Skip to main content

From the latest Atlantic Yards/Pacific Park Construction Alert: module deliveries on hold; changes at B3 site for Green Roof work (less bike parking)

Two weeks after Greenland Forest City Partners renamed Atlantic Yards as Pacific Park, Empire State Development, which sends out two-week Construction updates after preparation by Forest City Ratner, had made an adjustment.

The email yesterday had the subject line "Atlantic Yards dba PACIFIC PARK BROOKLYN TWO WEEK LOOK AHEAD," and came with a note about the "ongoing effort to update you on the activities surrounding the Atlantic Yards Project (dba Pacific Park Brooklyn)." But it also was addressed to "the Atlantic Yards Community," so they're still working on the nomenclature.

At B2

Notably, no more modules were delivered to the B2 modular tower in the past two weeks, leaving a total of 297 (of 930), with the tenth floor complete. Erection of 11th floor modules will begin in September 2014.

During these two weeks, mechanical, plumbing and electrical mate line work will continue at the building, as will "exterior punch list." That typically refers to final fixes, but note that some of the module faces, flapping in the wind, seem to have arrived with flaws.

Also, water main tie-in work on Flatbush Avenue at night should begin. It unclear how/whether traffic would be affected.

Green roof work (and less bicycle parking)

Coming soon to the B3 site, at the southeast corner of the arena block, will be trailers used in connection with the Green Roof.

Also, an area within that B3 footprint "will be fenced in for storage of equipment and materials used in connection with work going on inside the building." That is related to the green roof but I thought the work was all exterior.

Also, they've begun removing the bike racks, which once were able to accommodate 400 bikes (though hardly used but occasionally hyped) "to make way for the upcoming crane installation, which is slated for October." Instead, "racks to accommodate approximate 45 bikes will be installed in the plaza on 6th Avenue.

Note that this is a departure from the 2009 Amended Memorandum of Environmental Commitments (and the 2014 Second Amended Memorandum), which requires the developer to "provide any ticketholder traveling to the arena by bicycle with free indoor bicycle storage in a secure, manned facility designed to accommodate at least 400 bicycles on the arena block."

LIRR rail yard activities

Pile drilling along the north side of Pacific Street will continue during this reporting period and should take about four months, according to the alert. The contractor will continue excavation and hauling of soil from Blocks 1120 and 1121.

The contractor will continue installation of tiebacks, lagging, excavation of soil and demolition of the lower portion of the concrete retaining wall along Pacific Street, between Carlton and Vanderbilt avenues. The contractor has begun grading/paving work in the area of the yard between the Arena and 6th Avenue.

Community Liaison Office (CLO)

According to the document:
The Community Liaison Office has been relocated to Atlantic Center, 625 Atlantic Avenue. Located on the 3rd floor, visitors seeking the office should enter through the mall entrance located at the corner of Atlantic Avenue and So. Portland Avenue. The CLO’s hours are M-F from 9am – 4pm and the phone number, 866-923-5315 and email, communityliaison@atlanticyards.com remains the same.
That probably needs an update, since Forest City has already sent out emails indicating a new address: communityliaison@pacificparkbrooklyn.com.

Comments

  1. Anonymous8:41 AM

    Have we addressed the error directly with the head of outreach at ESD, Marion Phillips? One Atlantic Yards neighbor had an amusing phone calls to ESD and around and around they went.

    ReplyDelete
    Replies
    1. No, but I presume they read this and will adjust.

      If you have something to report, please feel free to email me directly with details. (Email at top of this page)

      Delete

Post a Comment

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.