Skip to main content

From the latest Construction Alert: Forest City now starting work on B2 tower at 5:30 am, rather than 7 am (timetable pressure?)

Forest City Ratner may be feeling pressure to get the first Atlantic Yards tower done on schedule, given that the developer is starting work on the B2 tower this week on some days at 5:30 am rather than the official city start time of 7 am. (Normal construction hours are 7 am to 6 pm weekdays.)

The new timetable was revealed quietly in the bi-weekly Construction Alert (bottom) issued yesterday by Empire State Development, the state agency overseeing/enabling Atlantic Yards, after preparation by Forest City:
• Construction Activities are scheduled to start as early 5:30 am Monday through Friday. Work will include, first concrete pump set up, a quiet activity, followed later by pouring of concrete, while the installation of reinforcement steel for walls and associated formwork takes place, along with, general clean up. This earlier work day schedule would apply only on days that concrete pours are to occur.
If this occurs only on days of concrete pours, this should be every two to three days, as noted below.

Trying to follow up

Though the alert states, "If you have any questions please feel free to contact ESD’s Manager, Atlantic Yards Project Community/Government Relations," that seems like a rather empty assurance. I sent a few questions to Derek Lynch:
The paragraph suggests the concrete pump sets up at 5:30 and is a quiet activity.

It implies that pouring of concrete and installation of reinforcement steel, etc. happens later and is less quiet. Approximately when? And how should it be characterized: "less quiet," non-quiet, etc?
I was trying to figure out whether the activities not characterized as "quiet" would begin before 7 am. My query went unanswered.

25 trucks two or three times a week

The document explains that concrete pours will occur every two or three days:
• Begin pouring concrete foundation walls. This activity will be take place approximately every 2-3 days during the reporting period. The day of the pour there will be 25 concrete trucks delivery to the site during the course of the day. A separate logistics plan has been submitted and approved by the OEM for this work.
In other words, there will be 25 trucks two or three times a week. The last alert did not specify a frequency, leaving the impression that the "day of the pour" referred to a single pour.

Saturday and late night hours
• Construction Activities are scheduled for upcoming Saturdays. Work hours will be 7am till 6pm and work will include, installing reinforcement steel for foundation walls, formwork and general clean up. Work hours may be extended up to as late as 11 pm Monday through Friday. Construction activities will be limited to installing rebar in the foundation walls.
The previous construction alert also said that work hours "may be extended" until 11 pm, but neither state whether permission has been granted.

Update: the photo at right shows the work permit for Saturday, at least.

Dean Street Playground Comfort Station

The new comfort station--constructed by Forest City as partial mitigation for increased neighborhood noise--near the eastern entrance to the park at Bergen Street between 6th and Carlton Avenues has been inspected, and a temporary certificate of occupancy is expected to be issued "as soon as paperwork is processed by the DOB."

FCRC has transitioned the property to the NYC Department of Parks & Recreation.

LIRR Yard Activities and continued vibrations

The document states:
• Excavation/hauling of soil, installation of lagging and retaining wall removal have begun. Contractor is using a hoe ram with sound deadening wrapped around it to conduct this work. This work will continue for the next several months.
In the last alert, the "sound deadening" aspect of the hoe ram was not mentioned.

Note that complaints continue regarding the impact of railyard construction on residences across the street. Yesterday, a Newswalk resident reported, "Vibrations are shaking apartment walls."

Comments

Popular posts from this blog

Forest City acknowledges unspecified delays in Pacific Park, cites $300 million "impairment" in project value; what about affordable housing pledge?

Updated Monday Nov. 7 am: Note follow-up coverage of stock price drop and investor conference call and pending questions.

Pacific Park Brooklyn is seriously delayed, Forest City Realty Trust said yesterday in a news release, which further acknowledged that the project has caused a $300 million impairment, or write-down of the asset, as the expected revenues no longer exceed the carrying cost.

The Cleveland-based developer, parent of Brooklyn-based Forest City Ratner, which is a 30% investor in Pacific Park along with 70% partner/overseer Greenland USA, blamed the "significant impairment" on an oversupply of market-rate apartments, the uncertain fate of the 421-a tax break, and a continued increase in construction costs.

While the delay essentially confirms the obvious, given that two major buildings have not launched despite plans to do so, it raises significant questions about the future of the project, including:
if market-rate construction is delayed, will the affordable h…

Revising official figures, new report reveals Nets averaged just 11,622 home fans last season, Islanders drew 11,200 (and have option to leave in 2018)

The Brooklyn Nets drew an average of only 11,622 fans per home game in their most recent (and lousy) season, more than 23% below the announced official attendance figure, and little more than 65% of the Barclays Center's capacity.

The New York Islanders also drew some 19.4% below announced attendance, or 11,200 fans per home game.

The surprising numbers were disclosed in a consultant's report attached to the Preliminary Official Statement for the refinancing of some $462 million in tax-exempt bonds for the Barclays Center (plus another $20 million in taxable bonds). The refinancing should lower costs to Mikhail Prokhorov, owner of the arena operating company, by and average of $3.4 million a year through 2044 in paying off arena construction.

According to official figures, the Brooklyn Nets attendance averaged 17,187 in the debut season, 2012-13, 17,251 in 2013-14, 17,037 in 2014-15, and 15,125 in the most recent season, 2015-16. For hoops, the arena holds 17,732.

But official…

Is Barclays Center dumping the Islanders, or are they renegotiating? Evidence varies (bond doc, cash receipts); NHL attendance biggest variable

The Internet has been abuzz since Bloomberg's Scott Soshnick reported 1/30/17, using an overly conclusory headline, that Brooklyn’s Barclays Center Is Dumping the Islanders.

That would end an unusual arrangement in which the arena agrees to pay the team a fixed sum (minus certain expenses), in exchange for keeping tickets, suite, and sponsorship revenue.

The arena would earn more without the hockey team, according to Bloomberg, which cited “a financial projection shared with potential investors showed the Islanders won’t contribute any revenue after the 2018-19 season--a clear signal that the team won’t play there, the people said."

That "signal," however, is hardly definitive, as are the media leaks about a prospective new arena in Queens, as shown in the screenshot below from Newsday. Both sides are surely pushing for advantage, if not bluffing.

Consider: the arena and the Islanders can't even formally begin their opt-out talks until after this season. The disc…

Skanska says it "expected to assemble a properly designed modular building, not engage in an iterative R&D experiment"

On 12/10/16, I noted that FastCo.Design's Prefab's Moment of Reckoning article dialed back the gush on the 461 Dean modular tower compared to the publication's previous coverage.

Still, I noted that the article relied on developer Forest City Ratner and architect SHoP to put the best possible spin on what was clearly a failure. From the article: At the project's outset, it took the factory (managed by Skanska at the time) two to three weeks to build a module. By the end, under FCRC's management, the builders cut that down to six days. "The project took a little longer than expected and cost a little bit more than expected because we started the project with the wrong contractor," [Forest City's Adam] Greene says.Skanska jabs back
Well, Forest City's estranged partner Skanska later weighed in--not sure whether they weren't asked or just missed a deadline--and their article was updated 12/13/16. Here's Skanska's statement, which shows th…

Not just logistics: bypassing Brooklyn for DNC 2016 also saved on optics (role of Russian oligarch, Shanghai government)

Surely the logistical challenges of holding a national presidential nominating convention in Brooklyn were the main (and stated) reasons for the Democratic National Committee's choice of Philadelphia.

And, as I wrote in NY Slant, the huge security cordon in Philadelphia would have been impossible in Brooklyn.

But consider also the optics. As I wrote in my 1/21/15 op-ed in the Times arguing that the choice of Brooklyn was a bad idea:
The arena also raises ethically sticky questions for the Democrats. While the Barclays Center is owned primarily by Forest City Ratner, 45 percent of it is owned by the Russian billionaire Mikhail D. Prokhorov (who also owns 80 percent of the Brooklyn Nets). Mr. Prokhorov has a necessarily cordial relationship with Russia’s president, Vladimir V. Putin — though he has been critical of Mr. Putin in the past, last year, at the Russian president’s request, he tried to transfer ownership of the Nets to one of his Moscow-based companies. An oligarch-owned a…

Former ESDC CEO Lago returns to NYC to head City Planning Commission

Carl Weisbrod, Mayor Bill de Blasio's City Planning Commission Chairman and Director of the Department of City Planning, is resigning,

And he's being replaced by Marisa Lago, currently a federal official, but who Atlantic Yards-ologists remember as the short-term Empire State Development Corporation CEO who, in an impolitic but candid 2009 statement, acknowledged that the project would take "decades."

Still, Lago not long after that played the good soldier at a May 2009 Senate oversight hearing, justifying changes in the project but claiming the public benefits remained the same.

By returning to City Planning, Lago will join former ESDC General Counsel Anita Laremont, who after retiring from the state (and taking a pension) got the job with the city.

Back at planning

Lago, a lawyer, in 1983 began work as an aide to City Planning Chairman Herb Sturz, and later served as the General Counsel to the president of the NYC Economic Development Corporation, Weisbrod himself.