Skip to main content

Transit connection to arena now said to be less delayed than was reported last month. How so? Construction monitor fudged the timetable.

Barclays Center bondholders take note: they moved the goalposts again regarding project construction. And while that may not make it less likely you'll get the interest you expect, it sure raises questions about the credibility of the reports you're getting.

Once a month, real estate consultant Merritt & Harris, the real estate consultant that "strives to be the leader in providing consistently excellent construction-related services to the real estate lending and investment community," issues a Site Observation Report report to the arena PILOT Bond Trustee (Bank of New York Mellon), Forest City Ratner, and the Empire State Development Corporation.

In the latest report is dated 4/2/12 and based on a visit of 2/23/12 and documents made available 3/20/12, Merritt and Harris began fudging the schedule for the new Transit Connection.

In other words, as with the arena, Merritt and Harris declared the Transit Connection less behind schedule than previously estimated, all because it extended the schedule, with no real explanation.

Transit connection

The text of the report contains some standard language:
The document seems to be updated elsewhere, since it provides a later date:

Note that the Construction Schedule did not slip because of "early delays." Such delays had no significant impact, because the transit connection was well ahead of schedule for many months, as the graphics below indicate.

But given that there is slack in the schedule--the arena will open in September--the delay should not be fatal.

Transit connection progress

If the Construction Schedule had slipped by about two months, it should be finished in June, right? That's what all previous graphs marking progress have noted, as indicated below. The graphs measure projected spending (the solid circle) vs. actual spending, with the percentage difference noted in the bottom row.

In last month's report, as indicated in the graphic below, as of October 2011, the transit connection was behind 0.35%. As of January 2012, the transit connection was behind 3.42%. (Click on graphics to expand.)

Merritt & Harris report, March 2012
But let's look at the April report, below. In that report, as of October 2011, the transit connection was ahead 4.36%, not behind 0.35%.

In the April report, as of January 2012, the transit connection was behind only 0.22%, not behind 3.42%.

Merritt & Harris report, April 2012

What's behind the recalculation? The secret is extending the timetable through an additional month, to July 2012. By extending the timetable, the spending is stretched out through another month.

Thus, the projected spending per month diminishes and, voila, the actual spending becomes more prominent. Thus the graph gets revised to make the project look more certain.

But that technique is not explained anywhere in the report.

Indeed, the graphic contradicts the text of the report, which nowhere suggests that the transit connection would be finished in July. And that date presumably would exceed the "approximately 2 months" the schedule is said to have slipped from the original target of 4/2/12.


Arena progress

The document states that the arena is still expected to be substantially complete by 9/5/12:

However, there's still no documentation on a final completion date. The report mentions a new GMP2 (Guaranteed Maximum Price) schedule to be issued in February that would establish the final completion date. As with many promised documents in the past, it has not emerged as scheduled.
The latest chart of arena construction, below, suggests that actual spending handily outpaces projected spending. But, as I pointed out in February, the chart accompanying the January report indicated that the arena had been slightly behind for three months.


How to fudge

The solution, in the reports beginning in February (and indicated above in the latest report), was to stretch out the timetable for the hard cost spending total of $485 million-plus, thus portraying current spending as outpacing the projected spending.

In the January report, as of the June 2013 final completion date, there was to be $485,012,000 spent, or 100% percent of the total.

In the February 2012 report, that timetable was relaxed. As of June 2013, there was to be $479,818,000 spent, or 98.88% of the total. The March 2012 report put the June 2013 total at $480,131,000, or 98.88% of the total. The latest report puts the June 2013 total at $480,186,000, or 98.88% of the total

Given the longer period to spend the total, each previous month has a target completion percentage lower than in the January chart, with less spending needed to keep pace. Oddly, unlike with the chart regarding the transit connection, there's no indication of when the 100% mark would be met.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

So, Forest City has some property subject to the future Gowanus rezoning

Writing yesterday, MAP: Who Owns All the Property Along the Gowanus Canal, DNAinfo's Leslie Albrecht lays out the positioning of various real estate players along the Gowanus Canal, a Superfund site:
As the city considers whether to rezone Gowanus and, perhaps, morph the gritty low-rise industrial area into a hot new neighborhood of residential towers (albeit at a fraction of the height of Manhattan's supertall buildings), DNAinfo reviewed property records along the canal to find out who stands to benefit most from the changes.
Investors have poured at least $440 million into buying land on the polluted waterway and more than a third of the properties have changed hands in the past decade, according to an examination of records for the nearly 130 properties along the 1.8-mile canal. While the single largest landowner is developer Property Markets Group, other landowners include Kushner Companies, Alloy Development, Two Trees, and Forest City New York.

Forest City's plans unc…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…