How can three B2 modules be stored on site overnight? The limit should be one.

Forest City Ratner presentation
In November 2011, we were told by Forest City Ratner that, in construction of the B2 modular tower, "1 module will be delivered at night and stored on site overnight."

So how could three modules have been stored on site today, a non-work day, on a long truck in the work zone that stretches into Dean Street behind a green construction fence?

(Note that Saturday work on the building is ongoing. Were any modules taken down from the structure?)

Surely the mods will have spent a few nights on site.