Skip to main content

From the Response to Comments: the conundrum of an unfinished Phase 1, plus unexamined impacts of undisclosed arena elements

I've been going through the Response to Comments document produced by Empire State Development to accompany the release last month of the Final Scope for a Supplementary Environmental Impact Statement. (The SEIS is coming this spring, and more information may be announced at the ESD board meeting tomorrow.)

A judge ordered a SEIS regarding Phase 2 of the project, but Phase 1 isn't finished.

So that sets up a conundrum: the baseline condition will assume Phase 1 is finished, but...  it's not. So the construction impacts of the remaining Phase 1 buildings will also be analyzed. But Phase 1 as construction will be assumed to be part of the background condition.

No, it doesn't quite make sense to me, either.

What's the baseline?

The comment:
Comment 18: The baseline should start now, not at the time of the completion of all of Phase I. There is no logic to moving the baseline to a point the project agreements don’t even require to exist, especially given changes to the project and its background effect on the first phase of construction. (Krashes)
The response:
Response: The SEIS is being undertaken pursuant to the Court Order to evaluate the potential environmental impacts of a prolonged delay in the completion of Phase II of the Project. Phase I has been approved and is under construction. Therefore, the Draft Scope of Work notes that for all areas of analysis Phase I of the Project will be assumed to be constructed and to be part of the background condition. Thus, all Phase I elements of the Project, including associated mitigation measures as well as any recent changes to the traffic network, will be assumed as part of the baseline conditions for the Future Without Phase II (2035), and therefore the effects of Phase I will be accounted for in the analysis. In the analysis of construction impacts of Phase II of the Project, the SEIS will take into account the potential for some overlap in the construction of certain Phase I and Phase II buildings. In describing the Project, the SEIS will summarize the status of Phase I construction, and the assumptions made with respect to the construction sequences and schedules analyzed.
Another comment:
Comment 70: The baseline should start now, not at the time of the completion of Phase I. Even if the Phase I project is completed in full, the project agreements enable the construction of Phase I to overlap with Phase II in multiple scenarios. (Brooklyn Speaks)
The response:
Response: As described in the Draft Scope of Work, Phase I of the Project will be assumed to be constructed and to be part of the background condition. This is consistent with the Court’s Order that the SEIS assess the potential for impacts associated with a prolonged schedule for the construction of Phase II of the Project. Any potential overlap between Phase I and Phase II will be reflected in the construction schedules that will be developed for Phase II of the Project under the Extended Build-Out Scenario.
What about B1 and Site 5 towers?

The comment:
Comment 69: If it is built, B1 may be constructed at any point in the project’s construction phase. It is perched above the key transit entrance to the main entrance to the arena. What is the MPT [maintenance and protection of traffic] for the construction, what are its impacts? Please detail the construction of B1 and Site 5 over the course of the project’s development (Krashes, Brooklyn Speaks)
The response:
Response: B1 and Site 5 are elements of Phase I of the Project. Accordingly, as with the other Phase I elements of the Project, the SEIS analysis will take into account the effects of the construction and operation of these buildings as background conditions in assessing the environmental impacts of Phase II of the Project, and will account for the possibility that there may be an overlap between the construction of certain Phase I elements and the Phase II construction. To the extent that information regarding construction of these buildings is available and relevant to the analysis, such information will be taken into account and disclosed in the SEIS.
New impacts from the pad and other functions?

The comment:
Comment 139: The SEIS should assess whether there are any new land use, zoning, public policy, neighborhood character impacts not previously disclosed in the FEIS, and whether any additional or different mitigation measures would be required. This assessment should include the land use and neighborhood character impacts created by arena operations to the south of the arena on Dean Street like the pad, whose operations may be permanent but were not disclosed in the FEIS.
The SEIS should examine how use of this site for at-grade arena operations like security screening as well as truck and bus storage is consistent with the FEIS’ land use analysis which states B2 and B3 would serve as a "buffer" between the residences to the south of the arena and the arena itself, and that "security screening and loading functions would be entirely within the building." (FEIS p. 3-2). Other functions not studied in relation to their locations in the FEIS include the satellite uplink parking lot, LIRR operations, a trailer area in the B4 footprint and construction offices in 752 Pacific Street. The SEIS should detail and assess the interim locations of unanticipated project elements until the time they are placed below grade.
The SEIS should assess whether these unanticipated functions reduce opportunities for the project to implement the commitment in the MEC to provide publicly accessible interim open space in the event FCRC does not expect to commence construction of a particular portion of the Project site or to use such portion of the Project site for interim parking facilities or construction-related activities, including staging. (Brooklyn Speaks)
The response mostly ignored the request:
Response: The SEIS will assess opportunities for interim open space during the construction period for Phase II of the Project under the Extended Build-Out Scenario.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …

For Atlantic Yards Quality of Life meeting Sept. 19, another bare-bones agenda (green wall?)

A message from Empire State Development (ESD) reminds us that the next Atlantic Yards/Pacific Park Quality of Life Meeting--which aims to update community members on construction and other issues--will be held:
Tuesday, September 19, 2017 @ 6 pm
Shirley Chisholm State Office Building
55 Hanson Place
1st Floor Conference Room
Brooklyn, NY 11217 The typically bare-bones, agenda, below, tells us nothing about the content of the presentation. One thing to look for is any hint of plans to start a new building on the southeast block of the project by the end of the year.

If not, ESD is supposed to re-evaluate a longstanding request from project neighbors to move back a giant wall encroaching on part of Dean Street between Carlton and Vanderbilt avenues. It's said to enclose construction activity, but, in recent months, has significantly served to protect worker parking.

Also, by the way, if you search for Atlantic Yards on Google or the ESD website, it leads to this page for the Atlantic Ya…