Skip to main content

Transit connection to arena now said to be less delayed than was reported last month. How so? Construction monitor fudged the timetable.

Barclays Center bondholders take note: they moved the goalposts again regarding project construction. And while that may not make it less likely you'll get the interest you expect, it sure raises questions about the credibility of the reports you're getting.

Once a month, real estate consultant Merritt & Harris, the real estate consultant that "strives to be the leader in providing consistently excellent construction-related services to the real estate lending and investment community," issues a Site Observation Report report to the arena PILOT Bond Trustee (Bank of New York Mellon), Forest City Ratner, and the Empire State Development Corporation.

In the latest report is dated 4/2/12 and based on a visit of 2/23/12 and documents made available 3/20/12, Merritt and Harris began fudging the schedule for the new Transit Connection.

In other words, as with the arena, Merritt and Harris declared the Transit Connection less behind schedule than previously estimated, all because it extended the schedule, with no real explanation.

Transit connection

The text of the report contains some standard language:
The document seems to be updated elsewhere, since it provides a later date:

Note that the Construction Schedule did not slip because of "early delays." Such delays had no significant impact, because the transit connection was well ahead of schedule for many months, as the graphics below indicate.

But given that there is slack in the schedule--the arena will open in September--the delay should not be fatal.

Transit connection progress

If the Construction Schedule had slipped by about two months, it should be finished in June, right? That's what all previous graphs marking progress have noted, as indicated below. The graphs measure projected spending (the solid circle) vs. actual spending, with the percentage difference noted in the bottom row.

In last month's report, as indicated in the graphic below, as of October 2011, the transit connection was behind 0.35%. As of January 2012, the transit connection was behind 3.42%. (Click on graphics to expand.)

Merritt & Harris report, March 2012
But let's look at the April report, below. In that report, as of October 2011, the transit connection was ahead 4.36%, not behind 0.35%.

In the April report, as of January 2012, the transit connection was behind only 0.22%, not behind 3.42%.

Merritt & Harris report, April 2012

What's behind the recalculation? The secret is extending the timetable through an additional month, to July 2012. By extending the timetable, the spending is stretched out through another month.

Thus, the projected spending per month diminishes and, voila, the actual spending becomes more prominent. Thus the graph gets revised to make the project look more certain.

But that technique is not explained anywhere in the report.

Indeed, the graphic contradicts the text of the report, which nowhere suggests that the transit connection would be finished in July. And that date presumably would exceed the "approximately 2 months" the schedule is said to have slipped from the original target of 4/2/12.


Arena progress

The document states that the arena is still expected to be substantially complete by 9/5/12:

However, there's still no documentation on a final completion date. The report mentions a new GMP2 (Guaranteed Maximum Price) schedule to be issued in February that would establish the final completion date. As with many promised documents in the past, it has not emerged as scheduled.
The latest chart of arena construction, below, suggests that actual spending handily outpaces projected spending. But, as I pointed out in February, the chart accompanying the January report indicated that the arena had been slightly behind for three months.


How to fudge

The solution, in the reports beginning in February (and indicated above in the latest report), was to stretch out the timetable for the hard cost spending total of $485 million-plus, thus portraying current spending as outpacing the projected spending.

In the January report, as of the June 2013 final completion date, there was to be $485,012,000 spent, or 100% percent of the total.

In the February 2012 report, that timetable was relaxed. As of June 2013, there was to be $479,818,000 spent, or 98.88% of the total. The March 2012 report put the June 2013 total at $480,131,000, or 98.88% of the total. The latest report puts the June 2013 total at $480,186,000, or 98.88% of the total

Given the longer period to spend the total, each previous month has a target completion percentage lower than in the January chart, with less spending needed to keep pace. Oddly, unlike with the chart regarding the transit connection, there's no indication of when the 100% mark would be met.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …

For Atlantic Yards Quality of Life meeting Sept. 19, another bare-bones agenda (green wall?)

A message from Empire State Development (ESD) reminds us that the next Atlantic Yards/Pacific Park Quality of Life Meeting--which aims to update community members on construction and other issues--will be held:
Tuesday, September 19, 2017 @ 6 pm
Shirley Chisholm State Office Building
55 Hanson Place
1st Floor Conference Room
Brooklyn, NY 11217 The typically bare-bones, agenda, below, tells us nothing about the content of the presentation. One thing to look for is any hint of plans to start a new building on the southeast block of the project by the end of the year.

If not, ESD is supposed to re-evaluate a longstanding request from project neighbors to move back a giant wall encroaching on part of Dean Street between Carlton and Vanderbilt avenues. It's said to enclose construction activity, but, in recent months, has significantly served to protect worker parking.

Also, by the way, if you search for Atlantic Yards on Google or the ESD website, it leads to this page for the Atlantic Ya…