DEIS dismisses Coney Island arena option

What happened to the Coney Island site next to Keyspan Park for the proposed Brooklyn arena? After all, that was Borough President Marty Markowitz's original idea, which he maintained fondly through early 2003. (Graphic from the Brooklyn Papers 1/31/04).

Despite that, the Empire State Development Corporation, in the Project Description chapter of the Draft Environmental Impact Statement, dismisses the much-discussed Coney option, thanks to project guidelines supplied by developer Forest City Ratner.

Feasibility study

The DEIS cites a 1974 city-sponsored preliminary feasibility study for the Brooklyn Sports Complex, a 15,000-seat arena that could accommodate professional basketball and other sports, and also supply sports facilities for local school and college athletic programs, and community athletic facilities. Multiple sites were suggested, especially those around Downtown. The DEIS recounts:
Of the five downtown sites considered, plus Fulton Ferry, only two appeared to meet the key criteria for size and accessibility. Both sites were listed in ATURA. One is the current site of the Bank of New York Tower and the two shopping centers: Atlantic Center and Atlantic Terminal. The other is the site currently being proposed for the Atlantic Yards Arena. In the 1974 report, the arena site extended from the corner of Flatbush and Atlantic Avenues eastward along Atlantic Avenue to Carlton Avenue. The site extended southward along Flatbush Avenue to Dean Street, continued eastward to 6th Avenue, then northward to Pacific Street and eastward to Carlton Avenue. In short, the site encompassed the arena block and Block 1120.(Emphasis added.)

Note that the 9.5-acre site (right, in red) that was proposed for the arena is not the same as the 22-acre site proposed for the Atlantic Yards project, which would incorporate two large blocks east of Carlton Avenue to Vanderbilt Avenue, and also encompass the streetbed of Pacific Street. The project also would include a rectangle of land 100 feet east of Sixth Avenue between Pacific and Dean streets, as well as Site 5, the wedge west of Flatbush Avenue where it meets Atlantic and Fourth avenues, and Pacific Street.

What's different

The DEIS continues:
The desire for a first-class professional team continues to be strong in Brooklyn. The overall benefit of an arena for such a team as a focal point for investment and development in Downtown Brooklyn remains an opportunity. The site that could accommodate such development, identified more than 30 years ago, is still underutilized today. What is different now is the presence of a developer and team owner willing to locate an arena and related development on the project site.

Note the difference, again, between the "project site" and the "arena site." And also note that had the site been put out for bid, many developers might have made proposals.

Sports facilities themselves are not necessarily spurs to development and investment; the main reason the Brooklyn arena is projected as successful is that it would absorb revenues from New Jersey, current home to the Nets.

Sites considered--and dismissed

The DEIS states that Forest City Ratner checked out other sites in Brooklyn, under the following siting criteria:
• The site should be large enough to accommodate an arena with a minimum footprint of 240,000 sf. In addition, the project site footprint should also allow for other mixed-use development. Recent experience with new arenas, such as the MCI Arena in Washington, D.C., and San Diego’s PETCO Park (the signature component of its “Ballpark District”), has shown that these facilities thrive in combination with a strong mix of urban land uses, e.g., offices, shops, restaurants, and housing.
• The site should be readily accessible to mass transit, which could serve the arena patrons, workers, residents, and other visitors who would travel to the site regularly.
• The site should be close to or within a Central Business District, so that the office component of the mixed-use development would add to the critical mass of business activity.
• The site should have access to appropriate infrastructure—transportation, roads, sewer, water, etc.—to support the mixed-use development.
• The site should be large enough and close enough to major arterial roadways to accommodate truck deliveries for a range of arena events.
• The site shape and size should be adequate to provide security and access control around and beneath the arena and related development.


Note that Coney Island would seem to fit nearly all of these criteria, except for the item regarding a Central Business District (CBD). But, as I've pointed out, the office component of the Atlantic Yards plan has diminished by two-thirds, so proximity to a CBD would be less crucial. In Coney Island, the mixed-use aspect could emphasize entertainment and recreation.

Indeed, Thor Equities has recently proposed a 10-acre condo/hotel/entertainment venue, though the renderings released (right) were apparently preliminary.

What about Coney?

The DEIS dismisses the sites considered in the 1974 study. The Brooklyn Navy Yard would displace active businesses. Other sites would be too small or are no longer available. The Coney Island site is unavailable, because it "is now home to KeySpan Park."

That was indeed the original site proposed. However, after KeySpan park was announced, local advocates, including Borough President Markowitz, shifted their sights to another site, next door in the vast parking lot serving the antiquated Abe Stark rink, as noted in the top graphic. That effort goes unmentioned in the DEIS.

The AY site?

The DEIS winds up:
This leaves only Site 1a, which, as noted above, covers the proposed arena site plus the block on the south side of Atlantic Avenue between 6th Avenue and Carlton Avenue. Although ultimately project planners concluded that this site plus the two blocks to the east (from Carlton to Vanderbilt Avenues between Atlantic Avenue and Dean Street) would be best for the proposed project, they considered variations in this general location in response to community suggestions.

This fudges the difference between the previous plan and the Atlantic Yards plan, which would be more than twice as big. The Atlantic Yards plan encompasses two large blocks east of Vanderbilt Avenue between Pacific and Dean streets so the developers could build housing.

What about variations?

Forest City Ratner, the DEIS says, did consider building the arena at another nearby location:
One was to build the arena on a span over Atlantic Avenue. This would require that the base of the arena be at least 20 feet above street level, so that the entire structure would appear larger than an at-grade building and would hover over the street and be visible from long distances. The elevation of the arena would create serious operational problems—loading/unloading would be a major hardship and keeping the arena secure when it sits above an active major thoroughfare would also be problematic.

The concern about security for an arena built over Atlantic Avenue is legitimate; after all, an arena would be a target. But the DEIS doesn't discuss a simpler solution that was also proposed and dismissed: building the arena at the site of the Atlantic Center mall. Forest City Ratner apparently plans to build towers over that property.

The DEIS continues:
The project planners also considered the possibility of building the arena at grade in the bed of Atlantic Avenue while relocating the street to the south above the Vanderbilt Yard. While the challenge of building over an active railway tunnel and relocating major utilities could be met, this alternative would not produce a footprint large enough for both the arena and related development. The realignment of the street would break up the site, so that development parcels would be fragmented. This arrangement would also inhibit implementation of a comprehensive master plan, with cohesive design and a site plan that provides substantial contiguous publicly accessible open space. Furthermore, this realignment would bring Atlantic Avenue, one of the borough’s major thoroughfares, farther from the commercial uses to the north and closer to the residential neighborhoods to the south.
It was clear after consideration of alternative sites that only the project site would be large enough to accommodate a cohesive, comprehensive development containing the arena and a mix of synergistic uses, while offering extraordinary transportation access, proximity to a Central Business District, and substantial publicly accessible open space designed to foster pedestrian activity and promote connections with the surrounding neighborhoods.


This reads like a predetermined conclusion. After all, open space that "promote[s] connections with the surrounding neighborhoods" can only do so at a site that serves as a transition between neighborhoods rather than a site within a neighborhood.

Alternatives & questions

However, even within the general plan proposed, there are alternative locations or configurations for the arena--moved slightly east, so streets would not be demapped, as the Municipal Art Society has proposed, or moved toward Vanderbilt Avenue, as in Doug Hamilton's Pacific Plan. But the DEIS is written to reach certain conclusions, so the conclusions are not unexpected.

It could just have easily acknowledged that the publicly accessible open space is too little for the expected population and that the demapping of streets might stymie connections with the surrounding area.

And the size of the project may have just as much to do with selling sufficient market-rate housing to ensure the developer's profits than to "accommodate a cohesive, comprehensive development."

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

Click on graphic to enlarge. This is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change, and the project is already well behind that tentative timetable.


Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…