Skip to main content

From the latest Atlantic Yards Construction Alert: pace of modules increases, to 246 of 930

According to the latest two-week Atlantic Yards Construction Alert (below), dated and distributed July 21 by Empire State Development after preparation by Forest City Ratner, there were some 57 modules delivered to the B2 modular tower in a two-week period, far more than 24 in the previous two weeks and even 48 in the period before that.

The total is now about 246 of 930 modules. [UPDATED] Should a pace of 50 every two weeks be maintained--which depends on the factory--the modules could be delivered in just 28 weeks. There's surely additional work after that, but it's possible the building could be finished much closer to its previous December 2014 completion date rather than a year later.

Also, work promised in the previous alert--such as constriction of Atlantic Avenue and Pacific Street for construction activities--has begun or is expected to begin.

Below are some verbatim excerpts from the report.

B-2 Tower, Modular Residential



  • Erection of 9th floor is complete and the 10th module erection will follow during this reporting period. During this same period mechanical, plumbing and electrical mate line work will continue. 



  • Masonry and spray on fireproofing on the 1st floor are completed. Exterior and interior wall framing will begin during this reporting period. 



  • Hoist is operational and will continue to be jumped up the building during this reporting period. 



  • Work related to the perimeter framing for the metal panels on the 1st floor and Dean Street entrance will continue during this reporting period.


  • LIRR Yard Activities - Block 1120 & 1121 


  • Pacific Street between 6th Avenue and Carlton Avenue has been converted to one-way only (westerly traffic flow) and MPT has been installed along the north side of Pacific Street in order to allow for pile drilling preparations in this area. Work will include support of excavation (SOE) work including the installation of soldier piles, lagging and tiebacks.



  • During this reporting period, the contractor will prepare the area inside of the Pacific Street MPT for drilling. This work includes sidewalk removal, grading, and relocation of light poles.



  • Pile drilling along the north side of Pacific Street is scheduled to begin during this reporting period and is expected to take approximately 4 months to complete. During this time period the north sidewalk will be closed. Once pile drilling is complete, the MPT will be shifted further north allowing two-way traffic to be returned on Pacific Street; however the north sidewalk in the area of the work will remain closed for ongoing SOE installations. The MPT will remain in this location with this portion the north sidewalk closed for approximately 8 months. Noise blankets will be installed on the chain link fence around the work area. Compressors will be located below grade in the LIRR yard.



  • During this reporting period, demolition of the existing concrete site access ramp will begin at the west end of Block 1120 just east of 6th Avenue. Construction access to the yard will be shifted to the earthen ramp located on Pacific Street just east of Carlton Avenue, which will be completed during this reporting period.



  • During this reporting period, the Contractor will begin excavation and hauling of soil from Blocks 1120 and 1121. Soil that has been classified as clean, contaminated or hazardous will be removed from the site as part of the excavation activities and brought to appropriate disposal locations.



  • Contractor will continue installation of tiebacks, lagging, excavation of soil and demolition of the lower portion of the concrete retaining wall along Pacific Street, between Carlton and Vanderbilt Avenues during this reporting period.



  • All work shall be done during daytime hours pursuant to approved DOT permits; while not expected, if required, any nighttime or weekend work would be pursuant to proper permits and advance notification will be given to the community.



  • Particulate monitoring will continue during these activities and soil will be kept damp as needed.


  • LIRR Yard Activities – Atlantic Avenue



  • During this reporting period, installation of Maintenance and Protection of Traffic (MPT) work on Atlantic Ave, between Fort Greene Place and South Cumberland Street will commence. MPT installations, which will include removal of existing concrete medians (starting at Fort Greene Place and proceeding east), placing MPT barriers and shifting/altering of traffic lanes (3 westbound lanes and 2 eastbound lanes will be maintained throughout the term of the MPT installation), will allow for construction of the LIRR West Portal along the south side of Atlantic Avenue. MPT installations along Atlantic Avenue will be modified as work progresses. This work will be ongoing and MPT will be in place along Atlantic Avenue for approximately 24 months. Transportation Enforcement Agents (TEAs) will be in place, as outlined in the DOT permit stipulations.



  • This MPT installation and striping is being done at night per DOT permit stipulations and is expected to take 2 nights to complete.



  • With the MPT is in place, the Contractor will begin work to remove the Atlantic Avenue concrete median. This work will be done during daytime hours. Equipment used during the course of this work may include hoe rams and/or jackhammers. A noise shroud (noise blanket) will be placed around any hoe ram that may be used. Quieter make/model jackhammers as described in DEP noise code will be used if such are required.


  • How to Reach Our Community Liaison Office (CLO)



  • The Community Liaison Office is located at 752 Pacific Street. The CLO’s hours are M-F from 9am–4pm and the phone number, 866-923-5315 and email, communityliaison@atlanticyards.com will remain the same. Visitors seeking the office should enter through the guard booth at the corner of Carlton Avenue and Pacific Street.

  • Comments

    Popular posts from this blog

    Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

    Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

    Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

    The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

    While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
    if market-rate construction is delayed, will the affordable h…

    Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

    The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

    The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

    The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

    According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

    But official…

    At 550 Vanderbilt, big chunk of apartments pitched to Chinese buyers as "international units"

    One key to sales at the 550 Vanderbilt condo is the connection to China, thanks to Shanghai-based developer Greenland Holdings.

    It's the parent of Greenland USA, which as part of Greenland Forest City Partners owns 70% of Pacific Park (except 461 Dean and the arena).

    And sales in China may help explain how the developer was able to claim early momentum.
    "Since 550 Vanderbilt launched pre-sales in June [2015], more than 80 residences have gone into contract, representing over 30% of the building’s 278 total residences," the developer said in a 9/25/15 press release announcing the opening of a sales gallery in Brooklyn. "The strong response from the marketplace indicates the high level of demand for well-designed new luxury homes in Brooklyn..."

    Maybe. Or maybe it just meant a decent initial pipeline to Chinese buyers.

    As lawyer Jay Neveloff, who represents Forest City, told the Real Deal in 2015, a project involving a Chinese firm "creates a huge market for…

    Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

    The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

    That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

    The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

    That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

    Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

    Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

    On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

    Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
    Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

    Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

    Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

    And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

    But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
    The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…