Skip to main content

Barclays Center completion date pushed back a week, but arena "is slightly ahead of schedule." How so? They changed the schedule to erase delays.

Delays are taking their toll on Barclays Center construction, pointing to a hectic--and perhaps nerve-wracking--pace to the finish line.

Not only is the Carlton Avenue Bridge delayed, the substantial completion date for the arena has been nudged back one week for the second time in five weeks, to 9/5/12. That gives arena operators little more than three weeks to test building systems before the first event, a 9/28/12 concert with superstar Jay-Z.

Also, after a report in January indicated that the Barclays Center was behind schedule, a new report from the same construction monitor asserts that the arena is "slightly ahead of schedule," based on actual cash flow versus projected cash flow.

(The final completion date is 6/30/13, which indicates additional work will have to be done while the building is operating.)

Presto: the arena's ahead

Top chart from Feb. 2012
bottom from Jan. 2012
That happy conclusion, however depends on changing the schedule, a slight-of-pen unacknowledged in the latest Site Observation Report by Merritt & Harris, the real estate consultant to the arena PILOT Bond Trustee. (Dated 2/6/12, it's based on a visit of 12/22/11 and a documents review.)

Merritt & Harris chronicles construction progress via charts, like the ones at right. (Click on all graphics to enlarge.) The solid circles represent projected cash flow, while the hollow circles indicate actual money spent.

The top chart at right, taken from the February report, suggests that actual spending handily outpaces projected spending.

However, the chart accompanying the January report, in bottom at right, points to a convergence of the two trend lines. As I wrote 1/5/12, the data  indicated that the arena had been slightly behind for three months.

Changing the schedule

How to get around that problem? Change the schedule.

Top chart from Jan. 2012
bottom from Feb. 2012
By stretching out the timetable to meet the hard cost spending total of $485 million-plus, current spending can be portrayed as outpacing the projected spending.

Take a look at the graphic at left. In the top half, from the January 2012 Merritt & Harris report, as of the June 2013 final completion date, there would be $485,012,000 spent, or 100% percent of the total.

In the bottom half of the graphic, from the February 2012 report,as of the June 2013 final completion date, there would be $479,818,000 spent, or 98.88% of the total. Each previous month has a target completion percentage lower than in previous reports.

There's no indication of when 100% would be spent.

The bottom line

In the last three reports, Merritt & Harris has moved back the substantial completion date for the arena from 8/23/12 to 8/30/12 to 9/5/12.

(In last month's report, the firm, also moved back the completion date for site work around the arena to 9/25/12 from 8/29/12, but this month moves it up to 9/5/12.)

The overall construction schedule points to challenges in meeting the June 2013 final completion date. While that may set up snags in coordinating construction efforts with arena activities, the more lesson is this: these documents are tough to trust, as significant changes are presented with no acknowledgement or explanation.

Transit connection delayed

As noted in the screenshot at right, according to the Construction Progress Chart (below), based on cash flow, "the Arena is slightly ahead of schedule, while the Transit Connection is approximately 2 months behind schedule."

However, because there's some slack in the schedule--the Transit Connection isn't supposed to open until the arena does--the "additional 2 months will have no impact on the overall project schedule"

A new schedule to be issued this month is supposed to include all delays and establish the final completion date.

In the screenshots below, I've highlighted some figures on the chart, notably the percentage difference between actual and projected cash flows--percentages that have changed as the schedule was attenuated--as well as the percentage completion expected in the last few months of the project.

February 2012 report

January 2012 report




December 2011 report

November 2011 report


The transit connection

The report states that "due to early delays" the Construction Schedule slipped by approximately 2 months." 

That simply doesn't compute. The early delays had no significant impact, because the transit  connection was well ahead of schedule for many months. 

The project began, as the graphic below indicates, in August 2010, and didn't start to lose ground until July 2011.

When is substantial completion for the arena?

In April 2001, the substantial completion date was nudged back two weeks from 8/12/12 to 8/27/12, but in October 2011 was nudged forward to 8/23/12. That number stuck through December 2011.

As noted, in the past two reports the date has slipped by a week each month.

December 2011 report

Note the substantial completion date of 8/23/12 for the arena and 8/29/12 for the site work.



January 2012 report

Note the substantial completion date of 8/30/12 for the arena, a weeklong delay, and 9/25/12, nearly a monthlong delay, for the site work.


February 2012 report 

Note the substantial completion date of 9/5/12 for the arena, while that is now the date for the  site work, as well.



Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

This graphic, posted in November 2017, is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. Note the unbuilt B1 and the proposed shift in bulk to the unbuilt Site 5.

The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change. The project is already well behind that tentative timetable.

The previous graphic, from August 2017 (without the ghost B1)

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Not quite the pattern: Greenland selling development sites, not completed condos

Real Estate Weekly, reporting on trends in Chinese investment in New York City, on 11/18/15 quoted Jim Costello, a senior vice president at research firm Real Capital Analytics:
“They’re typically building high-end condos, build it and sell it. Capital return is in a few years. That’s something that is ingrained in the companies that have been coming here because that’s how they’ve grown in the last 35 years. It’s always been a development game for them. So they’re just repeating their business model here,” he said. When I read that last November, I didn't think it necessarily applied to Atlantic Yards/Pacific Park, now 70% owned (outside of the Barclays Center and B2 modular apartment tower), by the Greenland Group, owned significantly by the Shanghai government.
A majority of the buildings will be rentals, some 100% market, some 100% affordable, and several--the last several built--are supposed to be 50% market/50% subsidized. (See tentative timetable below.)

Selling development …