Skip to main content

From the latest Construction Alert: "loud banging noises" predicted until 1 am over ten days; work to begin on broadcast parking lot, comfort station at Dean Playground

The latest two-week Atlantic Yards Construction Alert, dated 5/7/12 (and embedded below) and released yesterday by Empire State Development after preparation by Forest City Ratner, contains some warnings to neighbors near the site.

Notably, from 3:30pm – 1:00 am between May 10-20, residents should expect to hear "loud banging noises by dump trucks will occur as they empty their loads of stone in the east yard between Carlton and Vanderbilt Avenues."

Also, there will be additional demolition on the southeast block of the project site, Block 1129, in preparation for construction on the surface parking lot, which is to start May 15.

New broadcast parking lot, comfort station

A "vacant lot at the northeast corner of Dean Street and 6th Avenue that is currently being used as temporary NYPD parking will be improved for use as an at grade broadcast location for the Arena," according to the alert. Of course, the lot was dis-improved by being created out of, in part, two intact houses that were demolished. A Department of Buildings permit is expected within two weeks.

Also, "[a]s part of the construction impact mitigation requirements AYDC [Atlantic Yards Development Company] will construct a comfort station in the Dean Street Playground," including men’s and women’s rooms, a small maintenance storage room and perimeter paving and landscaping. A permit is expected within two weeks.

While such a comfort station was on the Parks department wish list, it is less a mitigation of the noise impacting the playground than an offset. Then again, Forest City Ratner agreed to spend $1.25 million after first offering only $20,000.

I've bolded the notable changes from the previous alert.

Arena site
Revisions to the perimeter construction fence are projected to continue this reporting period, in order to allow the site construction activity to ramp up. Adjustments will be made to the portion of the fence along Dean Street & 6th Avenue and Dean Street & Flatbush Avenue. A temporary sidewalk bridge will be placed on Flatbush Avenue east side during the erection of the main entry canopy. The permit has been secured for this work and the work is projected to start late during this reporting period.
Façade Installation
• The installation of curtain wall and curtain wall/lattice panels will continue on the Flatbush Avenue elevation as needed, and then following the canopy steel erection. In the interest of public safety, and as approved by the New York City Building Department, pedestrians using the east side sidewalk of Flatbush Avenue next to the arena may be temporarily diverted to across the street by Hunt flagmen during high level work outside the canopy zone. A sidewalk bridge is to be installed when the canopy steel & facade erection is adjacent to the pedestrian way. The façade erector will continue with installation of panels along the 6th Avenue and Dean Street elevations during this reporting period installing the low and mid level panels.
Waterproofing & Fireproofing
The waterproofing of the interior walls of the east and west stormwater retention tanks has been completed. The preparation for the testing of the tanks has begun. The testing is projected to start this reporting period.
Mechanical, Electrical, & Plumbing
• The installation of the truck elevator service turntable is substantially complete. Punch list and testing will continue this reporting period.• The installation of the arena bowl ribbon (video boards) will continue this reporting period. The main scoreboard hoist has been placed.
Interior buildout
• Seating installation will continue in the upper bowl this reporting period.
New Subway Entrance/Work outside the Fence
• Permits have been secured for the portions of the street immediately adjacent to the “Tip” of the project area. The southern eastbound lane of Atlantic Avenue continues to be taken behind an expanded MPT in order to facilitate the water main installation. This expanded MPT has been approved by DOT. The backfill over the main is now substantially complete.
Rail Yard Track Work
• From 3:30pm – 1:00am loud banging noises by dump trucks will occur as they empty their loads of stone in the east yard between Carlton and Vanderbilt Avenues. These truckload deliveries of stone are expected to occur from May 10th through May 20th.
Carlton Ave. Bridge
• MPT continues to be in place at Carlton Ave. and Pacific Street during this reporting period the contractor will continue to form and install rebar for the stem wall of the new South Abutment and place concrete as required. Noise attenuation blanketing is being utilized to cover a generator being used to cool the concrete during curing at the South Abutment.Construction of Pier #2 has been completed.
• The footing and the first level of the stem wall for the North Abutment have been completed. Work is to commence on Pier #1 during the next two weeks.
Replacement of Adjacent Water Mains and other Utility Work
• Catch basins at the corner of Pacific and 6th Avenue were modified. During the next two week period the finish castings will be installed. Roadway restoration will be scheduled and coordinated with LIRR drainage work and traffic mitigation roadway work in the area.
Block 1129
• During May and possibly into June, the west wall of 754 Pacific Street will be reinforced, sidewalk bridges will be removed and the fragments of a former building at 585 Dean Street will be demolished. • Construction of the Block 1129 parking lot is officially slated to start on May 15th. Initial operations will consist of clearing the site, demolition of the remaining structures on the site, and grading of the site down to the final subgrade elevation. This grading operation will include removal of abandoned foundations from previous buildings as needed and will include removing the soil from the site. All of the soil on the site has been sampled and tested and is classified as “historic fill”, which is a low-level contamination unsuitable for use in other sites but not needing special considerations for handling.
Traffic Mitigation Site Work
Atlantic Avenue Medians
Work was expected to begin in late April 2012 on the remaining traffic mitigation work but was postponed due to delays in the City water main work east of Carlton Avenue. The city’s work is expected to be complete by early June. Most of the traffic mitigation site work is made up of raised medians along Atlantic Avenue from Flatbush Avenue to Vanderbilt Avenue. OCMC is reviewing the scope and location of the medians and will determine whether the work shall be performed during limited daytime hours, which will prolong the construction period, or at night between 10 pm and 6 am. If the work is done at night, mobile light units will be used to illuminate the work area. The arena block, Carlton Avenue Bridge reconstruction and DDC utility work between Carlton and Vanderbilt Avenues also take lanes out of service. Therefore, the median work must be scheduled block by block to coordinate with the other work schedules and MPT configurations. Because the work is a few feet directly above the LIRR tunnel into Atlantic Terminal, the means and methods must be reviewed and approved by the LIRR.
Arena Site Work
The curb installation work and street light installation work has now substantially complete on Flatbush Avenue. This work will continue for the rest of the month of May. Upon completion of this work, curbs and sidewalks along Atlantic Avenue will then be installed.
[No, the above is not quite coherent]

Broadcast Lot – Block 1128
The vacant lot at the northeast corner of Dean Street and 6th Avenue that is currently being used as temporary NYPD parking will be improved for use as an at grade broadcast location for the Arena. The improvements include permeable asphalt paving, fencing with a decorative screen, lights which will be focused on the interior of the lot and pedestals for power and data connections. We have submitted an Alteration Type 2 application to the Department of Buildings and expect a permit within the two week period. The contractor will mobilize at the site, erect standard construction fencing and perimeter protection immediately upon receipt of the permit. The work is scheduled to be complete this fall.

Dean Street Playground Comfort Station
As part of the construction impact mitigation requirements AYDC will construct a comfort station in the Dean Street Playground near the eastern entrance to the park at Bergen Street between 6th and Carlton Avenues. The design, which includes men’s and women’s rooms, a small maintenance storage room and perimeter paving and landscaping, has been approved by the New York City Department of Parks and Recreation, Community Board and the New York City Public Design Commission. We have submitted a New Building application to the Department of Buildings and expect a permit within the two week period. The contractor will mobilize at the site, erect standard construction fencing and perimeter protection immediately upon receipt of the permit. The work is scheduled to be complete this fall.
Community Liaison Office
In the next two weeks the Community Liaison Office will be relocated to the existing building at 754 Pacific Street, due to construction on Block 1129. The CLO will continue to be open M-F from 9am – 4pm and the phone number, 866-923-5315 and email, communityliaison@atlanticyards.com will remain the same. Visitors will enter through the guard booth at the corner of Carlton Avenue and Pacific St.
AY Construction Alert 5-7-2012

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

Click on graphic to enlarge. This is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change, and the project is already well behind that tentative timetable.


Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…