After bombshell about delays: What's new schedule? Affordable housing by 2025? Tower reconfiguration?

The evidence for Atlantic Yards/Pacific Park delays has been glaring, as the headlines at right from this blog indicate.

But not until last Thursday did Forest City Realty Trust, in a press release, announce that "the company, as part of a formal strategic plan update, made the decision to revise the overall project schedule to delay future vertical development."

That raised some significant lingering questions, only a few of which were touched on during the conference call the next day with investment analysts.

But they need to be answered, and the Nov. 14 meeting of the Atlantic Yards Community Development Corporation (AY CDC), the body set up to advise Empire State Development (the state authority overseeing/shepherding the project), should offer an opportunity.

Project timing: when is it finished?

As I wrote, Forest City CEO David LaRue did not reveal the new schedule. But surely the development team--Greenland Forest City Partners--has a new schedule (or schedules) and they should share it.

Company CFO Bob O'Brien said in the conference call that the firm's financial model "extends to 2035, 20 years from now."  That doesn't necessarily mean a completion date by 2035, but it does suggest that the project won't be done by 2025, the time by which the affordable housing is supposed to be completed.

The 2035 date may represent stabilization of income, but presumably that's no more than five years--maybe less--after which the project should be finished. That suggests delays in fighting the "blight" of the open railyard and delivering the much-promoted "open space," which the developers call a "park" (not really).

(Remember, the 2035 date was the shocking "outside date" agreed to in a 2009 project revision, which in 2014 was dialed back to 2025 for the affordable housing.)

Note in below map significant delays: for example, the two unbuilt sites on the southeast block, B12 and B13, should be under way, but aren't, and are rather for sale, as is B4.

My October 2016 annotation of 2014 tentative schedule
Affordable housing deadline

As I asked Friday, what happens to the June 2014 agreement, reached by New York State and some community community negotiators, to guarantee--with penalties--the 2,250 units of affordable housing by May 2025, "subject to extensions set forth in the Development Agreement and the General Project Plan"?

None of the investment analysts asked about this affordable housing commitment and, perhaps because of that, the issue didn't make into any of the mainstream coverage (Cleveland Plain Dealer, The Real Deal).

On Twitter, Gib Veconi, who in 2014 on behalf of BrooklynSpeaks helped negotiate the 2025 affordable housing deadline (after the project was given an "outside date" of 2035, a 25-year buildout), seemed reasonably confident that penalties will enforce the 2025 date.

So I have my doubts, given the pattern of this project.

One way, perhaps, to meet that 2025 deadline is to build more "100% affordable" rental buildings. Note that, in the original plan, all the rental buildings were to be 50% market, 50% subsidized--though that's actually 50/30/20, given the breakdown of moderate- and middle-income units, as well as low-income units.

Now we have two "100% affordable" rental buildings, which in turn will be matched by "100% market" rental buildings. That deviation from the more egalitarian model was justified as delivering affordable housing sooner.

That justification might be heard again, and result in buildings with distinctly different profiles: a project divided mostly into market-rate and affordable buildings.


What about the railyard?

The new Vanderbilt Yard to store and service Long Island Rail Road trains was supposed to be finished by December 2017. Now it looks to be 2018, according to O'Brien's remarks last Friday.

It's worth finding out when in 2018 the completion is projected.

Other questions

As I wrote, several other questions remain:
  • will covering the railyard for vertical construction be delayed? And doesn't that prolong blight?
  • how much tension is this causing between Forest City and its Shanghai-based partner?
  • beyond the three sites already up for sale/new investment, how much more might be sold?
  • will the developers seek more subsidies, or relaxed terms regarding the affordable housing?
Indeed, it was fascinating to hear Forest City use language that left the impression this was a unilateral decision, and to hear the investment analysts fail to press regarding Greenland's role.

Greenland surely had to concur with such decisions, but surely is not happy with a project it once claimed could be built out in eight years.

There are larger retrospective questions, of course, about what went wrong--a series of factors, I'd say--which likely will surface for analysis shortly.

How things might get better/worse for developers

Atlantic Yards, as I've said, is a "never say never" project, and there are multiple ways the scenario might change. Here are a few speculations:
  • a new 421-a law makes building apartments more attractive, and starts the timetable again
  • additional subsidies, or relaxed terms, make the affordable units more profitable
  • an approval to move bulk from the B1 site at the arena prow to Site 5 across Flatbush Avenue unlocks a huge new project
  • new investors inject capital into the project
  • Forest City and Greenland clash (and sue each other?) and/or buy each other out (and then sell to others)
  • the deck over the railyard gets delayed 

Another tentative timetable showing delay

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

Click on graphic to enlarge. This is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change, and the project is already well behind that tentative timetable.


Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…