Skip to main content

Featured Post

Atlantic Yards/Pacific Park infographics: what's built/what's coming/what's missing, who's responsible, + project FAQ/timeline (pinned post)

Steel truss installation on Barclays Center green roof planned for Saturday

Empire State Development yesterday circulated an alert that work on the Barclays Center green roof will take place on Saturday from 7 am through 3:30 pm, involving the installation of a truss--part of the framework for supporting the roof turf.
Arena Green Roof:
On Saturday, March 28, 2015, T2 Truss installation will take place. Similar with weekday work, lifts will take place from both the Dean Street and Atlantic Avenue crane locations; there will be no steel deliveries. Work will be taking place during the hours 7 AM to 3:30 PM pursuant to the Department of Buildings weekend work permit.


Comments