From the latest Construction Update: after-hours weekday work expands at B4 and B15, from 6 am to 9 pm
There's a significant change from the previous update regarding after-hours work at the B4 (18 Sixth Ave.) and B15 (37 Sixth Ave., 662-664 Pacific St.) sites. While previously work lasted until 7 pm on weekdays, now it officially ends at 6 pm--but an after-hours variance allows work until 9 pm.
Similarly, while the weekday work officially starts at 7 am, an after-hours variance allows deliveries, garbage removal, hoist and crane operation to start as early as 6 am.
One adjustment slightly limits specially permitted weekend work. On Saturdays, instead of work starting at 8 am, it will start at 9 am, again lasting until 5 pm.
Construction progress
Also, the update indicates some benchmarks. The exterior brick facade of B15 and window installation has progressed through the 14th floor, a little more than halfway up the 26-story building.
At B4, the concrete superstructure program has progressed through the 35th floor of a 51-story building. Topping out of the building is expected in early December. The curtainwall has been installed through the 20th floor.