Skip to main content

New report: for three months, arena has been (slightly) behind schedule; completion date for arena nudged back; site work could continue almost to Jay-Z concert date

Delays are taking their toll on Atlantic Yards construction, with new data from November indicating--for the first time--that the arena is now behind, and had been slightly behind for three months.

Apparently as a consequence, the substantial completion date of the arena has been pushed back a week to 8/30/12, and the substantial completion date of site work (landscaping, trees, sidewalks, bollards, etc.) pushed back a month to 9/25/12, just three days before Jay-Z is supposed to inaugurate the Barclays Center.

The information comes from the latest Site Observation Report, based on a visit of 11/22/11 and documents made available on 12/20/11, from Merritt & Harris, the real estate consultant to the arena PILOT Bond Trustee.

(The substantial completion date last April was nudged back two weeks from 8/12/12 to 8/27/12, but in October was nudged forward to 8/23/12.)

Cause for worry?

The report, dated 1/4/12, indicates that work seems to be proceeding appropriately. Confoundingly, it does not acknowledge in its text that the arena is behind, as a chart indicates.

Construction progress, based on cash flow, is behind 1.23%, a relatively small figure. However, given that the arena has long been ahead of schedule, that surely has provoked concern, as well as second shifts to get the work done.

Though the Barclays Center displays significant structural and exterior work, as of November, the arena was still only about half-finished, in terms of cash flow.

The Merritt & Harris report, dated 12/27/11, was completed before news surfaced of the shutdown of ASI Limited, the firm fabricating the custom panels for the arena exterior; the firm's owner left open the possibility of a reopening.

The report also acknowledges that the associated Transit Connection is a week late, though that project likely has much more leeway, given scheduled completion on 4/1/12.

And there are other indications of a slowdown. The Final Completion Date for the project, involving punch list work and subcontractor close-outs, was in the previous month's report indicated as 3/8/13; now, it could be extended nearly three months,  to 5/30/13.

Also, the latest report indicates the expectation of a GMP2 (Guaranteed Maximum Price 2), which both offers an early completion bonus (July 2012) and seemingly contemplates additional delays.
That report has apparently been issued but not made public.

Contradictory, confusing information

The Merritt & Harris report is contradictory and confusing in places. For example, the text of the document indicates that the arena is on schedule:

But that is contradicted by the chart and other data in the report. The highlighted part of the chart and the highlighted statistics (click to enlarge) indicate that actual cash flow has lagged estimated progress.

It's also the first time that Merritt & Harris has revealed any delays in arena construction (note the negative percentages on the bottom line).

The consultant did not explain in yesterday's report why delays had not been previously reported, but apparently there were errors in the chart accompanying the previous report (below), issued 12/2/11.

Note that both the chart and the statistics offered two separate notations for the month of September 2011 and that neither the September 2011 nor October 2011 statistics in the two charts match.

The Transit Connection

The Transit Connection has been behind for three months. The document at one point states:
The construction term of 20 months (August 2, 2010-April 1, 2012) is reasonable, but, due to early delays with approval of the test piles, had slipped by approximately 1 week.
At another point, it states:
The construction term of 20 months (August 2, 2010-April 1, 2012) is reasonable, but, due to early delays with approval of the test piles, had slipped by approximately 1 month.
Both are misleading, as I wrote two months ago: the "early delays with approval of the test piles" did not cause ongoing slippage in the Construction Schedule, since the project was able to return to schedule thanks to "excavation and demolition work."

After omitting the graphic regarding the Transit Connection last month, this month's report does contain such a graphic. It indicates that the Transit Connection is more than 78% done, in terms of cash flow, so it's in the home stretch. But it should be more than 85% done.


Finally checking on that Deficiency

In my 12/7/11 post, I noted that a section in the report headed Deficiency indicates, as in predecessor reports, that some concrete compression test results have been found to be deficient, but also leaves things murky, given that expected 56-day testing presumably was complete as of June 2011.

The latest report finally follows up, noting that a letter has been requested from the Structural Engineer.

ASI Limited

That chart below on subcontracts indicates that the contract with ASI Limited for the exterior facade, at $32.4 million, was considerably below the $39.2 million originally budgeted by the general contractor.

Did ASI Limited offer a low bid to get the work? If so, is that part of the firm's financial troubles? Both of those questions are speculative, as of now, but worth consideration.

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

So, Forest City has some property subject to the future Gowanus rezoning

Writing yesterday, MAP: Who Owns All the Property Along the Gowanus Canal, DNAinfo's Leslie Albrecht lays out the positioning of various real estate players along the Gowanus Canal, a Superfund site:
As the city considers whether to rezone Gowanus and, perhaps, morph the gritty low-rise industrial area into a hot new neighborhood of residential towers (albeit at a fraction of the height of Manhattan's supertall buildings), DNAinfo reviewed property records along the canal to find out who stands to benefit most from the changes.
Investors have poured at least $440 million into buying land on the polluted waterway and more than a third of the properties have changed hands in the past decade, according to an examination of records for the nearly 130 properties along the 1.8-mile canal. While the single largest landowner is developer Property Markets Group, other landowners include Kushner Companies, Alloy Development, Two Trees, and Forest City New York.

Forest City's plans unc…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…