From the latest Construction Update: after-hours weekday work continues; towers make progress

The latest Atlantic Yards/Pacific Park Construction Update (bottom), covering the two weeks beginning today, was circulated Friday, 10/30/20 at 12:15 pm (lead time) by Empire State Development (ESD) after preparation by Greenland Forest City Partners. 

Continuing the change announced in the previous update regarding after-hours work at the B4 (18 Sixth Ave.) and B15 (37 Sixth Ave., 662-664 Pacific St.) sites, a variance allows weekday work until 9 pm, and for deliveries, garbage removal, hoist and crane operation to start as early as 6 am, rather than the official workplace start time of 7 am. 

After-hours work on Saturday, when permits are received, are for work starting at 9 am until 5 pm. 

Other progress

At B15, the exterior brick facade of the building and window installation has progressed three more floors, through the 17th floor. 

At B4, the concrete superstructure program has progressed five more floors, through the 40th floor. The curtainwall has been installed three more floors, through the 23rd Floor. 

Meanwhile, punch-list closeout work continues at the railyard, and minor facade remedial work continues at B3, 38 Sixth Avenue. 

At the B12 & B13 sites (615 Dean and 595 Dean), excavation and foundation work, including delivery of equipment and materials, removal of soil materials, installation of soldier piles and foundation materials continues. 