DDDB, allies aim to reopen case based on Development Agreement that gives Forest City 25 years to complete AY; ESDC claims those provisions trumped

Pointing to the curious delay by the Empire State Development Corporation (ESDC) in releasing the Atlantic Yards Development Agreement until after a key January 19 oral argument in the case challenging the ESDC's 2009 approval of the project, Develop Don't Destroy Brooklyn (DDDB) and 19 community groups have asked that the case be reopened.

The Development Agreement, as I've written, gives developer Forest City Ratner 12 years to build Phase 1 and 25 years to build Phase 2. Meanwhile. the ESDC maintained the project would take a decade, a finding to which Supreme Court Justice Marcy Friedman reluctantly deferred in her March 10 ruling dismissing the case.

"ESDC's continuing use of the 10 year build-out was supported—albeit, in this court’s opinion, only minimally—by the factors articulated by ESDC," she wrote, with one of those factors being the ESDC's professed intention to ensure that Forest City Ratner used "commercially reasonable" efforts to finish the project in a decade.

However, wrote DDDB attorney Jeff Baker in an affirmation filed today:
As set forth below, ESDC did not obtain a commitment from FCR to use commercially reasonable efforts to complete the project by 2019 and in fact signed an agreement that extends the completion of project until at least 2035. Thus, where the Court previously found that ESDC’s rational [basis] was only “minimally” supported, since one of the essential elements is demonstrably false, the Court should reconsider its decision in light of the new evidence.
"We think the Court will recognize that the ESDC's argument, and therefore the ruling, was egregiously incomplete, lacking the essential document that worked against their entire rationale that the project would take ten years. Reconsideration of the case is necessary because of the self-contradicting and revealing information ESDC intentionally held back from the Court and the public," said Develop Don't Destroy Brooklyn legal director Candace Carponter.

Bad faith

The petitioners might have gone even farther, charging bad faith. Remember, the Development Agreement, signed December 23, 2009, was not released until January 25, about three weeks after ESDC spokeswoman Elizabeth Mitchell told me the documents would be made available.

ESDC response and defense

Mitchell told the Brooklyn Paper that the agency will oppose the motion and expects to prevail.

Still, the ESDC has offered a rather weak defense of the timeline discrepancy in a motion to dismiss the only extant case, which challenges the failure to issue a new Determination & Findings:
Their allegations... [of delay] are inconsistent with the plain terms of the Development Agreement, which requires that the Project be constructed in accordance with the 2009 MGPP. See Development Agreement at pp. 4-5 (“Project Description”); p. 10 (requiring that the 2009 MGPP requirements be satisfied); p. 4 (requiring that FCRC use commercially reasonable efforts to complete the entire Project by 2019); p. 21 (requiring that the Project “shall have not less than the required Project Site Affordable Housing Units,” a term defined at page 15 of Appendix A to mean the 2,250 affordable housing unit required by the 2009 MGPP).
In a Memorandum of Law, the ESDC stated:
The Development Agreement expressly provides that the deadlines and periods set forth in Article VIII, which covers Construction Activities, “shall not modify, limit or otherwise impair” FCRC’s obligation under Section 2.2 of the agreement to use commercially reasonable efforts to substantially complete the Project by December 31, 2019, which is in full accord with the MGPP.
However, wrote Baker in the document filed today:
This Court relied on ESDC’s representations regarding its assurance that it will require commercially reasonable efforts to require FCRC to complete the project by 2019. However, while that term is used in a general provision of the Development Agreement, the more specific requirements of Articles 8 and 17 of the Agreement control over the vague provision of Sec. 2.2.
(Emphasis in original. See documents embedded below.)

Baker noted that “commercially reasonable” appears in only one place, and is not defined. Meanwhile, the Project Effective Date--the time when properties are delivered--is no earlier than this year, which means the Outside Phase II Substantial Completion Date would be 2035.

More on the Development Agreement

There is no date by which construction of Phase II must actually commence, writes Baker. He apparently missed the provision that does require the commencement of one building on the southeast block, Block 1129, to be begin within a decade after the Effective Date.

Beyond that, he points out that the document requires the Atlantic Yards Development Corporation to begin construction--or cause it to begin--of the platform no later than the 15th anniversary of the Project Effective Date.

However, as he notes, Section 8.5 "does not actually require commencement of construction" since all that's required is a completion guarantee and plans for construction:
Thus, even under this section, all that is required is a Development Lease, plans, and a completion guarantee for the first building on Phase II. There is nothing that even specifies when the construction of the platform must actually commence, when that first building must commence construction and when the balance of the platform must be constructed. Nor is there any requirement that FCRC actually proceed with the acquisition of the air rights over the Vanderbilt Yards.
Beyond that, the developer, according to Section 8.6 must complete Phase I within 12 years of the Project Effective Date—or 2022 at the earliest.

And, while Article 17 provides for Events of Default and Liquidated Damages, "none of the relevant defaults pertaining to Phase II are subject to liquidated damages," which means ESDC could terminate the agreement, with no penalties for the developer beyond losing the development rights.

What's commercially reasonable?

Baker observes:
“Commercially reasonable efforts” is in itself a largely meaningless term. The Development Agreement makes it clear that ESDC defines “commercially reasonable efforts” as meaning not 2019, but in realty 2035 at the earliest and even that date is largely devoid of any penalties or incentives.
Thus, the ESDC's plan to alleviate blight, a precursor to the use of eminent domain, is illusory, and thus the ESDC failed "to consider the effect of the significantly delayed plan or the possibility that it would not be completed when it made its findings under the [Urban Development Corporation Act]."

Atlantic Yards Development Agreement Section 2.3
Atlantic Yards Development Agreement Section 8
Atlantic Yards Development Agreement 17.2

Comments

Popular posts from this blog

Barclays Center/Levy Restaurants hit with suit charging discrimination on disability, race; supervisors said to use vicious slurs, pursue retaliation

The Daily News has an article today, Barclays Center hit with $5M suit claiming discrimination against disabled, while the New York Post headlined its article Barclays Center sued over taunting disabled employees.

While that's part of the lawsuit, more prominent are claims of racial discrimination and retaliation, with black employees claiming repeated abuse by white supervisors, preferential treatment toward Hispanic colleagues, and retaliation in response to complaints.

Two individual supervisors, for example, are charged with  referring to black employees as “black motherfucker,” “dumb black bitch,” “black monkey,” “piece of shit” and “nigger.”

Two have referred to an employee blind in one eye as “cyclops,” and “the one-eyed guy,” and an employee with a nose disorder as “the nose guy.”

There's been no official response yet though arena spokesman Barry Baum told the Daily News they, but take “allegations of this kind very seriously” and have "a zero tolerance policy for…

Behind the "empty railyards": 40 years of ATURA, Baruch's plan, and the city's diffidence

To supporters of Forest City Ratner's Atlantic Yards project, it's a long-awaited plan for long-overlooked land. "The Atlantic Yards area has been available for any developer in America for over 100 years,” declared Borough President Marty Markowitz at a 5/26/05 City Council hearing.

Charles Gargano, chairman of the Empire State Development Corporation, mused on 11/15/05 to WNYC's Brian Lehrer, “Isn’t it interesting that these railyards have sat for decades and decades and decades, and no one has done a thing about them.” Forest City Ratner spokesman Joe DePlasco, in a 12/19/04 New York Times article ("In a War of Words, One Has the Power to Wound") described the railyards as "an empty scar dividing the community."

But why exactly has the Metropolitan Transportation Authority’s Vanderbilt Yard never been developed? Do public officials have some responsibility?

At a hearing yesterday of the Brooklyn Borough Board Atlantic Yards Committee, Kate Suisma…

No, security guards can't ban photos. Questions remain about visibility of ID/sticker system.

The bi-monthly Atlantic Yards/Pacific Park Community Update meeting June 14, held at 55 Hanson Place, addressed multiple issues, including delays in the project, a new detente with project neighbors,concerns about traffic congestion, upcoming sewer work and demolitions, and an explanation of how high winds caused debris to fly off the under-construction 38 Sixth Avenue building. I'll have more coverage.
Security issues came up several times at the meeting.
Wayne Bailey, a resident who regularly takes photos and videos (that I often use) of construction/operations issues that impact residents, asked representatives of Tishman Construction if the security guard at the sites they're building works for them.
After Tishman Senior VP Eric Reid said yes, Bailey asked why a guard told him not to shoot video of the site, even though he was on a public street.

"I will address it with principals for that security firm," Reid said.
Forest City Ratner executive Ashley Cotton, the …

Barclays Center event June 11 to protest plans to expand Israeli draft; questions about logistics

At right is a photo of a poster spotted in Hasidic Williamsburg right. Clearly there's an event scheduled at the Barclays Center aimed at the Haredi Jewish community (strict Orthodox Jews who reject secular culture), but the lack of English text makes it cryptic.

The website Matzav.com explains, Protest Against Israeli Draft of Bnei Yeshiva Rescheduled for Barclays Center:
A large asifa to protest the drafting of bnei yeshiva in Eretz Yisroel into the Israeli army that had been set to take place this month will instead be held on Sunday, 17 Sivan/June 11, at the Barclays Center in Downtown Brooklyn, NY. So attendees at a big gathering will protest an apparent change of policy that will make it much more difficult for traditional Orthodox Jewish students--both Hasidic (who follow a rebbe) and non-Hasidic (who don't)--to get deferments from the draft. Comments on the Yeshiva World website explain some of the debate.

The logistical questions

What's unclear is how large the ev…

Atlantic Yards/Pacific Park graphic: what's built/what might be coming (post-dated pinned post)

Click on graphic to enlarge. This is post-dated to stay at the top of the blog. It will be updated as announced configurations change and buildings launch. The August 2014 tentative configurations proposed by developer Greenland Forest City Partners will change, and the project is already well behind that tentative timetable.


Atlanta's Atlantic Yards moves ahead

First mentioned in April, the Atlantic Yards project in Atlanta is moving ahead--and has the potential to nudge Atlantic Yards in Brooklyn further down in Google searches.

According to a 5/30/17 press release, Hines and Invesco Real Estate Announce T3 West Midtown and Atlantic Yards:
Hines, the international real estate firm, and Invesco Real Estate, a global real estate investment manager, today announced a joint venture on behalf of one of Invesco Real Estate’s institutional clients to develop two progressive office projects in Atlanta totalling 700,000 square feet. T3 West Midtown will be a 200,000-square-foot heavy timber office development and Atlantic Yards will consist of 500,000 square feet of progressive office space in two buildings. Both projects are located on sites within Atlantic Station in the flourishing Midtown submarket.
Hines will work with Hartshorne Plunkard Architecture (HPA) as the design architect for both T3 West Midtown and Atlantic Yards. DLR Group will be t…

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…