producing the pre-weathered steel for the Barclays Center exterior?

Well, another aspect of that project seems to be behind. According to the latest ATLANTIC YARDS CONSTRUCTION UPDATE, Weeks of April 25, 2011 through May 8, 2011, produced by Forest City Ratner and distributed by the Empire State Development Corporation:
The excavation and concrete footing placement for a long term but temporary visual mockup of the weathered steel façade panels has been completed at 752 Pacific Street. The mockup panel delivery and placement of the footing was originally expected to be completed during the reporting periods covering March 7th through March 25th, however the delivery has been revised to mid-May.