Skip to main content

In Our Time Press, questionable coverage of the latest lawsuit

The notorious Stephen Witt, now writing for Bed-Stuy-based Our Time Press, has produced his coverage of the lawsuit filed earlier this week: Another Atlantic Yards lawsuit: Allegations that training program does not bring union jobs as promised.

There's no mention of the issue of unpaid wages, but a "he said, she said" focus on whether jobs and union cards were promised to 36 trainees in a highly selective program. Witt writes:
But both FCR and BUILD officials said union cards were never promised, and charged James, state Sen. Velmanette Montgomery and longtime foes of Atlantic Yards are behind the lawsuit. They also said their opposition is a major contributing force behind the lack of jobs as promised by the CBA.

...[BUILD's James] Caldwell said his organization has placed close to 400 people from the community with jobs, many on other FCR developments, and that the downturn in the economy has caused the build-out of the Atlantic Yards project to be much slower.

...[Forest City spokesman Joe] DePlasco said there are about 800 people currently working on the Atlantic Yards project...

Of these workers, 410 are city residents including 174 from Brooklyn, of which 67 are from Central Brooklyn...

DePlasco said of the 36 people that went through the BUILD pre-apprenticeship training program, 19 were working in property management, retail or construction-related positions as of September this year.
All that is irrelevant to the question of whether the 36 people, who began the program in August 2010, were promised jobs and union cards. After all, some of those 19 people have jobs at McDonald's.

A "thought" or a promise?

Witt ends the article thusly:
But plaintiff Maurice Griffin, 23, said he took the training because he thought it meant he would get a construction union card. He finally got one on his own with the carpenters union.
I posted a comment (not yet live):
Here’s more coverage, with video, that provides some facts and context left out above:

For example, the article above states “plaintiff Maurice Griffin, 23, said he took the training because he thought it meant he would get a construction union card.”

He said explicitly that it wasn’t merely his “thought.” He said, “They guaranteed me a union card, They said it’s not a question of whether we have it, but whether you complete the program. And I completed it. I came every time, early. I did my work. I’m here to let everybody know I’m not going to stand for this.”

Comments

  1. Here's a link to the PDF of Our Time Press, which includes my column on Atlantic Yards, and which mentions you in regards to your ongoing coverage.


    http://www.ourtimepress.com/upload/November172011sm

    ReplyDelete
  2. Stephen Witt writes that that "For doing this"-consistently seeking out the views of project supporters--" opponents of the project and their media mouthpieces, including Atlantic Yards Report blogger Norman Oder, continually blasted me."

    Um, I'm a journalist, and that means that, when Stephen Witt writes nonsense
    http://atlanticyardsreport.blogspot.com/2008/05/are-ay-foes-real-land-grabbers-courier.html
    he deserves to get called on it.

    ReplyDelete

Post a Comment

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…