According to the latest Site Observation Report, dated 5/1/12 and prepared by construction consultant Merritt & Harris on behalf of the arena bond trustee, Forest City Ratner, and Empire State Development, the Barclays Center arena is on schedule for substantial completion by 9/5/12--a date that was nudged back earlier this year--and a final completion by 6/30/13.
The associated transit connection is 3.5 months late beyond the 4/2/12 schedule,, but given that it doesn't need to open until the arena does, the slippage "will have no impact on the overall project schedule. "The slippage was dubiously attributed to "early delays." There were no such early delays.
Nor, actually, is either schedule completely credible, since, as I've reported, they revised the charts.
Schedule unclear
There's still a mystery. As noted in the screenshot below, the GMP2 [Guaranteed Maximum Price] executed 3/9/12 clarifies any "extension of the construction term" and "establishes the final completion date."
Merritt & Harris is still reviewing it. Note that the GMP2 was supposed to be issued before the end of 2011.
ASI Limited
Is everything back to normal with ASI Limited, the Indiana firm producing the pre-weathered lattice panels that shut down at the end of last year and reopened thanks to an insurer? The report hedges, suggesting efforts "intended to resolve the delays in the shop and field."
ASI is also performing various corrective work on the curtain wall.
A curious change order
The change order below suggests there will be food served from an arena-front retail outlet--could this be the Brooklyn Water Bagel Company?
Number of workers
There have been 520 workers at the arena and 62 at the transit connection, according to the report. That doesn't count workers at the separate railyard project.
The associated transit connection is 3.5 months late beyond the 4/2/12 schedule,, but given that it doesn't need to open until the arena does, the slippage "will have no impact on the overall project schedule. "The slippage was dubiously attributed to "early delays." There were no such early delays.
Nor, actually, is either schedule completely credible, since, as I've reported, they revised the charts.
Schedule unclear
There's still a mystery. As noted in the screenshot below, the GMP2 [Guaranteed Maximum Price] executed 3/9/12 clarifies any "extension of the construction term" and "establishes the final completion date."
Merritt & Harris is still reviewing it. Note that the GMP2 was supposed to be issued before the end of 2011.
ASI Limited
Is everything back to normal with ASI Limited, the Indiana firm producing the pre-weathered lattice panels that shut down at the end of last year and reopened thanks to an insurer? The report hedges, suggesting efforts "intended to resolve the delays in the shop and field."
ASI is also performing various corrective work on the curtain wall.
A curious change order
The change order below suggests there will be food served from an arena-front retail outlet--could this be the Brooklyn Water Bagel Company?
Number of workers
There have been 520 workers at the arena and 62 at the transit connection, according to the report. That doesn't count workers at the separate railyard project.
Comments
Post a Comment