Skip to main content

From the latest Construction Alert: some milestones nudged back; possibility for Atlantic Avenue median work to be done during the day, rather than at night

The latest two-week Atlantic Yards Construction Alert, dated 1/2/12, was distributed yesterday by Empire State Development (after preparation by developer Forest City Ratner).

As I noted yesterday, there was no mention of the shutdown of the arena facade contractor, or any prediction of how that might affect facade work.

While there's continued progress in several areas, there are some issues to point out:
  • work on raised medians along Atlantic Avenue may be performed during daylight hours, as opposed to previous plans to do so only at night (other night work has been noisy)
  • completion of bollard placement has been nudged back from December to January 
  • some railyard drilling work has been nudged back a month
  • some water main work has been nudged back a few weeks
  • one Flatbush Avenue sidewalk may be temporarily impassible

The text below is excerpted from the latest document (bottom), with the bolded text indicating what's new compared to the previous alert.

Construction at the Arena Site
Both of the two larger steel erection cranes inside the arena have been demobilized and replaced by a hydraulic crane in the Bowl.

Façade Installation
• The façade erector will continue the installation of erection clips and panels on the Flatbush Avenue and along the west elevations during this reporting period. The installation of curtain wall and curtain wall/lattice panels will continue on the Flatbush Avenue elevation during this reporting period. In the interest of public safety, and as approved by the New York City Building Department, pedestrians using the east side sidewalk of Flatbush Avenue next to the arena may be temporarily diverted to across the street by Hunt flagmen during high level work. The façade erector will continue with installation of erection clips along the 6th Avenue elevation this reporting period. Installation of the erection clips will continue on the Dean Street elevation during this reporting period.

Mechanical, Electrical, & Plumbing
• The piping for the storm/sanitary/water services from the street mains to the arena at 6th and Pacific has been cancelled for this reporting period, due to site constraints ((access at the main gate). This work will take place in March 2012. A second and/or third shift as well as weekend work is being considered to execute this work prior to March 2012.
(It doesn't make sense to have the work take place both in and prior to March.)

Interior Build-out
• Precast concrete stadia erection of the upper seating bowl was completed during the last reporting period at Blocks 10-12 (Dean Street elevation). Precast erection will resume within the lower bowl seating area following completion of roof erection. The placement of concrete column wraps will continue during this reporting period.
The gypsum wallboard (GWB) aka drywall framing & construction subcontractor will continue layout of walls during this reporting period and will begin placement of the top wall track and partition walls at all levels. Steel stud placement for partition walls will continue during this reporting period. The wallboard installation will continue on the Event Level, on Main Concourse, and on Lower Suite Level this reporting period.

Subway entrance: work outside the Fence
• Work on the northern and southern vent shafts along Flatbush Avenue is now substantially complete.

Steel Erection
• Steel erection of the above ground entrance canopy is now complete and the deck installation is substantially completed. The concrete structural roof slab has now been placed.

Railyard: Drilling – Support of Excavation, & Tiebacks
Some remaining drilling of tiebacks in the east and middle yard will continue. This tieback drilling and placement of the attendant wood lagging will continue for the next month, as they go together the remaining with excavation.

Drainage System
• Posillico/Tully is working from west to east to install deep drainage piping in the yard. They will also continue excavation for the associated stormwater manholes. This work will be ongoing for the next 3 months. Through this period, Retention Basins “A” and “B” have been completed and back-filled. Work will now move further east to Basins “C” and “D”.

Carlton Ave. Bridge
• Formwork for the footing of Pier #2 has been placed in a prepared excavation in the mid-yard. Rebar will be placed during this reporting period prior to pouring the Pier #2 footing in January.

East End (former Gasoline Station)
• Posillico/Tully will continue working on the lagging and tieback work at this location and continue to lower the grade there. SOE Pile-drilling in this area below grade is complete although caisson piles will be drilled in early February [previously: January] after the yard has been lowered. The excavation and associated support work will be on-going for the next couple of months.

Replacement of Adjacent Water Mains and other Utility Work
Stage One began in early August. The first work included the installation of a distribution water main along the sidewalk of Flatbush, north of Atlantic. The work is being done at night (10 pm to 6 am) and requires partial closure of the sidewalk and the curb lane of traffic during the work hours. The work will take two to three months in this location and then will move on southward and cross Flatbush. The bus stop at the west side of Flatbush, north of Pacific, has been removed by NYC DOT, per the approval of NYCTA. The trench for most of the work in the Flatbush sidewalk is completed and plated. The contractor will continue for the next month [previously: next 3 to 4 weeks]. Steel pipe was installed, welded and partially backfilled along the northern part of the zone.

Traffic Mitigation Site Work:Atlantic Avenue Medians
Work will begin late 1st quarter or early 2nd quarter 2012 on the remaining traffic mitigation work, most of which is made up of raised medians along Atlantic Avenue from Flatbush Avenue to Vanderbilt Avenue. OCMC is reviewing the scope and location of the medians and will determine whether the work shall be performed during limited daytime, which will prolong the construction period, or at night between 10 pm and 6 am. If the work is done at night, mobile light units will be used to illuminate the work area. The arena block, Carlton Avenue Bridge reconstruction and DDC utility work between Carlton and Vanderbilt Avenues also take lanes out of service. Therefore, the median work must be scheduled block by block to coordinate with the other work schedules and MPT configurations. Because the work is a few feet directly above the LIRR tunnel into Atlantic Terminal, the means and methods must be reviewed and approved by the LIRR.
(Previously, day work was not considered, but night work at Atlantic and Flatbush avenue caused huge concerns in October because of excessive noise.)

Arena Site Work
The revised Flatbush Avenue MPT is allowing work to continue on the installation of the Flatbush Avenue façade and the installation of bollards along this same stretch. Part of the overall site work for the arena block, bollard installation, commenced at the intersection of Dean and Flatbush in the area of the southern vents and is continuing north along Flatbush, eventually continuing around the entire block. The bollard work is anticipated to be complete by the middle of January [previously: middle of December]. Other work that will be done as part of the site work includes sidewalks, installation of pavers, street furniture, street trees, light and signal poles, way finding signage, hydrants and the canopy to the new subway entrance. Additional detail on the work will be provided as the contractor progresses.
Anticipated Nighttime & Weekend Work
During this reporting period the following work will be performed either at night or during the weekend as noted. All work will be done pursuant to approved permits:
• Long Island Rail Road/Vanderbilt Yard/ Carlton Avenue Bridge:
o All weekdays all locations in the yard: 6:00AM to 11:00PM
o Saturdays as required: 7:00 AM to 11:00 PM
o Sundays and Holidays as required: 8:00AM to 11:00PM
o The weekend work being performed could be in any area of the yard, and within MPT areas for which permits are on hand.
o The work hours will remain in place for a minimum of the next three months.
• Arena Site:
o Arena weekend work will be scheduled no later than close of business on the preceding Thursday, where make-up work due to weather or other delays makes it necessary. Saturday work is expected to continue for this reporting period.
o Subject to receipt of permits, a second shift shall be continued throughout this reporting period, from 3 – 11 PM, Monday-Friday only. Also subject to receipt of permits, a third shift may be instituted during this reporting period, from 11 PM – 7 AM, Monday –Friday only.
o Hunt has been granted a permit to allow for deliveries from 6 AM to 7 AM to the Arena site from the dispatch center. This work allows for an additional hour of deliveries to take place outside the neighborhood peak traffic patterns and reduce congestion and interference with the local traffic.
o The second shift arena contractors are noted within the arena summary above.
• NYC Transit Improvements:
o Temporary concrete road decking will now be removed as noted above. Such work will be performed at night per DOT regulations. Traffic will be restored every morning according to DOT stipulations.
Work related to the BMT structure and below grade concrete, steel and MEP work may be conducted on Saturdays January 7th and 14th during this reporting period.
• Arena Site Work:
o Underground utility work may occur within the site at the main plaza. Work will be conducted during the hours of 8 A.M. to 4 P.M., subject to NYCDOB permits.
• Block 1129 – staging area:
o Contractors conducting night work may have cause to enter and exit this area as it serves as a staging and material/equipment storage area.

Atlantic Yards Construction Alert 1-2-2012





Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

So, Forest City has some property subject to the future Gowanus rezoning

Writing yesterday, MAP: Who Owns All the Property Along the Gowanus Canal, DNAinfo's Leslie Albrecht lays out the positioning of various real estate players along the Gowanus Canal, a Superfund site:
As the city considers whether to rezone Gowanus and, perhaps, morph the gritty low-rise industrial area into a hot new neighborhood of residential towers (albeit at a fraction of the height of Manhattan's supertall buildings), DNAinfo reviewed property records along the canal to find out who stands to benefit most from the changes.
Investors have poured at least $440 million into buying land on the polluted waterway and more than a third of the properties have changed hands in the past decade, according to an examination of records for the nearly 130 properties along the 1.8-mile canal. While the single largest landowner is developer Property Markets Group, other landowners include Kushner Companies, Alloy Development, Two Trees, and Forest City New York.

Forest City's plans unc…

At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

And sales in China may help explain how the developer was able to claim early momentum.
"Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…